Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2157Completed286 units

Greenview غرين فيو Madinat Al Mataar · Dubai World Central by Emaar Dubai South DWC LLCAll phases of Dubai World Central Completed 18 January 2024 (DLD) DLD end date Jan 2024 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Jan 2024
DLD end date Jan 2024
Build time
53 months
Sep 2019 → Jan 2024
Latest sales
1,119 AED/sqft
5 sales
3 BR rent
110,000 AED/yr
81 leases, 12 months
Developer
35 projects
12 completed · 3,201 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3). Latest DLD inspection: 100% built on 16 March 2024 (inspections: 11).
Every DLD inspection and every change in the register %, newest first
Date % built Source
16 March 2024 100% DLD inspection
11 December 2023 90.2% DLD inspection
7 August 2023 67.7% DLD inspection
13 April 2023 43.4% DLD inspection
19 December 2022 20.2% DLD inspection
30 August 2022 12.2% DLD inspection
26 April 2022 8% DLD inspection
31 May 2021 7.3% DLD inspection
24 February 2021 3.1% DLD inspection
18 February 2020 0.5% DLD inspection
4 November 2019 0.1% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
53 monthsActual build
53 months
Start date
1 September 2019
DLD end date
18 January 2024
Completion date
18 January 2024
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
2157
Escrow agent
Mashreq Bank PSC
Zoning authority
Dubai South
Master project
Dubai World Central
DLD area
Madinat Al Mataar
Units · villas
0 · 286
Start → DLD end
Sep 2019 → Jan 2024
Registered units3 bed 194 · 4 bed 92; sizes 1,960–2,424 sqft

Homes: villas 286.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: PROJECT CONSISTS OF (G+1)X 286 RESIDENTIAL TOWN HOUSES LOCATED IN MADINAT AL MATAAR. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

This project's first registered off-plan sale is before 1 March 2020, near the start of our sales data, so its launch may be older and no launch price is shown.

Prices are over villas and townhouses, the type most sales in this project are.

Registered sales of villas and townhouses by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
3 BR 48 1,634 (9) Nov 2025 – Nov 2026
4 BR 20 1,050 (9) Nov 2025 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q1 → 2026-Q4

Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Madinat Al Mataar, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for villas and townhouses in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
3 BR AED 110,000 81 0%
4 BR AED 145,000 35 -3.3%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 22; registered amount AED 45.4M.

Since the first registration in 2024-Q3: 123 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 18 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
26 October 2026readyVilla · 3 BR 1,518 2,200,000 1,449
13 October 2026readyVilla · 4 BR 3,173 3,200,000 1,009
8 October 2026readyVilla · 3 BR 1,483 2,342,500 1,580
15 July 2026readyVilla · 4 BR 2,546 2,850,000 1,119
20 May 2026readyVilla · 4 BR 4,093 3,150,000 770
4 May 2026readyVilla · 4 BR 2,546 1,600,000 628
6 April 2026readyVilla · 4 BR 3,428 3,600,000 1,050
11 March 2026readyVilla · 4 BR 2,823 3,300,000 1,169
11 March 2026readyVilla · 3 BR 1,483 2,750,000 1,854
24 February 2026readyVilla · 4 BR 3,038 3,400,000 1,119

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationMadinat Al Mataar · Dubai Municipality community

No exact location yet.

Nearest places (DLD)

Nearest landmarkAl Makhtoum International Airport

As DLD lists it for the area in its sales records.

New homes in the community

Units by DLD end year

2019: 1082020: 2092023: 802025: 2,2582026: 7,9872027: 12,6382028: 6,9892029: 8,4492030: 2,322No end date: 4,818

Units and villas in open projects of Madinat Al Mataar, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Madinat Al Mataar: 168

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Azizi Venice 14 30.3% May 2026 1,649 2,546
Azizi Venice 6 11.6% Dec 2027 2,032 1,302
Azizi Venice 7 29.2% Jan 2026 1,849 1,180
Terra Heights 9.1% Mar 2029 1,994 1,017
Azizi Venice 15 0% May 2027 1,715 904
azizi venice 13 45.9% Sep 2027 1,675 797
Azizi Venice 10 36.3% — 1,707 776
azizi venice 12 21.6% Sep 2027 1,685 753
Azizi Venice 11 25.9% Aug 2027 1,667 696
Terra Gardens 0.1% Oct 2029 2,127 544
Terra Woods 0% Mar 2030 2,200 505
South Square 2.6% Jun 2028 1,473 428

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Madinat Al Mataar

Developer in DLD data Emaar Dubai South DWC LLC · DLD developer no. 1155

Projects registered
35
12 completed · 16 under construction · 7 not started
Units delivered
3,201
5,540 in the pipeline
Median build time
34 months
completed projects measured: 12
Past the DLD end date
0
of 13 under construction with a DLD end date

Completed a month or more after their DLD end date: 0 of 12 completed projects with both dates. In 10 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Emaar Dubai South DWC LLC is one of 7 DLD-registered developers we list together as Emaar. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Dubai World Central

DLD lists 72 projects in the master project Dubai World Central.

Discovery DunesUnder construction · 70% · Dec 2023
Azizi Venice 5Under construction · 63.5% · Oct 2025
Azizi Venice 4Under construction · 62.2% · Dec 2025
Azizi Venice 2Under construction · 57.2% · Dec 2025
Azizi Venice 1Under construction · 67.4% · Dec 2025
Azizi Venice 3Under construction · 76% · Dec 2025
Azizi Venice 7Under construction · 29.2% · Jan 2026
Expo City ValleyUnder construction · 66% · Jan 2026
Azizi Venice 14Under construction · 30.3% · May 2026
Fairway Villas 2Under construction · 92.2% · Dec 2026
Azizi Venice 11Under construction · 25.9% · Aug 2027
azizi venice 13Under construction · 45.9% · Sep 2027

Questions about Greenview

When was Greenview completed?

Greenview is recorded as completed on 18 January 2024 (DLD register of 1 November 2026).

Who is the developer of Greenview?

Emaar Dubai South DWC LLC, as registered with DLD.

What is the DLD project number of Greenview?

2157.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error