Reef Luxury Development L.L.C ريف لكشري للتطوير ذ.م.م 7 projects in the DLD register: 0 completed, 4 under construction, 3 not started or pending. 0 of the 4 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 7- 0 units and villas in completed projects; 1,528 in projects not yet completed.
- Under construction past their DLD end date: 0 of 4 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Reef Luxury Development L.L.C Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|
| Reef 9983651 · Wadi Al Safa 5 · Dubai Land Residence Complex | Under construction | 2.1% | Jun 2028 19 mo to go | 339 | 281 |
| Reef 9964062 · Me'Aisem First · International Media Production Zone | Not started | 0.1% | Sep 2028 22 mo to go | 505 | 247 |
| 999 Residences by Reef Luxury Development3400 · Jabal Ali First · Al Furjan | Under construction | 13.2% | Jun 2027 7 mo to go | 148 | 135 |
| Reef 10003219 · Wadi Al Safa 5 · Dubai Land Residence Complex | Under construction | 67.2% | Dec 2026 1 mo to go | 126 | 101 |
| 997 Residences by Reef Luxury Development3837 · Palm Deira | Under construction | 4.9% | Mar 2028 16 mo to go | 63 | 20 |
| Project 4610, Jumeirah First4610 · Jumeirah First · Pearl Jumeira | Pending | 70% | Feb 2027 3 mo to go | — | 0 |
| Reef 9954285 · Wadi Al Safa 5 · Dubai Land Residence Complex | Not started | 0% | Nov 2028 24 mo to go | 347 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 7, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.