DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai Municipality communityDLD area Jabal Ali FirstAl FurjanWasl GateDiscovery Gardens

Jabal Ali First جبل علي الأولى 77 projects not yet completed · 19,833 units · 10,755 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Jabal Ali First has 77 projects not yet completed in the Dubai Land Department projects register as of 1 November 2026, with 19,833 units and villas; its projects had 10,755 registered sales in the last 24 months.

Projects not yet completed
77
of 148 DLD projects here
Units not yet completed
19,833
units and villas
Sales, 24 mo
10,755
registered with DLD
Service charges
15.99 AED/sqft a year
Al Furjan: median of 39 developments’ owners’ association budgets, 2026

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Projects on the map77 of the 77 projects listed have a map pin.

Sobha Central Phase I · Under construction · Approximate project locationSobha Central Phase II · Under construction · Approximate project locationSobha Central · Under construction · Project locationTaiyo Residences · Under construction · Project locationSPARKLZ by Danube · Under construction · Project locationBoulevard Park 2 · Not started / Pending / Conditionally activating · Project locationSouth Garden C · Under construction · Project locationHills View at Wasl Gate · Under construction · Project locationSouth Garden A · Under construction · Project locationSola Residences · Under construction · Project locationSouth Garden B · Under construction · Project locationSouth Garden E · Under construction · Project locationHavelock Residences · Not started / Pending / Conditionally activating · Project locationSouth Garden D · Under construction · Project locationBoulevard Park 1 · Not started / Pending / Conditionally activating · Project locationHammock Park · Under construction · Project locationBellavion by Sunrise · Under construction · Project location999 Residences by Reef Luxury Development · Under construction · Project locationAvenue Residence 7 By Nabni · Under construction · Project locationOmya Residences · Not started / Pending / Conditionally activating · Project locationAzizi Zain · Under construction · Project locationVistara House · Under construction · Project locationEquiti Garden · Under construction · Project locationThe Hub Residences by ZaZEN · Under construction · Project locationAvenue Residence 8 · Under construction · Project locationBeverly Gardens By Aa And Hmb Real Estate Development · Under construction · Project locationTrussardi Residences 2 · Under construction · Project locationTrussardi Residences · Under construction · Project locationHillside Residences 3 · Under construction · Project locationPG Maison · Under construction · Project locationRaffi By Azizi · Under construction · Project locationEvora Residences · Under construction · Project locationThe Stella Residences · Under construction · Project locationMinati Homes 1 · Under construction · Project locationEnqlave By Aqasa · Under construction · Project locationSunbliss Residences by Purvanchal Real Estate Developers · Under construction · Project locationCeleste Heights by Zimaya Properties · Under construction · Project locationPristine By Zoya · Under construction · Project locationAzizi Amir · Under construction · Project locationHillside Residences 2 · Under construction · Project locationHillside Residences 1 · Under construction · Project locationPrimero Residences by Main Realty · Not started / Pending / Conditionally activating · Project locationLa Cle by Maaia Developers · Under construction · Project locationVistara House 2 · Under construction · Project locationSerene Gardens by Prescott · Under construction · Project locationSunvale · Under construction · Project locationSymbolic Aura · Under construction · Project locationSymbolic Zen Residences · Under construction · Project locationCalifornia 2 by SD · Under construction · Project locationSerene Gardens 2 by Prescott · Under construction · Project locationRepose Residence · Under construction · Project locationAlmaara Residences · Under construction · Project locationKingdom Gate · Under construction · Project locationFloarea Vista · Under construction · Project locationCalifornia by SD · Under construction · Project locationAvenue Residence 6 · Under construction · Project locationGate Royale Residences · Under construction · Project locationRosalia Residences · Under construction · Project locationManam Pearl · Not started / Pending / Conditionally activating · Project locationOrvessa Residences by Michel Adam · Under construction · Project locationAryam Tower By Abu Alnaga · Under construction · Project locationAzizi Jewel · Under construction · Project locationAzizi Neila · Under construction · Project locationAmaya Residences · Under construction · Project locationProject 3621, Jabal Ali First · Not started / Pending / Conditionally activating · Project locationThe Mansions by MAG · Under construction · Project locationMaison Cannelle Residences by Casa Moderna · Under construction · Project locationAzizi Sikander · Under construction · Project locationAl Ghaf 2 · Under construction · Project locationW1 · Under construction · Project locationCasa Altia · Not started / Pending / Conditionally activating · Project locationAt 85 Residences · Not started / Pending / Conditionally activating · Project locationProject 4339, Jabal Ali First · Not started / Pending / Conditionally activating · Project locationHQA by Arista · Not started / Pending / Conditionally activating · Project locationJohn Richmond Residences · Not started / Pending / Conditionally activating · Project locationBoulevard Living 1 · Not started / Pending / Conditionally activating · Project locationBoulevard Living 2 · Not started / Pending / Conditionally activating · Project locationDubai Municipality · Makani
Under construction Not started / Pending / Conditionally activating Approximate project locations

