Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2237Completed31 units

Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 17 مدينة محمد بن راشد آل مكتوم الحي الأول ، المرحلة الثالثة ، ريسيدنز 17 Al Merkadh · Mohammed Bin Rashid AL Maktoum City -District -1 Community by District One - FZAll phases of Mohammed Bin Rashid AL Maktoum City -District -1 Community Completed 30 December 2022 (DLD) DLD end date Dec 2022 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Dec 2022
DLD end date Dec 2022
Build time
19 months
Jun 2021 → Dec 2022
Latest sales
—
Fewer than 5 recent sales
1 BR rent
85,000 AED/yr
9 leases, 12 months
Developer
38 projects
36 completed · 1,752 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 31 May 2023 (inspections: 5).
Every DLD inspection and every change in the register %, newest first
Date % built Source
31 May 2023 100% DLD inspection
5 January 2023 90.2% DLD inspection
5 October 2022 61% DLD inspection
22 June 2022 33% DLD inspection
16 December 2021 3.6% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
19 monthsActual build
19 months
Start date
1 June 2021
DLD end date
30 December 2022
Completion date
30 December 2022
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Finishes.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Closed
357755
Issued
1 February 2021
Work start
7 November 2021
Completion
4 January 2023
Consultant · contractor
AE SEVEN MORSE ARCHITECTURE & ENGINEERING CONSULTANCIES CO L.L.C · BHATIA GENERAL CONTRACTING CO.(L.L.C.)
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Finishes1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
2237
Escrow agent
Dubai Islamic Bank (Public Joint Stock Company)
Zoning authority
Dubai Municipality
Master project
Mohammed Bin Rashid AL Maktoum City -District -1 Community
DLD area
Al Merkadh
Units · villas
31 · 0
Start → DLD end
Jun 2021 → Dec 2022
Registered units1 bed 26 · 2 bed 5; sizes 778–832 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Residential building (basement + ground + 4 floors + roof)

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 home sales after the launch window in the last 12 months, so no comparison is shown.

Dubai Statistics Center residential price index (flats), 2022-Q4 to 2026-Q2: +24%.

Prices are over apartments, the type most sales in this project are.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2022-Q4 → 2023-Q1

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Merkadh, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
1 BR AED 85,000 9 -15%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

No mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4).

Since the first registration in 2024-Q2: 31 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

No registered sales in the 12 months to 5 November 2026; the newest 10 before that
DateMarketType Size (sqft) Price (AED) AED/sqft
24 January 2023off-planApartment · 1 BR 831 1,485,000 1,787
2 January 2023off-planApartment · 2 BR 1,382 2,685,000 1,943
21 December 2022off-planApartment · 2 BR 1,382 2,685,000 1,943
21 December 2022off-planApartment · 2 BR 1,382 2,685,000 1,943
21 December 2022off-planApartment · 2 BR 1,382 2,685,000 1,943
21 December 2022off-planApartment · 1 BR 1,586 2,485,000 1,567
21 December 2022off-planApartment · 1 BR 782 1,485,000 1,899
21 December 2022off-planApartment · 1 BR 767 1,485,000 1,936
21 December 2022off-planApartment · 1 BR 782 1,485,000 1,899
21 December 2022off-planApartment · 1 BR 769 1,485,000 1,931

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Merkadh · Dubai Municipality community

Park · 310 mFair Mart · 580 mGrand Fresh · 690 mPark · 1.1 kmPolo Residence Park · 1.1 kmSpinneys · 1.1 kmBeach · 1.3 kmBeach · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationBusiness Bay Metro Station · Red Metro line · 4.5 km
MallSobha Mall (Under Construction) · 2.9 km
SupermarketFair Mart · 580 m
HospitalBIOS CLINIC · 3.7 km
SchoolDubai International School · 2.6 km
ParkPark · 310 m
BeachBeach · 1.3 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 15, with 1,700 units and villas.

2025: 532026: 412027: 1,2192028: 2162029: 171

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Merkadh: 17

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Sobha Creek Vista Heights 91.5% — 2,076 224
Azizi Riviera Reve 76.6% Feb 2025 — 144
Azizi Riviera 50 60.9% Mar 2027 2,294 79
Azizi Riviera 68 74.6% May 2027 1,971 79
Azizi Riviera 49 54.4% Mar 2027 2,316 75
The Highbury 80% — 2,196 69
Azizi Riviera 66 91% May 2027 1,352 41
ِِAzizi Riviera 60 97.1% Mar 2027 2,125 40
Naya at District One 68.5% Sep 2027 2,106 33
Casa Serene 74% Dec 2024 — 2
Project 3532, Al Merkadh 0% Sep 2025 — 0
Azizi Riviera 53 63.2% Mar 2027 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Merkadh

Developer in DLD data District One - FZ · DLD developer no. 956

Projects registered
38
36 completed · 1 under construction · 1 not started
Units delivered
1,752
456 in the pipeline
Median build time
26 months
completed projects measured: 36
Past the DLD end date
0
of 1 under construction with a DLD end date

Completed a month or more after their DLD end date: 0 of 36 completed projects with both dates. In 35 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Questions about Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 17

When was Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 17 completed?

Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 17 is recorded as completed on 30 December 2022 (DLD register of 1 November 2026).

Who is the developer of Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 17?

District One - FZ, as registered with DLD.

What is the DLD project number of Mohammed Bin Rashid Al Maktoum City , District One Phase III , Residences 17?

2237.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error