DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4339Pending

Project 4339, Jabal Ali First نيتو تاور Jabal Ali First · Wasl Gate by Neeto Properties L.L.CAll phases of Wasl Gate DLD status: Pending (DLD register as of 1 November 2026) DLD end date May 2028 18 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
5%
DLD register, 1 November 2026
Registered start
Nov 2025
DLD end date May 2028
Latest sales
—
Fewer than 5 recent sales
Developer
1 project
0 completed · 0 units delivered

Completion

DLD status: Pending. 5% built, DLD end date 1 May 2028. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 5% 1 May 2028Pending

Source: DLD projects register, export of 1 November 2026.

DLD registration

DLD services ↗
DLD project number
4339
Escrow agent
Procedure Participant Ar
Zoning authority
Dubai Municipality
Master project
Wasl Gate
DLD area
Jabal Ali First
Units · villas
0 · 0
Start → DLD end
Nov 2025 → May 2028

Description in the DLD register: B+G+P+14 Floors

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

LocationJabal Ali First · Dubai Municipality community

Energy Metro Station · 550 mPark · 720 mFestival Plaza · 850 mFestival Plaza · 860 mLulu · 980 mJebel Ali Primary School · 1.3 kmLifeline Hospital · 1.3 kmOasis Supermarket · 1.3 kmShakland 4 Supermarket · 1.3 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Metro and tram Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationEnergy Metro Station · Red Metro line · 550 m
MallFestival Plaza · 850 m
SupermarketLulu · 980 m
HospitalLifeline Hospital · 1.3 km
SchoolJebel Ali Primary School · 1.3 km
ParkPark · 720 m
BeachBeach · 2.1 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 19, with 5,963 units and villas.

2027: 1,6902028: 1,5392029: 9442030: 717No end date: 1,073

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Jabal Ali First: 76

Open projects in the same DLD area with a DLD end year from 2027 to 2029, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Taiyo Residences 12.1% Dec 2027 1,596 356
SPARKLZ by Danube 7.8% May 2028 1,688 330
Boulevard Park 2 0% Nov 2029 1,699 316
South Garden C 16.2% Dec 2027 1,220 255
Hills View at Wasl Gate 9.1% Jun 2028 1,425 255
South Garden A 16.2% Dec 2027 1,313 243
Sola Residences 23.6% Sep 2027 1,380 242
South Garden B 16.2% Dec 2027 1,357 236
South Garden E 8% May 2028 1,443 223
South Garden D 5.7% May 2028 1,425 216
Bellavion by Sunrise 10.3% Dec 2027 1,414 161
999 Residences by Reef Luxury Development 13.2% Jun 2027 1,547 135

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Jabal Ali First

Developer in DLD data Neeto Properties L.L.C · DLD developer no. 2016

Projects registered
1
0 completed · 0 under construction · 1 not started
Units delivered
0
0 in the pipeline

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error