DLD project no. 4469Not started195 units
Boulevard Living 1 بوليفارد ليفينج 1 DLD status: Not started (DLD register as of 1 November 2026) · DLD end date Dec 2029 · 37 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.
Completion
DLD status: Not started. 0% built, DLD end date 9 December 2029. DLD Project Status shows inspection reports once works begin.
| Date | % built | DLD end date | DLD status |
|---|---|---|---|
| 28 October 2026 | 0% | 9 December 2029 | Not started |
Source: DLD projects register, export of 1 November 2026.
Inspection photos and reports
DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.
CraneScore links to DLD and does not copy or host its photos or reports.
DLD registration
DLD services ↗Also registered: shops and showrooms 3.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: 8 floors Commercial & Residential Building G+2 Podium+8 Floors+R
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
LocationJabal Ali First · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 19, with 5,768 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2027 | 6 | 1,690 |
| 2028 | 6 | 1,539 |
| 2029 | 2 | 749 |
| 2030 | 1 | 717 |
| No end date | 4 | 1,073 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Jabal Ali First: 76
Open projects in the same DLD area with a DLD end year from 2028 to 2030, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Sobha Central Phase I | 7.1% | Jun 2030 | 2,839 | 1,192 |
| Sobha Central Phase II | 6.4% | Jun 2030 | 2,969 | 809 |
| SPARKLZ by Danube | 7.8% | May 2028 | 1,688 | 330 |
| Boulevard Park 2 | 0% | Nov 2029 | 1,699 | 316 |
| Hills View at Wasl Gate | 9.1% | Jun 2028 | 1,425 | 255 |
| South Garden E | 8% | May 2028 | 1,443 | 223 |
| South Garden D | 5.7% | May 2028 | 1,425 | 216 |
| Boulevard Park 1 | 0% | Apr 2030 | 1,721 | 211 |
| Omya Residences | 0% | Jun 2028 | 1,721 | 121 |
| Avenue Residence 8 | 17.8% | Jun 2028 | 1,434 | 107 |
| Raffi By Azizi | 2% | Jan 2028 | 1,695 | 76 |
| Sunvale | 1.3% | May 2028 | — | 37 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Jag Development L.L.C · DLD developer no. 1233
Completed a month or more after their DLD end date: 1 of 3 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.