Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2834Completed93 units

MOONSA Residences مساكن مونسا Warsan Fourth · International City Phase 3 by Dugasta Properties Development L.L.CAll phases of International City Phase 3 Completed 30 October 2026 (DLD) DLD end date Aug 2025 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Oct 2026
DLD end date Aug 2025
Build time
34 months
Jan 2024 → Oct 2026
Latest sales
1,318 AED/sqft
13 sales
Developer
8 projects
2 completed · 231 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

1 November 2026
Built
100%
Latest DLD register reading: 100% built on 1 November 2026 (register readings: 3). Latest DLD inspection: 100% built on 28 October 2026 (inspections: 5).
Every DLD inspection and every change in the register %, newest first
Date % built Source
1 November 2026 100% DLD register
28 October 2026 100% DLD inspection
28 October 2026 95% DLD register
31 March 2026 95% DLD inspection
29 September 2025 66.2% DLD inspection
22 January 2025 50.2% DLD inspection
12 May 2024 25% DLD register, archived export
4 January 2024 25.1% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
20 monthsActual build
34 months
Start date
2 January 2024
DLD end date
25 August 2025
Completion date
30 October 2026
Completion vs DLD end date
14 months after

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

1 Nov 2026DLD status: Under construction → Completed. Completion date: none → 30 October 2026. Construction completed: 95% → 100%.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
2834
Escrow agent
Mashreq Bank PSC
Zoning authority
Trakhees
Master project
International City Phase 3
DLD area
Warsan Fourth
Units · villas
93 · 0
Start → DLD end
Jan 2024 → Aug 2025
Registered unitsStudio 40 · 1 bed 25 · 2 bed 24 · 3 bed 4; sizes 354–828 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: B + G + 1 + 2-6 Typ +7 + Roof Residential Building.The project designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft
Launch price
1,347 AED/sqft
Median of 7 off-plan sales in the 90 days from the first one (Jul 2024)
Latest registered sales
1,318 AED/sqft
Median of 13 home sales in the last 12 months, ready and off-plan

Dubai Statistics Center residential price index (flats), 2024-Q3 to 2026-Q2: +7.1%.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
Studio 1,380 (5) 1,315 (7) -4.7%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 31 1,315 (7) Nov 2025 – Nov 2026
1 BR 23 — —
2 BR 21 — —

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2024-Q3 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Warsan Fourth, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
13.3 AED/sqft a year
International City: median of 33 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 13 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
19 October 2026off-planApartment · 2 BR 828 1,177,754 1,422
23 September 2026off-planApartment · 1 BR 840 1,198,330 1,427
5 June 2026off-planApartment · 1 BR 840 1,176,000 1,400
22 April 2026off-planApartment · Studio 357 439,560 1,231
14 January 2026off-planApartment · Studio 349 423,672 1,214
5 January 2026off-planApartment · 2 BR 1,428 1,999,522 1,400
5 January 2026off-planApartment · 2 BR 828 1,117,584 1,350
5 January 2026off-planApartment · Studio 349 460,798 1,320
5 January 2026off-planApartment · Studio 349 460,096 1,318
5 January 2026off-planApartment · Studio 349 460,096 1,318

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationWarsan Fourth · Dubai Municipality community

Galaxy Market · 310 mShaklan Hypermarket · 640 mChoice Supermarket · 740 mPark · 1.2 kmPark · 1.3 kmPark · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationRashidiya Metro Station · Red Metro line · 9.3 km
MallQ1 Mall · 2.5 km
SupermarketGalaxy Market · 310 m
HospitalFakeeh University Hospital · 3 km
School宿舍 · 1.8 km
ParkPark · 1.2 km
BeachBeach · 2.1 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 39, with 4,213 units and villas.

2025: 3842026: 6352027: 8372028: 1,4992029: 858

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Warsan Fourth: 38

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Greenfield by Samana Developers 1.5% Oct 2028 1,384 299
Zenith Residences 24.1% Mar 2028 1,061 121
Mayflower Residences 96.1% Mar 2026 935 99
Moonsa Residences 2 1% Dec 2026 1,550 99
Tavora Residences By Jhk Heights Real Estate Development 86.2% Dec 2026 1,073 95
08 Life Residences 64.9% May 2026 1,017 91
Equiti Tower 70.2% Aug 2025 1,078 88
Nest 0.8% Apr 2027 1,044 74
Chapter 01 By Newbury Developments 2.4% Oct 2028 1,151 69
Elevia Residences 9.2% Jun 2027 1,351 67
The Maiden Residence 73% Dec 2025 1,016 41
Greenfield 2 by Samana Developers 0% Aug 2029 — 41

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Warsan Fourth

Developer in DLD data Dugasta Properties Development L.L.C · DLD developer no. 1157

Projects registered
8
2 completed · 6 under construction · 0 not started
Units delivered
231
1,272 in the pipeline
Past the DLD end date
0
of 6 under construction with a DLD end date

Completed a month or more after their DLD end date: 1 of 2 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in International City Phase 3

DLD lists 57 projects in the master project International City Phase 3.

Equiti TowerUnder construction · 70.2% · Aug 2025
The Maiden ResidenceUnder construction · 73% · Dec 2025
Mayflower ResidencesUnder construction · 96.1% · Mar 2026
08 Life ResidencesUnder construction · 64.9% · May 2026
Stellar Axis by Ajmal Estate DevelopersUnder construction · 26.7% · Oct 2026
Tavora Residences By Jhk Heights Real Estate DevelopmentUnder construction · 86.2% · Dec 2026
Moonsa Residences 2Under construction · 1% · Dec 2026
Vio ResidencesUnder construction · 6.4% · Dec 2026
Sadaat TowerUnder construction · 32.1% · Jan 2027
Zyra Vista ResidencesUnder construction · 2.1% · Mar 2027
NestUnder construction · 0.8% · Apr 2027

Questions about MOONSA Residences

When was MOONSA Residences completed?

MOONSA Residences is recorded as completed on 30 October 2026 (DLD register of 1 November 2026).

Who is the developer of MOONSA Residences?

Dugasta Properties Development L.L.C, as registered with DLD.

What is the DLD project number of MOONSA Residences?

2834.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error