Wasl Gate 20 of 23 phases not yet completed · 5,963 units · 3,373 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Wasl Gate has 23 projects in the Dubai Land Department projects register as of 1 November 2026: 20 not yet completed, with 5,963 units and villas. By DLD status: Under construction 13 · Not started 6 · Completed 3 · Pending 1.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 23 of the 23 phases: those with a map pin. Pins mark approximate locations.
Jabal Ali First (DM community)
Phases (23)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Taiyo Residences | Under construction | 12.1% | Dec 2027 13 months to go | 13 months to go | 379 | 356 | +9.8% |
| Boulevard Park 2 | Not started | 0% | Nov 2029 36 months to go | 36 months to go | 555 | 316 | -1.5% |
| South Garden C | Under construction | 16.2% | Dec 2027 13 months to go | 13 months to go | 258 | 255 | -5.7% |
| Hills View at Wasl Gate | Under construction | 9.1% | Jun 2028 19 months to go | 19 months to go | 350 | 255 | +0.3% |
| South Garden A | Under construction | 16.2% | Dec 2027 13 months to go | 13 months to go | 260 | 243 | +2.4% |
| Sola Residences | Under construction | 23.6% | Sep 2027 10 months to go | 10 months to go | 260 | 242 | +7.9% |
| South Garden B | Under construction | 16.2% | Dec 2027 13 months to go | 13 months to go | 258 | 236 | +2.5% |
| South Garden E | Under construction | 8% | May 2028 18 months to go | 18 months to go | 256 | 223 | +1.7% |
| South Garden D | Under construction | 5.7% | May 2028 18 months to go | 18 months to go | 256 | 216 | -4.7% |
| Boulevard Park 1 | Not started | 0% | Apr 2030 41 months to go | 41 months to go | 717 | 211 | +0.5% |
| Hammock Park | Under construction | 82.1% | — | — | 252 | 199 | — |
| Bellavion by Sunrise | Under construction | 10.3% | Dec 2027 13 months to go | 13 months to go | 275 | 161 | +7.1% |
| Omya Residences | Not started | 0% | Jun 2028 19 months to go | 19 months to go | 416 | 121 | -2.8% |
| The Nook | Completed | 100% | Jan 2022 | — | 605 | 120 | — |
| Hillside Residences 3 | Under construction | 12.9% | — | — | 306 | 86 | +13.1% |
| Hillside Residences 2 | Under construction | 18.5% | — | — | 280 | 57 | +9.9% |
| Hillside Residences 1 | Under construction | 26.3% | — | — | 235 | 52 | +12.3% |
| GardeniaTownHomes @ wasl gate | Completed | 100% | Mar 2020 | — | 0 | 24 | — |
| At 85 Residences | Not started | 0% | Mar 2028 16 months to go | 16 months to go | 261 | 0 | — |
| Boulevard Living 1 | Not started | 0% | Dec 2029 37 months to go | 37 months to go | 195 | 0 | — |
| Boulevard Living 2 | Not started | 0% | Dec 2029 37 months to go | 37 months to go | 194 | 0 | — |
| Project 4339, Jabal Ali First | Pending | 5% | May 2028 18 months to go | 18 months to go | 0 | 0 | — |
| Gardenia Townhomes II | Completed | 100% | Sep 2025 | — | 0 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
20 phases| DLD end year | Projects | Units |
|---|---|---|
| 2027 | 6 | 1,690 |
| 2028 | 6 | 1,539 |
| 2029 | 3 | 944 |
| 2030 | 1 | 717 |
| No end date | 4 | 1,073 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.