Projects not yet completed (77)Projects not yet completed in Jabal Ali First, by registered sales in 24 months

Projects not yet completed in Jabal Ali First, by registered sales in 24 months
Project Developer DLD status Built DLD end date Past DLD end date Sales, 24 mo
Sobha Central Phase I3713 · Jabal Ali First · DMCC-EZ2Sobha L.L.C Under construction 7.1% Jun 2030 43 mo to go— 1,192
Sobha Central Phase II4042 · Jabal Ali First · DMCC-EZ2Sobha L.L.C Under construction 6.4% Jun 2030 43 mo to go— 809
Sobha Central4328 · Jabal Ali First · DMCC-EZ2Sobha L.L.C Under construction 2.4% Dec 2031 61 mo to go— 614
Taiyo Residences3757 · Jabal Ali First · Wasl GateContinental Investments Lmd L.L.C Under construction 12.1% Dec 2027 13 mo to go— 356
SPARKLZ by Danube3611 · Jabal Ali First · Al FurjanDanube Properties Development L.L.C Under construction 7.8% May 2028 18 mo to go— 330
Boulevard Park 24211 · Jabal Ali First · Wasl GateJag Development L.L.C Not started 0% Nov 2029 36 mo to go— 316
South Garden C3141 · Jabal Ali First · Wasl GateJag Development L.L.C Under construction 16.2% Dec 2027 13 mo to go— 255
Hills View at Wasl Gate3627 · Jabal Ali First · Wasl GateSuncrest Hills Property L.L.C Under construction 9.1% Jun 2028 19 mo to go— 255
South Garden A3138 · Jabal Ali First · Wasl GateJag Development L.L.C Under construction 16.2% Dec 2027 13 mo to go— 243
Sola Residences3513 · Jabal Ali First · Wasl GateSola Residences Real Estate Development L.L.C Under construction 23.6% Sep 2027 10 mo to go— 242
South Garden B3140 · Jabal Ali First · Wasl GateJag Development L.L.C Under construction 16.2% Dec 2027 13 mo to go— 236
South Garden E3761 · Jabal Ali First · Wasl GateJag Development L.L.C Under construction 8% May 2028 18 mo to go— 223
Havelock Residences3213 · Jabal Ali First · Discovery GardensAa And Hmb Real Estate Development L.L.C Conditionally activating 11.4% Dec 2026 1 mo to go— 219
South Garden D3760 · Jabal Ali First · Wasl GateJag Development L.L.C Under construction 5.7% May 2028 18 mo to go— 216
Boulevard Park 14184 · Jabal Ali First · Wasl GateJag Development L.L.C Not started 0% Apr 2030 41 mo to go— 211
Hammock Park2920 · Jabal Ali First · Wasl GateDivine Hills One Real Estate Development L.L.C Under construction 82.1% — — 199
Bellavion by Sunrise3472 · Jabal Ali First · Wasl GateSunrise Capital Real Estate Development L.L.C Under construction 10.3% Dec 2027 13 mo to go— 161
999 Residences by Reef Luxury Development3400 · Jabal Ali First · Al FurjanReef Luxury Development L.L.C Under construction 13.2% Jun 2027 7 mo to go— 135
Avenue Residence 7 By Nabni3300 · Jabal Ali First · Al FurjanNabni Real Estate Development L.L.C Under construction 17.3% Oct 2027 11 mo to go— 126
Omya Residences4248 · Jabal Ali First · Wasl GatePantheon Elysee Real Estate Development L.L.C Not started 0% Jun 2028 19 mo to go— 121
Azizi Zain3335 · Jabal Ali First · Al FurjanAzizi Developments L.L.C Under construction 80.2% Oct 2027 11 mo to go— 111
Vistara House3448 · Jabal Ali First · Al FurjanObject One Real Estate Development L.L.C Under construction 7% Mar 2027 4 mo to go— 109
Equiti Garden3242 · Jabal Ali First · Al FurjanB N H Real Estate Developer Under construction 87% Dec 2025 10 mo past10 mo 108
The Hub Residences by ZaZEN3419 · Jabal Ali First · Al FurjanZazen Property Development L.L.C Under construction 34% Jan 2027 2 mo to go— 107
Avenue Residence 83551 · Jabal Ali First · Al FurjanNabni Almustaqbal Properties Development L.L.C Under construction 17.8% Jun 2028 19 mo to go— 107
Beverly Gardens By Aa And Hmb Real Estate Development3029 · Jabal Ali First · Discovery GardensAa And Hmb Real Estate Development L.L.C Under construction 75.3% — — 106
Trussardi Residences 23556 · Jabal Ali First · Discovery GardensM I R A Developments L.L.C Under construction 4.6% Jul 2027 8 mo to go— 104
Trussardi Residences2900 · Jabal Ali First · Al FurjanM I R A Developments L.L.C Under construction 36.2% Jan 2026 9 mo past9 mo 99
Hillside Residences 32810 · Jabal Ali First · Wasl GateJag Development L.L.C Under construction 12.9% — — 86
PG Maison3151 · Jabal Ali First · Al FurjanPg Maison Real Estate Development L.L.C Under construction 10% Dec 2027 13 mo to go— 82
Raffi By Azizi3508 · Jabal Ali First · Al FurjanAzizi Developments L.L.C Under construction 2% Jan 2028 14 mo to go— 76
Evora Residences3191 · Jabal Ali First · Al FurjanAnax Developments L.L.C Under construction 20.5% Aug 2026 2 mo past2 mo 75
The Stella Residences2951 · Jabal Ali First · Al FurjanAlgouta Properties L.L.C Under construction 71.1% Dec 2025 11 mo past11 mo 73
Minati Homes 13047 · Jabal Ali First · Al FurjanJanuss Real Estate Developers L.L.C Under construction 51.2% Sep 2026 1 mo past1 mo 73
Enqlave By Aqasa2959 · Jabal Ali First · Discovery GardensAqasa Homes Developers L.L.C Under construction 70.3% — — 67
Sunbliss Residences by Purvanchal Real Estate Developers3485 · Jabal Ali First · Al FurjanPurvanchal Real Estate Developers L.L.C Under construction 32.4% Dec 2026 1 mo to go— 64
Celeste Heights by Zimaya Properties3511 · Jabal Ali First · Al FurjanZimaya Properties L.L.C Under construction 41.2% Sep 2027 10 mo to go— 63
Pristine By Zoya3069 · Jabal Ali First · Al FurjanZoya One Real Estate Developments L.L.C Under construction 58.4% Jan 2027 2 mo to go— 62
Azizi Amir3844 · Jabal Ali First · Al FurjanAzizi Developments L.L.C Under construction 2.4% Jun 2027 7 mo to go— 61
Hillside Residences 22809 · Jabal Ali First · Wasl GateJag Development L.L.C Under construction 18.5% — — 57
Hillside Residences 12808 · Jabal Ali First · Wasl GateJag Development L.L.C Under construction 26.3% — — 52
Primero Residences by Main Realty3005 · Jabal Ali First · Al FurjanMain Realty Real Estate L.L.C Conditionally activating 21.1% Jun 2026 — 48
La Cle by Maaia Developers3412 · Jabal Ali First · Al FurjanMaaia Prime Real Estate Developers L.L.C Under construction 34.6% Jan 2027 2 mo to go— 43
Vistara House 23766 · Jabal Ali First · Al FurjanOBJ1 Real Estate Development L.L.C Under construction 2.1% Dec 2027 13 mo to go— 40
Serene Gardens by Prescott2740 · Jabal Ali First · Discovery GardensPrescott Real Estate Development L.L.C Under construction 61.7% — — 37
Sunvale4196 · Jabal Ali First · Al FurjanPrysm Real Estate Development L.L.C Under construction 1.3% May 2028 18 mo to go— 37
Symbolic Aura2988 · Jabal Ali First · Al FurjanSpeedex Aura Developers L.L.C Under construction 70.1% — — 36
Symbolic Zen Residences3755 · Jabal Ali First · Al FurjanMoizziyah Developers L.L.C Under construction 2.1% Jun 2027 7 mo to go— 33
California 2 by SD2883 · Jabal Ali First · Discovery GardensSamana Star Real Estate Development L.L.C Under construction 33.7% Oct 2026 under 1 mo past— 30
Serene Gardens 2 by Prescott2872 · Jabal Ali First · Discovery GardensPrescott Real Estate Development L.L.C Under construction 70% — — 26
