DLD master projectJabal Ali First
Al Furjan 44 of 106 phases not yet completed · 4,843 units · 4,101 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Al Furjan has 106 projects in the Dubai Land Department projects register as of 1 November 2026: 44 not yet completed, with 4,843 units and villas. By DLD status: Under construction 39 · Completed 62 · Conditionally activating 1 · Not started 3 · Pending 1. Under construction and past the DLD end date: 7.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 106 of the 106 phases: those with a map pin. Pins mark approximate locations.
Jabal Ali First (DM community)
Phases (106)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| SPARKLZ by Danube | Under construction | 7.8% | May 2028 18 months to go | 18 months to go | 358 | 330 | +1.2% |
| Equiti Home | Completed | 100% | Jan 2026 | — | 302 | 212 | +13.9% |
| 999 Residences by Reef Luxury Development | Under construction | 13.2% | Jun 2027 7 months to go | 7 months to go | 148 | 135 | +6.4% |
| Prime Residency 3 | Completed | 100% | Dec 2024 | — | 292 | 135 | +51.3% |
| Avenue Residence 7 By Nabni | Under construction | 17.3% | Oct 2027 11 months to go | 11 months to go | 166 | 126 | — |
| Al Furjan | Completed | 100% | May 2013 | — | 512 | 123 | — |
| Azizi Zain | Under construction | 80.2% | Oct 2027 11 months to go | 11 months to go | 115 | 111 | — |
| Vistara House | Under construction | 7% | Mar 2027 4 months to go | 4 months to go | 141 | 109 | +3.4% |
| Equiti Garden | Under construction | 87% | Dec 2025 10 months past it | 10 months past it | 133 | 108 | -0.9% |
| The Hub Residences by ZaZEN | Under construction | 34% | Jan 2027 2 months to go | 2 months to go | 105 | 107 | — |
| Avenue Residence 8 | Under construction | 17.8% | Jun 2028 19 months to go | 19 months to go | 104 | 107 | — |
| Azizi Central | Completed | 100% | Jun 2026 | — | 97 | 104 | — |
| Trussardi Residences | Under construction | 36.2% | Jan 2026 9 months past it | 9 months past it | 142 | 99 | — |
| STARZ TOWER by DANUBE | Completed | 100% | Feb 2019 | — | 454 | 86 | — |
| PG Maison | Under construction | 10% | Dec 2027 13 months to go | 13 months to go | 85 | 82 | — |
| Valores Residences | Completed | 100% | Oct 2026 | — | 90 | 79 | +12.7% |
| Raffi By Azizi | Under construction | 2% | Jan 2028 14 months to go | 14 months to go | 171 | 76 | -0.7% |
| Evora Residences | Under construction | 20.5% | Aug 2026 2 months past it | 2 months past it | 77 | 75 | — |
| PEARLZ by Danube | Completed | 100% | Jan 2025 | — | 302 | 75 | +31.3% |
| The Stella Residences | Under construction | 71.1% | Dec 2025 11 months past it | 11 months past it | 236 | 73 | +11.7% |
| Minati Homes 1 | Under construction | 51.2% | Sep 2026 1 month past it | 1 month past it | 82 | 73 | — |
| Glamz Residence | Completed | 100% | Oct 2020 | — | 426 | 70 | — |
| Azizi Samia Residence | Completed | 100% | Jan 2020 | — | 296 | 70 | — |
| Sunbliss Residences by Purvanchal Real Estate Developers | Under construction | 32.4% | Dec 2026 1 month to go | 1 month to go | 99 | 64 | — |
| Celeste Heights by Zimaya Properties | Under construction | 41.2% | Sep 2027 10 months to go | 10 months to go | 71 | 63 | — |
