DLD project no. 2266Completed
Mohammed Bin Rashid Al Maktoum City District One, B Villas مدينة محمد بن راشد آل مكتوم - الحي الأول ب فلل Completed 30 June 2024 (DLD) · DLD end date Jun 2024 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.
CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 27 February 2025 | 100% | DLD inspection |
| 25 November 2024 | 93.4% | DLD inspection |
| 12 October 2023 | 40% | DLD inspection |
| 18 July 2023 | 30.8% | DLD inspection |
| 28 March 2023 | 20% | DLD inspection |
| 13 December 2022 | 4.9% | DLD inspection |
| 14 September 2022 | 0.2% | DLD inspection |
| 5 August 2022 | 0% | DLD register, archived export |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
Building permits
3 of 161 buildingsBuildings on the project’s plots: 161, on construction permits: 161, as Dubai Municipality lists them.
Furthest stage reached: Completed.
| Work stage | Buildings |
|---|---|
| Finishes | 152 |
| Final works | 6 |
| Completed | 3 |
Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.
DLD registration
DLD services ↗Homes: villas 161.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: 161 Residential Luxury Villas (G+1) Villas, the project designed to have a concrete structure and block with internal and external finishes.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
No off-plan sales are registered for this project since 2020, so there is no launch price.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Mortgage registrations
Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.
| Quarter | Mortgage registrations |
|---|---|
| 2024-Q1 | 0 |
| 2024-Q2 | 0 |
| 2024-Q3 | 0 |
| 2024-Q4 | 0 |
| 2025-Q1 | 0 |
| 2025-Q2 | 4 |
| 2025-Q3 | 7 · registered amount AED 90.4M |
| 2025-Q4 | 9 · registered amount AED 136.8M |
| 2026-Q1 | 6 · registered amount AED 78.2M |
| 2026-Q2 | 4 |
| 2026-Q3 | 6 · registered amount AED 77.8M |
| 2026-Q4 | 6 · registered amount AED 47.3M |
Mortgage registrations on homes per quarter. Source: DLD.
Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 22; registered amount AED 232.8M.
Since the first registration in 2025-Q2: 42 in all.
Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
LocationAl Merkadh · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 10, with 972 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2025 | 2 | 53 |
| 2027 | 3 | 555 |
| 2028 | 4 | 216 |
| 2029 | 1 | 148 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Al Merkadh: 17
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Sobha Creek Vista Heights | 91.5% | — | 2,076 | 224 |
| Azizi Riviera Reve | 76.6% | Feb 2025 | — | 144 |
| Azizi Riviera 50 | 60.9% | Mar 2027 | 2,294 | 79 |
| Azizi Riviera 68 | 74.6% | May 2027 | 1,971 | 79 |
| Azizi Riviera 49 | 54.4% | Mar 2027 | 2,316 | 75 |
| The Highbury | 80% | — | 2,196 | 69 |
| Azizi Riviera 66 | 91% | May 2027 | 1,352 | 41 |
| ِِAzizi Riviera 60 | 97.1% | Mar 2027 | 2,125 | 40 |
| Naya at District One | 68.5% | Sep 2027 | 2,106 | 33 |
| Casa Serene | 74% | Dec 2024 | — | 2 |
| Project 3532, Al Merkadh | 0% | Sep 2025 | — | 0 |
| Azizi Riviera 53 | 63.2% | Mar 2027 | — | 0 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data District One - FZ · DLD developer no. 956
Completed a month or more after their DLD end date: 0 of 36 completed projects with both dates. In 35 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Mohammed Bin Rashid AL Maktoum City -District -1 Community
DLD lists 34 projects in the master project Mohammed Bin Rashid AL Maktoum City -District -1 Community.
Questions about Mohammed Bin Rashid Al Maktoum City District One, B Villas
When was Mohammed Bin Rashid Al Maktoum City District One, B Villas completed?
Mohammed Bin Rashid Al Maktoum City District One, B Villas is recorded as completed on 30 June 2024 (DLD register of 1 November 2026).
Who is the developer of Mohammed Bin Rashid Al Maktoum City District One, B Villas?
District One - FZ, as registered with DLD.
What is the DLD project number of Mohammed Bin Rashid Al Maktoum City District One, B Villas?
2266.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error