DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectJabal Ali First

Wasl Gate 20 of 23 phases not yet completed · 5,963 units · 3,373 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Wasl Gate has 23 projects in the Dubai Land Department projects register as of 1 November 2026: 20 not yet completed, with 5,963 units and villas. By DLD status: Under construction 13 · Not started 6 · Completed 3 · Pending 1.

Phases
23
3 completed
Not yet completed
20
13 under construction
Units not yet completed
5,963
units and villas
Sales, 24 mo
3,373
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 23 of the 23 phases: those with a map pin. Pins mark approximate locations.

Taiyo Residences · Under construction · Project locationBoulevard Park 2 · Not started / Pending · Project locationSouth Garden C · Under construction · Project locationHills View at Wasl Gate · Under construction · Project locationSouth Garden A · Under construction · Project locationSola Residences · Under construction · Project locationSouth Garden B · Under construction · Project locationSouth Garden E · Under construction · Project locationSouth Garden D · Under construction · Project locationBoulevard Park 1 · Not started / Pending · Project locationHammock Park · Under construction · Project locationBellavion by Sunrise · Under construction · Project locationOmya Residences · Not started / Pending · Project locationThe Nook · Completed · Project locationHillside Residences 3 · Under construction · Project locationHillside Residences 2 · Under construction · Project locationHillside Residences 1 · Under construction · Project locationGardeniaTownHomes @ wasl gate · Completed · Approximate project locationAt 85 Residences · Not started / Pending · Project locationBoulevard Living 1 · Not started / Pending · Project locationBoulevard Living 2 · Not started / Pending · Project locationProject 4339, Jabal Ali First · Not started / Pending · Project locationGardenia Townhomes II · Completed · Approximate project locationDubai Municipality · Makani
Under construction Not started / Pending Completed Approximate project locations

Jabal Ali First (DM community)

Phases (23)Ordered by registered sales over 24 months

Phases (23)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Taiyo ResidencesUnder construction 12.1% Dec 2027 13 months to go 13 months to go 379 356 +9.8%
Boulevard Park 2Not started 0% Nov 2029 36 months to go 36 months to go 555 316 -1.5%
South Garden CUnder construction 16.2% Dec 2027 13 months to go 13 months to go 258 255 -5.7%
Hills View at Wasl GateUnder construction 9.1% Jun 2028 19 months to go 19 months to go 350 255 +0.3%
South Garden AUnder construction 16.2% Dec 2027 13 months to go 13 months to go 260 243 +2.4%
Sola ResidencesUnder construction 23.6% Sep 2027 10 months to go 10 months to go 260 242 +7.9%
South Garden BUnder construction 16.2% Dec 2027 13 months to go 13 months to go 258 236 +2.5%
South Garden EUnder construction 8% May 2028 18 months to go 18 months to go 256 223 +1.7%
South Garden DUnder construction 5.7% May 2028 18 months to go 18 months to go 256 216 -4.7%
Boulevard Park 1Not started 0% Apr 2030 41 months to go 41 months to go 717 211 +0.5%
Hammock ParkUnder construction 82.1% — — 252 199 —
Bellavion by SunriseUnder construction 10.3% Dec 2027 13 months to go 13 months to go 275 161 +7.1%
Omya ResidencesNot started 0% Jun 2028 19 months to go 19 months to go 416 121 -2.8%
The NookCompleted 100% Jan 2022 — 605 120 —
Hillside Residences 3Under construction 12.9% — — 306 86 +13.1%
Hillside Residences 2Under construction 18.5% — — 280 57 +9.9%
Hillside Residences 1Under construction 26.3% — — 235 52 +12.3%
GardeniaTownHomes @ wasl gateCompleted 100% Mar 2020 — 0 24 —
At 85 ResidencesNot started 0% Mar 2028 16 months to go 16 months to go 261 0 —
Boulevard Living 1Not started 0% Dec 2029 37 months to go 37 months to go 195 0 —
Boulevard Living 2Not started 0% Dec 2029 37 months to go 37 months to go 194 0 —
Project 4339, Jabal Ali FirstPending 5% May 2028 18 months to go 18 months to go 0 0 —
Gardenia Townhomes IICompleted 100% Sep 2025 — 0 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

20 phases
2027: 1,6902028: 1,5392029: 9442030: 717No end date: 1,073

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Wasl Gate

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology