Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2299Completed130 units

Port De La Mer - La Sirene 2 بورت دي لامير - لاسيرين 2 Jumeirah First · La Mer by Pdlm Residential L.L.CAll phases of La Mer Completed 6 June 2024 (DLD) DLD end date Jun 2024 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Jun 2024
DLD end date Jun 2024
Build time
30 months
Dec 2021 → Jun 2024
Launch → resale
2,878 AED/sqft
+38.5% on launch Launch 2,128 · 12 sales since completion
1 BR rent
110,000 AED/yr
27 leases, 12 months
Developer
7 projects
7 completed · 1,516 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 20 September 2024 (inspections: 6).
Every DLD inspection and every change in the register %, newest first
Date % built Source
20 September 2024 100% DLD inspection
12 May 2024 81% DLD register, archived export
12 March 2024 80.8% DLD inspection
24 August 2023 35.4% DLD inspection
2 May 2023 20.5% DLD inspection
19 January 2023 9.4% DLD inspection
27 June 2022 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
30 monthsActual build
30 months
Start date
5 December 2021
DLD end date
6 June 2024
Completion date
6 June 2024
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
2299
Escrow agent
Commercial Bank of Dubai(PSC)
Zoning authority
Dubai Development Authority (DDA)
Master project
La Mer
DLD area
Jumeirah First
Units · villas
130 · 0
Start → DLD end
Dec 2021 → Jun 2024
Registered units1 bed 64 · 2 bed 60 · 3 bed 5; sizes 800–1,217 sqft

Also registered: shops and showrooms 1 · other units 2.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Residential with retail units at Ground Floor Level. Shared floors: G + 1 + R Building 4, G+6 with total no. of 40 units Building 5, G+6 with total no. of 45 units Building 6, G+6 with total no. of 44 units

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft
Launch price
2,128 AED/sqft
Median of 100 off-plan sales in the 90 days from the first one (Jan 2022)
Latest registered sales
2,878 AED/sqft
Median of 12 home sales in the last 12 months, ready and off-plan
Change
+38.5%
Same home types on both sides, weighted by the later sales

Dubai Statistics Center residential price index (flats), 2022-Q1 to 2026-Q2: +36.9%.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
1 BR 2,128 (48) 2,878 (7) +35.2%
2 BR 2,126 (47) 3,042 (5) +43.1%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
1 BR 25 2,878 (7) Nov 2025 – Nov 2026
2 BR 23 3,042 (5) Nov 2025 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2022-Q1 → 2026-Q3

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Jumeirah First, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

What launch buyers got

The launch price against the registered resales after completion, same home types on both sides.

Launch price
2,128 AED/sqft
Median of 100 off-plan sales, Jan 2022 – Apr 2022
Resales after completion
2,878 AED/sqft
Median of 12 ready sales, Nov 2025 – Nov 2026
Change
+38.5%
Same home types, weighted by the resales

Over the same span, ready homes in DLD area Jumeirah First changed +49.2% (same home types).

Launch: the 90 days from the first off-plan sale (2020 onward). Resales: ready sales in the 12 months after the DLD completion date, or 24 when 12 hold fewer than 5. A price change is not a return: it leaves out fees, service charges, rent and the payment plan.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
1 BR AED 110,000 27 -5.2%
2 BR AED 195,000 23 -7.1%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 9; registered amount AED 20.6M.

Since the first registration in 2024-Q4: 26 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 12 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
25 September 2026readyApartment · 2 BR 1,207 4,775,000 3,956
8 September 2026readyApartment · 1 BR 834 2,140,000 2,566
24 July 2026readyApartment · 1 BR 834 2,400,000 2,878
11 March 2026readyApartment · 1 BR 780 2,450,000 3,141
9 March 2026readyApartment · 1 BR 819 2,300,000 2,808
16 February 2026readyApartment · 2 BR 1,206 4,580,000 3,798
6 February 2026readyApartment · 2 BR 1,200 3,650,000 3,042
6 January 2026readyApartment · 1 BR 800 2,400,000 3,000
31 December 2025readyApartment · 1 BR 779 2,380,000 3,055
12 December 2025readyApartment · 2 BR 1,198 3,350,000 2,796

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationJumeira First · Dubai Municipality community

Beach · 650 mLa Mer Beach · 690 mBooba · 780 mFranprix · 820 mSpinneys · 1.1 kmJumeirah Center · 1.1 kmJumeirah Plaza · 1.1 kmCentury Plaza · 1.2 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationWorld Trade Centre Metro Station · Red Metro line · 3.3 km
MallJumeirah Center · 1.1 km
SupermarketBooba · 780 m
HospitalIranian Hospital Dubai · 1.7 km
SchoolJumeirah Baccalaureate School · 2.1 km
ParkAl Wasl Park · 1.9 km
BeachBeach · 650 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 6, with 196 units and villas.

2027: 02029: 196

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Jumeira First: 7

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Solaya (1,2,3) 0% Jun 2029 — 67
Solaya (4,6) 0% Sep 2029 7,040 40
Jumeirah Asora Bay 4.4% Mar 2029 — 30
Solaya (5,7) 0% Sep 2029 — 22
Project 4610, Jumeirah First 70% Feb 2027 — 0
Jumeirah Residences - Asora Bay - Ocean Mansions 0.5% Mar 2029 — 0
Project 4614, Jumeirah First 0% Apr 2030 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Jumeira First

Developer in DLD data Pdlm Residential L.L.C · DLD developer no. 1253

Projects registered
7
7 completed · 0 under construction · 0 not started
Units delivered
1,516
0 in the pipeline
Median build time
30 months
completed projects measured: 7

Completed a month or more after their DLD end date: 1 of 7 completed projects with both dates. In 6 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in La Mer

DLD lists 14 projects in the master project La Mer.

Jumeirah Asora BayUnder construction · 4.4% · Mar 2029
Solaya (1,2,3)Not started · 0% · Jun 2029
Solaya (5,7)Not started · 0% · Sep 2029
Solaya (4,6)Not started · 0% · Sep 2029
Project 4614, Jumeirah FirstPending · 0% · Apr 2030
Sur La MerCompleted · 100% · Aug 2021
Port de La Mer - La CoteCompleted · 100% · Sep 2021
Port De La Mer - La VoileCompleted · 100% · Apr 2022
Port de La Mer - Le PontCompleted · 100% · Jul 2022
La RiveCompleted · 100% · Oct 2022
Sur La Mer 2Completed · 100% · Nov 2022

Questions about Port De La Mer - La Sirene 2

When was Port De La Mer - La Sirene 2 completed?

Port De La Mer - La Sirene 2 is recorded as completed on 6 June 2024 (DLD register of 1 November 2026).

Who is the developer of Port De La Mer - La Sirene 2?

Pdlm Residential L.L.C, as registered with DLD.

What is the DLD project number of Port De La Mer - La Sirene 2?

2299.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error