Repose Residence4012 · Jabal Ali First · Al FurjanSaion Real Estate Development L.L.C Under construction 37.5% Mar 2027 4 mo to go— 25
Almaara Residences3509 · Jabal Ali First · Al FurjanHamara Home Real Estate Development L.L.C Under construction 65.5% Oct 2026 under 1 mo past— 16
Kingdom Gate3826 · Jabal Ali First · Al FurjanKingdom Gate Property Development L.L.C Under construction 55.5% Mar 2027 4 mo to go— 16
Floarea Vista3028 · Jabal Ali First · Discovery GardensMashriq Elite Real Estate Development L.L.C Under construction 63% Jun 2026 4 mo past4 mo 15
California by SD2666 · Jabal Ali First · Discovery GardensSamana Si Holding Limited Dubai Branch Under construction 24.5% — — 11
Avenue Residence 62936 · Jabal Ali First · Al FurjanNabni Real Estate Development L.L.C Under construction 82.3% — — 11
Gate Royale Residences3824 · Jabal Ali First · Al FurjanBaron Prime Real Estate Development L.L.C Under construction 1.7% Jun 2027 7 mo to go— 10
Rosalia Residences2911 · Jabal Ali First · Al FurjanDeyaar Development (P.J.S.C) Under construction 82% — — 8
Manam Pearl3831 · Jabal Ali First · Al FurjanManam Real Estate Development L.L.C Not started 0% Jun 2028 19 mo to go— 5
Orvessa Residences by Michel Adam3434 · Jabal Ali First · Al FurjanBnw Echjay Real Estate Development L.L.C Under construction 1.5% Sep 2028 22 mo to go— 1
Aryam Tower By Abu Alnaga4488 · Jabal Ali First · Al FurjanAbualnaga Development L.L.C Under construction 33.2% Jun 2028 19 mo to go— 1
Azizi Jewel3020 · Jabal Ali First · Al FurjanAzizi Developments L.L.C Under construction 43% — — 0
Azizi Neila3203 · Jabal Ali First · Al FurjanAzizi Developments L.L.C Under construction 38.5% Jul 2027 8 mo to go— 0
Amaya Residences3516 · Jabal Ali First · Al FurjanPolygon Real Estate Development L.L.C Under construction 3.7% Mar 2027 4 mo to go— 0
Project 3621, Jabal Ali First3621 · Jabal Ali First · Al FurjanOzean Real Estate Development L.L.C Pending 0% May 2027 6 mo to go— 0
The Mansions by MAG3779 · Jabal Ali First · Al FurjanDigo Real Estate Development (Br Of Invest Group Overseas (L L C) ) Under construction 9.3% Apr 2027 5 mo to go— 0
Maison Cannelle Residences by Casa Moderna3782 · Jabal Ali First · Al FurjanCasa Moderna Real Estate Development L.L.C Under construction 40.4% Jun 2026 5 mo past5 mo 0
Azizi Sikander3845 · Jabal Ali First · Al FurjanAzizi Developments L.L.C Under construction 2% Jun 2027 7 mo to go— 0
Al Ghaf 23873 · Jabal Ali First · Al FurjanJersey Real Estate Development L.L.C Under construction 1.6% Oct 2027 11 mo to go— 0
W14130 · Jabal Ali First · Al FurjanMalina W1 Real Estate Development L.L.C Under construction 70.2% Apr 2026 6 mo past6 mo 0
Casa Altia4316 · Jabal Ali First · Al FurjanCasa Magnum Real Estate Development L.L.C Not started 0% Jun 2028 19 mo to go— 0
At 85 Residences4325 · Jabal Ali First · Wasl GateScope Properties - Dubai Branch Not started 0% Mar 2028 16 mo to go— 0
Project 4339, Jabal Ali First4339 · Jabal Ali First · Wasl GateNeeto Properties L.L.C Pending 5% May 2028 18 mo to go— 0
HQA by Arista4356 · Jabal Ali First · Al FurjanArista One Real Estate Development L.L.C Not started 0% Jun 2028 19 mo to go— 0
John Richmond Residences4428 · Jabal Ali First · Discovery GardensM I R A Developments L.L.C Pending 0% Dec 2028 25 mo to go— 0
Boulevard Living 14469 · Jabal Ali First · Wasl GateJag Development L.L.C Not started 0% Dec 2029 37 mo to go— 0
Boulevard Living 24470 · Jabal Ali First · Wasl GateJag Development L.L.C Not started 0% Dec 2029 37 mo to go— 0

