DLD project no. 1988Completed272 units
Pantheon Elysee بانثيون اليسي Completed 4 January 2021 (DLD) · DLD end date Jan 2021 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.
CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 4 January 2021 | 100% | DLD inspection |
| 8 October 2020 | 85.1% | DLD inspection |
| 27 May 2020 | 68.3% | DLD inspection |
| 5 March 2020 | 60.2% | DLD inspection |
| 8 September 2019 | 31.3% | DLD inspection |
| 28 February 2019 | 13.4% | DLD inspection |
| 4 September 2018 | 3.3% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
DLD registration
DLD services ↗Also registered: shops and showrooms 6.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: PROJECT CONSISTS OF 2B+G+4+R RESIDENTIAL BUILDING WITH RETAIL AT GROUND FLOOR LOCATED IN AL BARSHA SOUTH FOURTH. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
Dubai Statistics Center residential price index (flats), 2020-Q2 to 2026-Q2: +49.8%.
Prices are over apartments, the type most sales in this project are.
| Bedrooms | Sales, 24 months | Latest median AED/sqft | Latest sales |
|---|---|---|---|
| Studio | 27 | 1,345 (10) | Nov 2025 – Nov 2026 |
| 1 BR | 26 | 1,062 (6) | Nov 2025 – Nov 2026 |
| 2 BR | 7 | — | — |
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Median AED/sqft by quarter
2020-Q2 → 2026-Q4| Quarter | Registered sales | Median AED/sqft | DLD area Al Barsha South Fourth |
|---|---|---|---|
| 2020-Q2 | 89 (off-plan 89, ready 0) | 1,042 | 698 |
| 2020-Q3 | 37 (off-plan 37, ready 0) | 1,036 | 609 |
| 2020-Q4 | 56 (off-plan 56, ready 0) | 1,036 | 652 |
| 2021-Q1 | 38 (off-plan 34, ready 4) | 1,084 | 693 |
| 2021-Q2 | 14 (off-plan 0, ready 14) | 1,046 | 725 |
| 2021-Q3 | 13 (off-plan 0, ready 13) | 1,061 | 816 |
| 2021-Q4 | 2 (off-plan 0, ready 2) | — | 828 |
| 2022-Q2 | 1 (off-plan 0, ready 1) | — | 902 |
| 2022-Q3 | 1 (off-plan 0, ready 1) | — | 877 |
| 2022-Q4 | 4 (off-plan 0, ready 4) | — | 923 |
| 2023-Q1 | 8 (off-plan 0, ready 8) | 839 | 882 |
| 2023-Q2 | 12 (off-plan 0, ready 12) | 1,000 | 966 |
| 2023-Q3 | 13 (off-plan 0, ready 13) | 993 | 943 |
| 2023-Q4 | 20 (off-plan 0, ready 20) | 1,106 | 971 |
| 2024-Q1 | 10 (off-plan 0, ready 10) | 1,211 | 1,054 |
| 2024-Q2 | 4 (off-plan 0, ready 4) | — | 1,070 |
| 2024-Q3 | 7 (off-plan 0, ready 7) | 1,039 | 1,086 |
| 2024-Q4 | 18 (off-plan 0, ready 18) | 1,124 | 1,211 |
| 2025-Q1 | 10 (off-plan 0, ready 10) | 1,242 | 1,254 |
| 2025-Q2 | 10 (off-plan 0, ready 10) | 1,086 | 1,261 |
| 2025-Q3 | 8 (off-plan 0, ready 8) | 1,210 | 1,241 |
| 2025-Q4 | 12 (off-plan 0, ready 12) | 1,268 | 1,352 |
| 2026-Q1 | 3 (off-plan 0, ready 3) | — | 1,355 |
| 2026-Q2 | 3 (off-plan 0, ready 3) | — | 1,272 |
| 2026-Q3 | 1 (off-plan 0, ready 1) | — | 1,224 |
