DLD master projectJumeira First
La Mer 6 of 15 phases not yet completed · 196 units · 542 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
La Mer has 15 projects in the Dubai Land Department projects register as of 1 November 2026: 6 not yet completed, with 196 units and villas. By DLD status: Completed 9 · Not started 4 · Under construction 1 · Pending 1.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 14 of the 15 phases: those with a map pin. Pins mark approximate locations.
Jumeira First (DM community)
Phases (15)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Port De La Mer - Le Soleil | Completed | 100% | Jan 2026 | — | 184 | 76 | +34.9% |
| Solaya (1,2,3) | Not started | 0% | Jun 2029 31 months to go | 31 months to go | 67 | 67 | — |
| Port de La Mer - La Cote | Completed | 100% | Sep 2021 | — | 429 | 63 | — |
| La Rive | Completed | 100% | Oct 2022 | — | 284 | 55 | — |
| Port De La Mer - La Sirene 2 | Completed | 100% | Jun 2024 | — | 130 | 49 | +38.5% |
| Port De La Mer - La Voile | Completed | 100% | Apr 2022 | — | 183 | 43 | — |
| Port De La Mer - La Sirene | Completed | 100% | Feb 2024 | — | 151 | 41 | +26.2% |
| Solaya (4,6) | Not started | 0% | Sep 2029 34 months to go | 34 months to go | 44 | 40 | — |
| Jumeirah Asora Bay | Under construction | 4.4% | Mar 2029 28 months to go | 28 months to go | 30 | 30 | — |
| Port de La Mer - Le Pont | Completed | 100% | Jul 2022 | — | 155 | 30 | — |
| Solaya (5,7) | Not started | 0% | Sep 2029 34 months to go | 34 months to go | 55 | 22 | — |
| Sur La Mer | Completed | 100% | Aug 2021 | — | 113 | 19 | — |
| Sur La Mer 2 | Completed | 100% | Nov 2022 | — | 34 | 7 | — |
| Jumeirah Residences - Asora Bay - Ocean Mansions | Not started | 0.5% | Mar 2029 28 months to go | 28 months to go | 0 | 0 | — |
| Project 4614, Jumeirah First | Pending | 0% | Apr 2030 41 months to go | 41 months to go | 0 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
6 phases| DLD end year | Projects | Units |
|---|---|---|
| 2029 | 5 | 196 |
| 2030 | 1 | 0 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.