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

77 phases
2025: 3692026: 1,2112027: 4,2182028: 3,0082029: 9442030: 5,2432031: 2,169No end date: 2,671

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Jabal Ali First

Own a unit in one of these projects? Track it free

Area prices

2022-Q1 – 2026-Q4

Median AED/sqft of off-plan sales of apartments by quarter in DLD area Jabal Ali First, where most of the community’s projects are registered.

DLD area Jabal Ali First, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Source: Dubai Land Department transactions, on Dubai Data.

Rents in DLD area Jabal Ali First

New Ejari rent contracts for apartments across DLD area Jabal Ali First, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 45,500 3,592 -2.2%
1 BR AED 67,000 3,120 -1.5%
2 BR AED 93,000 1,583 -7%
3 BR AED 135,000 373 +8%
4 BR AED 142,500 53 —

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Service charges

What owners pay a year in completed buildings of the master communities here, from their owners’ association budgets: one figure per master community, the one with the most projects first.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
15.99 AED/sqft a year
Al Furjan: median of 39 developments’ owners’ association budgets, 2026
Too few of its budgets tell apartment buildings from villas, so both are counted.
16.4 AED/sqft a year
Discovery Gardens: median of 17 developments’ owners’ association budgets, 2026
Apartment buildings’ budgets; villa and townhouse budgets are left out.
16.76 AED/sqft a year
DMCC Master Community: median of 32 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales in DLD area Jabal Ali First

The newest home sales DLD has registered in DLD area Jabal Ali First, as DLD publishes them, with the project where DLD names one.

The newest 10 of 6,485 registered sales in the 12 months to 5 November 2026
DateProjectMarketType Size (sqft) Price (AED) AED/sqft
5 November 2026Al FurjanreadyVilla 6,458 7,000,000 1,084
5 November 2026Boulevard Park 2off-planApartment · 3 BR 1,793 3,160,000 1,762
5 November 2026Azizi Amiroff-planApartment · 3 BR 1,734 2,605,440 1,503
5 November 2026—readyApartment · 2 BR 1,577 1,930,510 1,224
5 November 2026—readyApartment · 2 BR 1,273 1,665,029 1,308
5 November 2026Boulevard Park 1off-planApartment · 1 BR 842 1,562,000 1,855
5 November 2026Equiti HomereadyApartment · 2 BR 1,133 1,500,000 1,324
5 November 2026Azizi Zainoff-planApartment · 1 BR 775 998,280 1,288
5 November 2026—readyApartment · 1 BR 838 755,000 901
5 November 2026—readyApartment · 1 BR 883 710,000 804

The newest 10 of 6,485 registered sales in the 12 months to 5 November 2026

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Places inside the community

Places inside the Dubai Municipality outline of the community, by kind.

Metro stations
6
Schools
5
Hospitals
2
Malls
6
Supermarkets
16
Parks
17

Metro and tram stations: Roads and Transport Authority (RTA) via Dubai Data. Other places: © OpenStreetMap contributors.

Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026; Dubai Municipality community outlines. Methodology