| 2026-Q4 | 1 (off-plan 0, ready 1) | — | 1,289 |
Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Barsha South Fourth, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Registered sales per quarter
| Quarter | Registered sales | Median AED/sqft | DLD area Al Barsha South Fourth |
|---|---|---|---|
| 2020-Q2 | 89 (off-plan 89, ready 0) | 1,042 | 698 |
| 2020-Q3 | 37 (off-plan 37, ready 0) | 1,036 | 609 |
| 2020-Q4 | 56 (off-plan 56, ready 0) | 1,036 | 652 |
| 2021-Q1 | 38 (off-plan 34, ready 4) | 1,084 | 693 |
| 2021-Q2 | 14 (off-plan 0, ready 14) | 1,046 | 725 |
| 2021-Q3 | 13 (off-plan 0, ready 13) | 1,061 | 816 |
| 2021-Q4 | 2 (off-plan 0, ready 2) | — | 828 |
| 2022-Q2 | 1 (off-plan 0, ready 1) | — | 902 |
| 2022-Q3 | 1 (off-plan 0, ready 1) | — | 877 |
| 2022-Q4 | 4 (off-plan 0, ready 4) | — | 923 |
| 2023-Q1 | 8 (off-plan 0, ready 8) | 839 | 882 |
| 2023-Q2 | 12 (off-plan 0, ready 12) | 1,000 | 966 |
| 2023-Q3 | 13 (off-plan 0, ready 13) | 993 | 943 |
| 2023-Q4 | 20 (off-plan 0, ready 20) | 1,106 | 971 |
| 2024-Q1 | 10 (off-plan 0, ready 10) | 1,211 | 1,054 |
| 2024-Q2 | 4 (off-plan 0, ready 4) | — | 1,070 |
| 2024-Q3 | 7 (off-plan 0, ready 7) | 1,039 | 1,086 |
| 2024-Q4 | 18 (off-plan 0, ready 18) | 1,124 | 1,211 |
| 2025-Q1 | 10 (off-plan 0, ready 10) | 1,242 | 1,254 |
| 2025-Q2 | 10 (off-plan 0, ready 10) | 1,086 | 1,261 |
| 2025-Q3 | 8 (off-plan 0, ready 8) | 1,210 | 1,241 |
| 2025-Q4 | 12 (off-plan 0, ready 12) | 1,268 | 1,352 |
| 2026-Q1 | 3 (off-plan 0, ready 3) | — | 1,355 |
| 2026-Q2 | 3 (off-plan 0, ready 3) | — | 1,272 |
| 2026-Q3 | 1 (off-plan 0, ready 1) | — | 1,224 |
| 2026-Q4 | 1 (off-plan 0, ready 1) | — | 1,289 |
Registered sales per quarter, off-plan and ready units. Source: DLD.
What launch buyers got
The launch price against the registered resales after completion, same home types on both sides.
Over the same span, ready homes in DLD area Al Barsha South Fourth changed +98.7% (same home types).
Launch: the 90 days from the first off-plan sale (2020 onward). Resales: ready sales in the 12 months after the DLD completion date, or 24 when 12 hold fewer than 5. A price change is not a return: it leaves out fees, service charges, rent and the payment plan.
Rents and gross yield
New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Gross yield: the median annual rent over the median registered ready sale price of the same bedroom count in this project over the same 12 months.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier | Gross yield |
|---|---|---|---|---|
| Studio | AED 48,000 | 63 | -4% | 8.3% |
| 1 BR | AED 70,000 | 44 | -5.4% | — |
Gross yield is before service charges, other costs and empty months.
