DLD project no. 2338Completed
Tilal AL Furjan- Phase One تلال الفرجان - المرحلة الأولى Completed 31 December 2024 (DLD) · DLD end date Dec 2024 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.
CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 28 April 2025 | 100% | DLD inspection |
| 24 January 2025 | 91.3% | DLD inspection |
| 25 September 2024 | 71.8% | DLD inspection |
| 12 May 2024 | 38% | DLD register, archived export |
| 16 February 2024 | 38.3% | DLD inspection |
| 17 October 2023 | 21.2% | DLD inspection |
| 27 July 2023 | 14.1% | DLD inspection |
| 29 March 2023 | 1.2% | DLD inspection |
| 26 December 2022 | 0% | DLD inspection |
| 27 September 2022 | 0% | DLD inspection |
| 5 August 2022 | 0% | DLD register, archived export |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
DLD registration
DLD services ↗Homes: villas 235.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: 235 Compounded Villas & Townhouses G+1.The project designed to have a concrete structure and block with internal and external finishes.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
No off-plan sales are registered for this project since 2020, so there is no launch price.
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Service charges
What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.
Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.
Source: Dubai Land Department, owners’ association budgets (service charges).
LocationJabal Ali First · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 13, with 1,930 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2025 | 1 | 133 |
| 2027 | 6 | 657 |
| 2028 | 3 | 302 |
| No end date | 3 | 838 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Jabal Ali First: 77
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Sobha Central Phase I | 7.1% | Jun 2030 | 2,839 | 1,192 |
| Sobha Central Phase II | 6.4% | Jun 2030 | 2,969 | 809 |
| Sobha Central | 2.4% | Dec 2031 | 3,224 | 614 |
| Taiyo Residences | 12.1% | Dec 2027 | 1,596 | 356 |
| SPARKLZ by Danube | 7.8% | May 2028 | 1,688 | 330 |
| Boulevard Park 2 | 0% | Nov 2029 | 1,699 | 316 |
| South Garden C | 16.2% | Dec 2027 | 1,220 | 255 |
| Hills View at Wasl Gate | 9.1% | Jun 2028 | 1,425 | 255 |
| South Garden A | 16.2% | Dec 2027 | 1,313 | 243 |
| Sola Residences | 23.6% | Sep 2027 | 1,380 | 242 |
| South Garden B | 16.2% | Dec 2027 | 1,357 | 236 |
| South Garden E | 8% | May 2028 | 1,443 | 223 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Alfurjan ( L.L.C ) · DLD developer no. 121
Completed a month or more after their DLD end date: 0 of 8 completed projects with both dates. In 7 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Al Furjan
DLD lists 105 projects in the master project Al Furjan.
Questions about Tilal AL Furjan- Phase One
When was Tilal AL Furjan- Phase One completed?
Tilal AL Furjan- Phase One is recorded as completed on 31 December 2024 (DLD register of 1 November 2026).
Who is the developer of Tilal AL Furjan- Phase One?
Alfurjan ( L.L.C ), as registered with DLD.
What is the DLD project number of Tilal AL Furjan- Phase One?
2338.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error