DLD project no. 2160Completed
Damac Hills - The Trump Estates 3 داماك هيلز - ذي ترامب ايستايتس 3 Completed 28 June 2022 (DLD) · DLD end date Jun 2022 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.
CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 31 May 2022 | 100% | DLD inspection |
| 26 August 2021 | 93.6% | DLD inspection |
| 25 January 2021 | 90.5% | DLD inspection |
| 12 May 2020 | 87.3% | DLD inspection |
| 21 October 2019 | 80% | DLD inspection |
| 12 May 2019 | 57.7% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
Building permits
1 of 1 buildingsBuildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.
Furthest stage reached: Finishes.
| Work stage | Buildings |
|---|---|
| Finishes | 1 |
Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.
DLD registration
DLD services ↗Homes: villas 13.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: Project consists of a cluster of 13 freehold G+1 Villas and Townhouses located in Al Hebiah Third, Dubailand Area. The villas are designed to have a concrete structure and block with internal and external finishes.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
No off-plan sales are registered for this project since 2020, so there is no launch price.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Mortgage registrations
Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.
| Quarter | Mortgage registrations |
|---|---|
| 2024-Q1 | 0 |
| 2024-Q2 | 0 |
| 2024-Q3 | 0 |
| 2024-Q4 | 0 |
| 2025-Q1 | 2 |
| 2025-Q2 | 0 |
| 2025-Q3 | 0 |
| 2025-Q4 | 1 |
| 2026-Q1 | 0 |
| 2026-Q2 | 0 |
| 2026-Q3 | 0 |
| 2026-Q4 | 0 |
Mortgage registrations on homes per quarter. Source: DLD.
No mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4).
Since the first registration in 2023-Q4: 4 in all.
Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Service charges
What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.
Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.
Source: Dubai Land Department, owners’ association budgets (service charges).
LocationAl Hebiah Third · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 14, with 2,976 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2024 | 1 | 0 |
| 2025 | 2 | 0 |
| 2026 | 1 | 0 |
| 2027 | 2 | 479 |
| 2028 | 2 | 0 |
| 2029 | 1 | 1,139 |
| 2030 | 1 | 288 |
| No end date | 4 | 1,070 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Al Hebiah Third: 9
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Damac District | 4.1% | Mar 2029 | 1,810 | 737 |
| Damac Hills - Golf Greens 2 | 45.2% | — | 1,666 | 348 |
| Damac Hills - Golf Greens 1 | 40.5% | Mar 2027 | 1,713 | 117 |
| Damac Hills - Ivory | 0.6% | Jun 2028 | — | 98 |
| Damac Hills - Golf Gate 2 | 80.4% | — | 1,472 | 84 |
| Damac Hills - Autograph Collection | 9.4% | May 2027 | — | 32 |
| Damac Hills - Gems Estates 1 | 48.8% | Nov 2026 | — | 14 |
| Damac Hills - Gems Estates 2 | 62.6% | Sep 2024 | — | 8 |
| DAMAC Hills - Lilac | 0% | Jan 2030 | — | 0 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Damac Crescent Properties · DLD developer no. 954
Completed a month or more after their DLD end date: 2 of 43 completed projects with both dates. In 31 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Damac Crescent Properties is one of 21 DLD-registered developers we list together as Damac. See the group
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Damac Hills
DLD lists 51 projects in the master project Damac Hills.
Questions about Damac Hills - The Trump Estates 3
When was Damac Hills - The Trump Estates 3 completed?
Damac Hills - The Trump Estates 3 is recorded as completed on 28 June 2022 (DLD register of 1 November 2026).
Who is the developer of Damac Hills - The Trump Estates 3?
Damac Crescent Properties, as registered with DLD.
What is the DLD project number of Damac Hills - The Trump Estates 3?
2160.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error