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Mortgage registrations
Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.
| Quarter | Mortgage registrations |
|---|---|
| 2024-Q1 | 5 · registered amount AED 2.7M |
| 2024-Q2 | 1 |
| 2024-Q3 | 4 |
| 2024-Q4 | 7 · registered amount AED 4.2M |
| 2025-Q1 | 5 · registered amount AED 2.6M |
| 2025-Q2 | 9 · registered amount AED 6.1M |
| 2025-Q3 | 2 |
| 2025-Q4 | 2 |
| 2026-Q1 | 2 |
| 2026-Q2 | 0 |
| 2026-Q3 | 1 |
| 2026-Q4 | 0 |
Mortgage registrations on homes per quarter. Source: DLD.
Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 3; the amount shows from 5 registrations.
Since the first registration in 2021-Q1: 62 in all.
Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Service charges
What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.
Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.
Source: Dubai Land Department, owners’ association budgets (service charges).
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 26 October 2026 | ready | Apartment · 2 BR | 1,293 | 1,050,000 | 812 |
| 25 August 2026 | ready | Apartment · Studio | 429 | 500,000 | 1,166 |
| 25 June 2026 | ready | Apartment · 1 BR | 779 | 827,355 | 1,062 |
| 8 June 2026 | ready | Apartment · 1 BR | 922 | 911,706 | 989 |
| 3 June 2026 | ready | Apartment · 1 BR | 779 | 750,000 | 963 |
| 9 March 2026 | ready | Apartment · Studio | 461 | 620,000 | 1,345 |
| 10 February 2026 | ready | Apartment · Studio | 426 | 610,000 | 1,432 |
| 16 January 2026 | ready | Apartment · 1 BR | 773 | 890,000 | 1,151 |
| 23 December 2025 | ready | Apartment · Studio | 465 | 484,900 | 1,043 |
| 19 December 2025 | ready | Apartment · Studio | 388 | 565,000 | 1,456 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
LocationAl Barsha South Fourth · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 144, with 35,321 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2010 | 1 | 0 |
| 2013 | 1 | 165 |
| 2024 | 1 | 229 |
| 2025 | 9 | 2,275 |
| 2026 | 38 | 8,959 |
| 2027 | 34 | 8,212 |
| 2028 | 31 | 8,148 |
| 2029 | 9 | 2,634 |
| No end date | 20 | 4,699 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Al Barsha South Fourth: 153
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Binghatti Circle | 22.1% | May 2027 | 1,611 | 779 |
| Serenz by Danube | 0.1% | Dec 2029 | 2,302 | 673 |
| Binghatti Amberhall | 70% | Feb 2026 | 1,696 | 623 |
| Binghatti Ruby | 65% | Feb 2026 | 1,967 | 552 |
| One Sky Park By Iman | 21.7% | Mar 2028 | 1,650 | 549 |
| Auresta Tower | 4.4% | Dec 2028 | 1,609 | 523 |
| Skyhills II by HRE | 96% | Jun 2026 | 1,531 | 481 |
| Skyhills III by HRE | 75.7% | Jun 2026 | 1,598 | 418 |
| Legado By Prescott | 23.3% | Aug 2027 | 1,748 | 342 |
| Violet Tower | 90.2% | Jun 2026 | 1,345 | 285 |
| The AUTOGRAPH-I Series | 4% | Aug 2028 | 1,691 | 269 |
| Maison Elysee Iii By Pantheon | 4.4% | Oct 2027 | 1,679 | 260 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Pantheon Real Estate Development L.L.C · DLD developer no. 1173
Completed a month or more after their DLD end date: 0 of 2 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Pantheon Real Estate Development L.L.C is one of 2 DLD-registered developers we list together as Pantheon. See the group
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Jumeirah Village Circle
DLD lists 410 projects in the master project Jumeirah Village Circle.
Questions about Pantheon Elysee
When was Pantheon Elysee completed?
Pantheon Elysee is recorded as completed on 4 January 2021 (DLD register of 1 November 2026).
Who is the developer of Pantheon Elysee?
Pantheon Real Estate Development L.L.C, as registered with DLD.
What is the DLD project number of Pantheon Elysee?
1988.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error