DLD project no. 4610Pending
Project 4610, Jumeirah First فيلا لو فان DLD status: Pending (DLD register as of 1 November 2026) · DLD end date Feb 2027 · 3 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.
Completion
DLD status: Pending. 70% built, DLD end date 23 February 2027. DLD Project Status shows inspection reports once works begin.
| Date | % built | DLD end date | DLD status |
|---|---|---|---|
| 28 October 2026 | 70% | 23 February 2027 | Pending |
Source: DLD projects register, export of 1 November 2026.
DLD registration
DLD services ↗Description in the DLD register: Basement + Ground + First + Roof
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
LocationJumeira First · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 3, with 166 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2029 | 3 | 166 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Developer in DLD data Reef Luxury Development L.L.C · DLD developer no. 1944
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error