Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 1867Completed138 units

Al Haseen Residence الحسين رسيدانس Saih Shuaib 2 by Dugasta Properties Development L.L.C Completed 30 April 2020 (DLD) DLD end date Apr 2020 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Lake and French Village buildings at Riverland, Dubai Parks and Resorts, Saih Shuaib, Dubai
Area photo: Saih Shuaib 2, not this project Photo: Aleksandr SerebrennikovCC BY 4.0
Completed
Apr 2020
DLD end date Apr 2020
Build time
36 months
May 2017 → Apr 2020
Latest sales
—
Fewer than 5 recent sales
1 BR rent
50,000 AED/yr
19 leases, 12 months
Developer
8 projects
2 completed · 231 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 11 May 2020 (inspections: 10).
Every DLD inspection and every change in the register %, newest first
Date % built Source
11 May 2020 100% DLD inspection
3 February 2020 95.6% DLD inspection
19 September 2019 90.4% DLD inspection
21 May 2019 80% DLD inspection
31 January 2019 70.2% DLD inspection
23 October 2018 56.2% DLD inspection
18 July 2018 50.7% DLD inspection
15 April 2018 36% DLD inspection
9 January 2018 21.6% DLD inspection
4 October 2017 13.7% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
36 monthsActual build
36 months
Start date
1 May 2017
DLD end date
30 April 2020
Completion date
30 April 2020
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Finishes.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Closed
178554
Issued
22 February 2017
Work start
26 March 2017
Completion
17 February 2020
Consultant · contractor
EMSQUARE ENGINEERING CONSULTANTS · HEILBRONN CONTRACTING (L.L.C)
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Finishes1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
1867
Escrow agent
Mashreq Bank PSC
Zoning authority
Dubai Development Authority (DDA)
DLD area
Saih Shuaib 2
Units · villas
138 · 0
Start → DLD end
May 2017 → Apr 2020
Registered unitsStudio 42 · 1 bed 60 · 2 bed 36; sizes 521–876 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: PROJECT CONSISTS OF G+6+2R RESIDENTIAL BUILDING LOCATED IN SAIH SHUAIB 2. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 sales with a size were registered in the first 90 days, so no launch price is shown.

Prices are over apartments, the type most sales in this project are.

Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 5 — —
1 BR 6 — —

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q3 → 2026-Q3

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Saih Shuaib 2, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 38,400 10 +9.7%
1 BR AED 50,000 19 +11.1%
2 BR AED 65,000 11 +18.2%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 3; the amount shows from 5 registrations.

Since the first registration in 2024-Q2: 5 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 3 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
7 September 2026readyApartment · 1 BR 730 766,280 1,050
13 July 2026readyApartment · 1 BR 730 766,280 1,050
28 January 2026readyApartment · 1 BR 752 1,013,859 1,348
25 August 2025readyApartment · Studio 408 450,000 1,103
11 August 2025readyApartment · Studio 509 585,994 1,151
7 July 2025readyApartment · 2 BR 955 1,312,946 1,375
16 April 2025readyApartment · Studio 547 766,276 1,401
3 February 2025readyApartment · Studio 547 731,520 1,337
2 January 2025readyApartment · 2 BR 886 1,192,050 1,345
17 December 2024readyApartment · 1 BR 757 832,843 1,100

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationSaih Shuaib 2 · Dubai Municipality community

Project location© OpenStreetMap contributors · Dubai Municipality · Makani
Project location

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallThe Outlet Village · 5.6 km
HospitalShifa International Hospitals DWC · 7.9 km

Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 19, with 3,596 units and villas.

2026: 2482027: 7732028: 1,7222029: 853

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Saih Shuaib 2: 23

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Samana Hills South 12.1% May 2028 1,455 512
Al Haseen Residence 4 11.8% Dec 2026 1,470 155
Al Haseen Residence 3 10.1% May 2027 1,480 148
Samana Hills South 3 4.6% Aug 2028 1,389 145
Samana Hills South 2 5.3% Aug 2028 1,696 130
Samana South Haven 0% Dec 2028 — 123
South Lofts by Premier Choice 0% Jan 2029 1,360 103
Elanora by zoya 0% Mar 2028 1,327 56
South Park Residences By Wellington 96.8% Dec 2027 980 25
Coventry Curve 0% Jun 2028 1,099 23
Coventry Residence 3 0% Dec 2027 1,317 18
Samana South Haven 2 0% Jun 2029 — 14

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Saih Shuaib 2

Developer in DLD data Dugasta Properties Development L.L.C · DLD developer no. 1157

Projects registered
8
2 completed · 6 under construction · 0 not started
Units delivered
231
1,272 in the pipeline
Past the DLD end date
0
of 6 under construction with a DLD end date

Completed a month or more after their DLD end date: 1 of 2 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Questions about Al Haseen Residence

When was Al Haseen Residence completed?

Al Haseen Residence is recorded as completed on 30 April 2020 (DLD register of 1 November 2026).

Who is the developer of Al Haseen Residence?

Dugasta Properties Development L.L.C, as registered with DLD.

What is the DLD project number of Al Haseen Residence?

1867.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error