Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4089Not started67 units

Solaya (1,2,3) (3، 2، 1) سولايا Jumeirah First · La Mer by La Mer North Property CO. L.L.CAll phases of La Mer DLD status: Not started (DLD register as of 1 November 2026) DLD end date Jun 2029 31 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0%
DLD register, 1 November 2026
Registered start
Jan 2026
DLD end date Jun 2029
Latest sales
6,880 AED/sqft
65 sales
2 BR estimate
14.34–16.35 M AED
Automated estimate, not a valuation
Developer
1 project
0 completed · 0 units delivered

Completion

DLD status: Not started. 0% built, DLD end date 30 June 2029. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0% 30 June 2029Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
4089
Escrow agent
Commercial Bank of Dubai(PSC)
Zoning authority
Dubai Development Authority (DDA)
Master project
La Mer
DLD area
Jumeirah First
Units · villas
67 · 0
Start → DLD end
Jan 2026 → Jun 2029
Registered units2 bed 14 · 3 bed 22 · 4 bed 24 · 5+ bed 7; sizes 3,162–5,233 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: - 3 Residential Buildings comprising of 67 Residential units (2BHK=14, 3BHK=22, 4BHK=24, 5BHK=4, PH=3) - Solaya 1 : B+G+6+R (18# -Resi. Units). - Solaya 2 : B+G+7+R (22# - Resi. Units). - Solaya 3 : B+G+8+R (27# - Resi. Units).

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 home sales after the launch window in the last 12 months, so no comparison is shown.

Dubai Statistics Center residential price index (flats), 2025-Q4 to 2026-Q2: -0.9%.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
2 BR 7,108 (13) 6,955 (13) -2.2%
3 BR 6,791 (20) 6,846 (21) +0.8%
4 BR 6,904 (24) 6,904 (24) 0%
5 BR 6,724 (6) 6,818 (7) +1.4%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
2 BR 14 6,955 (13) Nov 2025 – Nov 2026
3 BR 21 6,846 (21) Nov 2025 – Nov 2026
4 BR 25 6,904 (24) Nov 2025 – Nov 2026
5 BR 7 6,818 (7) Nov 2025 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2025-Q4 → 2026-Q3

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Jumeirah First, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents in DLD area Jumeirah First

New Ejari rent contracts for apartments across DLD area Jumeirah First, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 54,000 26 +8%
1 BR AED 105,000 358 -12.5%
2 BR AED 180,000 302 -3.2%
3 BR AED 240,000 63 +4.3%
4 BR AED 500,000 8 —

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 65 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
3 July 2026off-planApartment · 4 BR 4,604 31,192,000 6,775
24 March 2026off-planApartment · 5 BR 11,567 84,642,000 7,318
11 March 2026off-planApartment · 2 BR 2,139 14,671,000 6,859
19 February 2026off-planApartment · 3 BR 3,189 22,834,000 7,160
2 February 2026off-planApartment · 5 BR 6,979 47,797,000 6,849
28 January 2026off-planApartment · 3 BR 3,165 21,086,000 6,662
21 January 2026off-planApartment · 4 BR 4,540 31,909,000 7,028
21 January 2026off-planApartment · 3 BR 3,189 22,947,000 7,196
21 January 2026off-planApartment · 2 BR 2,149 14,390,000 6,696
15 January 2026off-planApartment · 3 BR 6,439 44,460,000 6,905

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Looking for a unit in this or similar projects?

Tell us what you are looking for in Solaya (1,2,3) or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Estimated value range
Bedrooms Range, AED Based on Compared at
2 BR 14,340,000 – 16,350,000 29 sales, 12 months This project
3 BR 22,700,000 – 27,360,000 45 sales, 12 months This project
4 BR 31,190,000 – 35,240,000 41 sales, 12 months This project
5 BR 48,020,000 – 81,890,000 12 sales, 12 months This project
Automated estimate, not a valuation

Estimate as of 5 November 2026 Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Jun 2029); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Jun 2029
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in Solaya (1,2,3)? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationJumeira First · Dubai Municipality community

Booba · 90 mFranprix · 120 mBeach · 200 mLa Mer Beach · 270 mSpinneys · 360 mJumeirah Center · 380 mJumeirah Plaza · 460 mCentury Plaza · 560 mIranian Hospital Dubai · 950 mAl Wasl Park · 1.3 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationWorld Trade Centre Metro Station · Red Metro line · 2.6 km
MallJumeirah Center · 380 m
SupermarketBooba · 90 m
HospitalIranian Hospital Dubai · 950 m
SchoolJumeirah Baccalaureate School · 1.6 km
ParkAl Wasl Park · 1.3 km
BeachBeach · 200 m

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 4, with 129 units and villas.

2027: 02029: 129

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Jumeira First: 6

Open projects in the same DLD area with a DLD end year from 2028 to 2030, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Solaya (4,6) 0% Sep 2029 7,040 40
Jumeirah Asora Bay 4.4% Mar 2029 — 30
Solaya (5,7) 0% Sep 2029 — 22
Jumeirah Residences - Asora Bay - Ocean Mansions 0.5% Mar 2029 — 0
Project 4614, Jumeirah First 0% Apr 2030 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Jumeira First

Developer in DLD data La Mer North Property CO. L.L.C · DLD developer no. 1824

Projects registered
1
0 completed · 0 under construction · 1 not started
Units delivered
0
67 in the pipeline

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error