Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4462Not started307 units

Greenfield 2 by Samana Developers جرينفيلد 2 باي سامانا ديفيلوبرز Warsan Fourth · International City Phase 3 by Samana Platinum Real Estate Development L.L.CAll phases of International City Phase 3 DLD status: Not started (DLD register as of 1 November 2026) DLD end date Aug 2029 33 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0%
DLD register, 1 November 2026
Registered start
May 2026
DLD end date Aug 2029
Latest sales
1,445 AED/sqft
41 sales
1 BR estimate
0.89–1.00 M AED
Automated estimate, not a valuation
Developer
7 projects
0 completed · 0 units delivered

Completion

DLD status: Not started. 0% built, DLD end date 31 August 2029. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0% 31 August 2029Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
4462
Escrow agent
Ajman Bank /P.J.S.C
Zoning authority
Trakhees
Master project
International City Phase 3
DLD area
Warsan Fourth
Units · villas
307 · 0
Start → DLD end
May 2026 → Aug 2029
Registered units1 bed 234 · 2 bed 70; sizes 593–883 sqft

Also registered: shops and showrooms 3.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: 2B+G+4P+14F+R

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 home sales after the launch window in the last 12 months, so no comparison is shown.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
1 BR 1,465 (32) 1,465 (32) 0%
2 BR 1,299 (9) 1,299 (9) 0%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
1 BR 32 1,465 (32) May 2026 – Nov 2026
2 BR 9 1,299 (9) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2026-Q4 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Warsan Fourth, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents in DLD area Warsan Fourth

New Ejari rent contracts for apartments across DLD area Warsan Fourth, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 40,000 1,446 +8.1%
1 BR AED 56,000 2,375 +7.7%
2 BR AED 73,000 385 +12.3%
3 BR AED 98,000 28 +9.1%
4 BR AED 152,500 9 —

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
13.3 AED/sqft a year
International City: median of 33 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 41 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
5 November 2026off-planApartment · 1 BR 636 919,000 1,445
5 November 2026off-planApartment · 1 BR 615 843,317 1,371
3 November 2026off-planApartment · 1 BR 901 1,158,094 1,285
3 November 2026off-planApartment · 1 BR 634 907,294 1,431
3 November 2026off-planApartment · 1 BR 634 892,494 1,408
2 November 2026off-planApartment · 1 BR 666 939,550 1,411
2 November 2026off-planApartment · 1 BR 577 881,741 1,528
2 November 2026off-planApartment · 1 BR 443 849,000 1,916
30 October 2026off-planApartment · 1 BR 568 914,000 1,609
30 October 2026off-planApartment · 1 BR 636 888,470 1,397

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Looking for a unit in this or similar projects?

Tell us what you are looking for in Greenfield 2 by Samana Developers or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Estimated value range
Bedrooms Range, AED Based on Compared at
1 BR 890,000 – 1,000,000 32 sales, 12 months This project
2 BR 1,300,000 – 1,320,000 9 sales, 12 months This project
Automated estimate, not a valuation

Estimate as of 5 November 2026 Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Aug 2029); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Aug 2029
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in Greenfield 2 by Samana Developers? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationWarsan Fourth · Dubai Municipality community

Shaklan Hypermarket · 60 mGalaxy Market · 420 mPark · 1.1 kmShaklan Supermarket · 1.3 kmPark · 1.4 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationRashidiya Metro Station · Red Metro line · 9.4 km
MallQ1 Mall · 2.5 km
SupermarketShaklan Hypermarket · 60 m
HospitalFakeeh University Hospital · 3.3 km
School宿舍 · 2.3 km
ParkPark · 1.1 km
BeachBeach · 2.8 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 38, with 3,792 units and villas.

2025: 3842026: 6922027: 7862028: 1,4992029: 431

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Warsan Fourth: 37

Open projects in the same DLD area with a DLD end year from 2028 to 2030, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Greenfield by Samana Developers 1.5% Oct 2028 1,384 299
Zenith Residences 24.1% Mar 2028 1,061 121
Chapter 01 By Newbury Developments 2.4% Oct 2028 1,151 69
Kyomi Residence 0% Jan 2028 1,482 31
Sports View Residence 2 By Al Helal Al Zahaby 13.4% Nov 2029 1,132 26
Ventana Residences 6.7% Feb 2028 — 22
Coventry 2 0% Dec 2028 1,174 22
Zyra Hills 0% Mar 2028 1,382 19
Park Residency 0% Jul 2029 — 8
Project 3883, Warsan Fourth 0% Jan 2028 — 0
Project 4406, Warsan Fourth 0% Apr 2028 — 0
Chapter 02 2.1% Dec 2028 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Warsan Fourth

Developer in DLD data Samana Platinum Real Estate Development L.L.C · DLD developer no. 2072

Projects registered
7
0 completed · 3 under construction · 4 not started
Units delivered
0
1,496 in the pipeline
Past the DLD end date
0
of 3 under construction with a DLD end date

Samana Platinum Real Estate Development L.L.C is one of 10 DLD-registered developers we list together as Samana. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error