| Pristine By Zoya | Under construction | 58.4% | Jan 2027 2 months to go | 2 months to go | 73 | 62 | +13.1% |
| Azizi Farishta Residence | Completed | 100% | Mar 2020 | — | 295 | 62 | — |
| Azizi Amir | Under construction | 2.4% | Jun 2027 7 months to go | 7 months to go | 104 | 61 | — |
| GEMZ by Danube | Completed | 100% | Mar 2025 | — | 279 | 58 | +21.3% |
| Azizi Amber | Completed | 100% | Jul 2025 | — | 115 | 57 | — |
| Westwood By Imtiaz | Completed | 100% | Nov 2023 | — | 188 | 50 | +59.1% |
| Primero Residences by Main Realty | Conditionally activating | 21.1% | Jun 2026 5 months past it | 5 months past it | 86 | 48 | — |
| La Cle by Maaia Developers | Under construction | 34.6% | Jan 2027 2 months to go | 2 months to go | 58 | 43 | +13.9% |
| Dreamz | Completed | 100% | Mar 2016 | — | 171 | 43 | — |
| Nadine Residences | Completed | 100% | Dec 2024 | — | 102 | 42 | — |
| Vistara House 2 | Under construction | 2.1% | Dec 2027 13 months to go | 13 months to go | 82 | 40 | +4% |
| Azizi Shaista Residence | Completed | 100% | Mar 2021 | — | 297 | 39 | — |
| Sunvale | Under construction | 1.3% | May 2028 18 months to go | 18 months to go | 94 | 37 | — |
| Maria Tower | Completed | 100% | Sep 2018 | — | 98 | 37 | — |
| Pg One At Al Furjan | Completed | 100% | Mar 2026 | — | 121 | 37 | +25.8% |
| Symbolic Aura | Under construction | 70.1% | — | — | 78 | 36 | — |
| Avenue Residence 5 | Completed | 100% | Oct 2025 | — | 85 | 35 | +25.4% |
| Nadine Residences 2 | Completed | 100% | Feb 2025 | — | 102 | 35 | +42.2% |
| Symbolic Zen Residences | Under construction | 2.1% | Jun 2027 7 months to go | 7 months to go | 92 | 33 | -11.1% |
| Murooj Alfurjan West | Completed | 100% | Jun 2024 | — | 0 | 30 | — |
| Amalia Residences | Completed | 100% | Nov 2025 | — | 98 | 28 | — |
| Avenue Residence 4 | Completed | 77.4% | Jan 2024 | — | 135 | 28 | +28.6% |
| Azizi. Freesia | Completed | 100% | Jul 2017 | — | 98 | 26 | — |
| Victoria Residency | Completed | 100% | Dec 2018 | — | 103 | 26 | — |
| Repose Residence | Under construction | 37.5% | Mar 2027 4 months to go | 4 months to go | 80 | 25 | — |
| Alfurjan Package 4 | Completed | 100% | Aug 2016 | — | 8 | 25 | — |
| Azizi. Daisy | Completed | 100% | Jul 2017 | — | 129 | 22 | — |
| Equiti Arcade | Completed | 100% | Dec 2023 | — | 83 | 22 | — |
| Azizi. Liatris | Completed | 100% | Oct 2016 | — | 129 | 21 | — |
| Alfurjan Package 6 | Completed | 100% | Sep 2016 | — | 0 | 21 | — |
| Azizi. Orchid | Completed | 100% | Nov 2016 | — | 99 | 20 | — |
| Avenue RESIDENCE1 | Completed | 100% | Sep 2014 | — | 99 | 19 | — |
| Azizi. Feirouz | Completed | 100% | Sep 2016 | — | 99 | 19 | — |
| Pg Upperhouse | Completed | 100% | Jun 2023 | — | 105 | 19 | +46.7% |
| Azizi. Iris | Completed | 100% | Dec 2015 | — | 99 | 18 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
44 phases| DLD end year | Projects | Units |
|---|---|---|
| 2025 | 2 | 369 |
| 2026 | 8 | 668 |
| 2027 | 21 | 2,139 |
| 2028 | 9 | 1,095 |
| No end date | 4 | 572 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Al Furjan
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology