DLD master projectMadinat Al Mataar
Dubai World Central 61 of 73 phases not yet completed · 30,812 units · 17,212 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Dubai World Central has 73 projects in the Dubai Land Department projects register as of 1 November 2026: 61 not yet completed, with 30,812 units and villas. By DLD status: Under construction 41 · Not started 17 · Completed 12 · Pending 3. Under construction and past the DLD end date: 9.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 65 of the 73 phases: those with a map pin. Pins mark approximate locations.
Madinat Al Mataar (DM community)
Phases (73)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Azizi Venice 14 | Under construction | 30.3% | May 2026 5 months past it | 5 months past it | 3,438 | 2,546 | +6.3% |
| Azizi Venice 6 | Under construction | 11.6% | Dec 2027 13 months to go | 13 months to go | 2,965 | 1,302 | +3.4% |
| Azizi Venice 7 | Under construction | 29.2% | Jan 2026 9 months past it | 9 months past it | 2,276 | 1,180 | +17.6% |
| Azizi Venice 15 | Not started | 0% | May 2027 6 months to go | 6 months to go | 1,855 | 904 | +6.4% |
| azizi venice 13 | Under construction | 45.9% | Sep 2027 10 months to go | 10 months to go | 1,888 | 797 | +4.4% |
| Azizi Venice 10 | Under construction | 36.3% | — | — | 1,263 | 776 | +8.9% |
| azizi venice 12 | Under construction | 21.6% | Sep 2027 10 months to go | 10 months to go | 1,428 | 753 | +2.1% |
| Azizi Venice 11 | Under construction | 25.9% | Aug 2027 9 months to go | 9 months to go | 1,094 | 696 | +7.2% |
| Azizi Venice 9 | Under construction | 54% | — | — | 778 | 428 | +8.4% |
| South Square | Under construction | 2.6% | Jun 2028 19 months to go | 19 months to go | 571 | 428 | +0.9% |
| Azizi Venice 8 | Under construction | 53% | — | — | 778 | 372 | -2.7% |
| Azizi Venice 16 | Not started | 0% | Jun 2027 7 months to go | 7 months to go | 1,055 | 310 | -1% |
| Azizi Venice 5 | Under construction | 63.5% | Oct 2025 12 months past it | 12 months past it | 484 | 309 | -2.8% |
| Azizi Venice 2 | Under construction | 57.2% | Dec 2025 10 months past it | 10 months past it | 526 | 264 | — |
| Expo Valley Views | Not started | 0% | Oct 2029 35 months to go | 35 months to go | 490 | 255 | +0.3% |
| Greenspoint 2 | Under construction | 40.1% | Mar 2029 28 months to go | 28 months to go | 244 | 245 | — |
| Golf Vale | Not started | 0% | Mar 2030 40 months to go | 40 months to go | 262 | 238 | +17.9% |
| Waada - Altura 2 | Under construction | 7.2% | Mar 2029 28 months to go | 28 months to go | 365 | 237 | +3.1% |
| Waada - Altura 1 | Under construction | 1.9% | Apr 2029 29 months to go | 29 months to go | 381 | 222 | +0.7% |
| Greenspoint | Under construction | 42.9% | Mar 2029 28 months to go | 28 months to go | 196 | 197 | — |
| Hayat 4 | Under construction | 4.5% | Jul 2028 20 months to go | 20 months to go | 200 | 194 | -13% |
| Golf Meadow | Under construction | 4.5% | Jul 2029 32 months to go | 32 months to go | 188 | 183 | — |
| Greenridge | Under construction | 35.6% | Dec 2028 25 months to go | 25 months to go | 520 | 182 | 0% |
| Golf Dale | Not started | 0.3% | Dec 2028 25 months to go | 25 months to go | 200 | 182 | — |
| Golf Hills 2 | Under construction | 4.2% | Sep 2029 34 months to go | 34 months to go | 204 | 181 | +4.2% |
| Golf Fields | Not started | 0% | Feb 2030 39 months to go | 39 months to go | 181 | 181 | — |
| Waada - Cascada 1 | Under construction | 1.6% | Oct 2028 23 months to go | 23 months to go | 249 | 178 | +3.2% |
| Golf Hills | Under construction | 3.7% | Sep 2029 34 months to go | 34 months to go | 204 | 178 | -1% |
| Golf Verge | Under construction | 4.2% | May 2029 30 months to go | 30 months to go | 204 | 177 | +14.4% |
| Golf Edge | Not started | 0% | Feb 2029 27 months to go | 27 months to go | 179 | 168 | — |
| Azizi Venice 4 | Under construction | 62.2% | Dec 2025 10 months past it | 10 months past it | 389 | 167 | +3.1% |
| Vista Ridge | Not started | 0% | Sep 2029 34 months to go | 34 months to go | 198 | 161 | -1.9% |
| Grove Ridge | Not started | 0% | Sep 2029 34 months to go | 34 months to go | 193 | 160 | -0.3% |
| Greenville 2 | Under construction | 47.3% | Mar 2029 28 months to go | 28 months to go | 148 | 150 | — |
| Waada - Rayhan 1 | Under construction | 15.1% | Oct 2028 23 months to go | 23 months to go | 287 | 144 | 0% |
| Hayat 2 | Under construction | 2% | May 2028 18 months to go | 18 months to go | 142 | 142 | -2% |
| Hayat 3 | Under construction | 3.9% | May 2028 18 months to go | 18 months to go | 144 | 141 | — |
| Greenville | Under construction | 46% | Mar 2029 28 months to go | 28 months to go | 140 | 140 | — |
| Hayat 1 | Not started | 0% | Mar 2029 28 months to go | 28 months to go | 122 | 117 | — |
| Golf Acres | Under construction | 3.5% | Dec 2028 25 months to go | 25 months to go | 158 | 113 | — |
| Hayat 5 | Not started | 0% | Jul 2028 20 months to go | 20 months to go | 112 | 109 | +1.9% |
| Golf Trails | Not started | 0% | Oct 2030 47 months to go | 47 months to go | 161 | 97 | — |
| Hayat 6 | Not started | 0% | Mar 2029 28 months to go | 28 months to go | 104 | 93 | — |
| Golf Point | Under construction | 4.8% | Oct 2028 23 months to go | 23 months to go | 590 | 87 | +1.3% |
| Greenview 3 | Completed | 100% | Oct 2025 | — | 241 | 87 | +95% |
| Waada - Cascada 2 | Not started | 0% | Mar 2029 28 months to go | 28 months to go | 249 | 84 | +0.3% |
| Azizi Venice 3 | Under construction | 76% | Dec 2025 10 months past it | 10 months past it | 352 | 83 | -1.1% |
| Greenview 2 | Completed | 100% | Jan 2024 | — | 292 | 80 | — |
| Parkside 2 | Completed | 100% | Jun 2023 | — | 422 | 79 | — |
| Parkside 3 | Completed | 100% | May 2022 | — | 365 | 78 | — |
| Parkside | Completed | 100% | Dec 2021 | — | 371 | 71 | — |
| Greenview | Completed | 100% | Jan 2024 | — | 286 | 68 | — |
| Urbana Iii | Completed | 100% | May 2020 | — | 372 | 67 | — |
| Azizi Venice 1 | Under construction | 67.4% | Dec 2025 10 months past it | 10 months past it | 143 | 66 | — |
| Greenway 2 | Under construction | 34.4% | May 2028 18 months to go | 18 months to go | 492 | 59 | +2.6% |
| Expo City Valley | Under construction | 66% | Jan 2026 9 months past it | 9 months past it | 528 | 50 | +16% |
| Golf Views | Completed | 100% | May 2020 | — | 291 | 50 | — |
| Waada- Raiha | Under construction | 7% | Oct 2028 23 months to go | 23 months to go | 132 | 42 | +7.7% |
| Urbana | Completed | 100% | Sep 2019 | — | 324 | 42 | — |
| Golf Links | Completed | 100% | May 2020 | — | 1 | 32 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
61 phases| DLD end year | Projects | Units |
|---|---|---|
| 2023 | 1 | 80 |
| 2025 | 5 | 1,894 |
| 2026 | 4 | 6,242 |
| 2027 | 6 | 10,285 |
| 2028 | 13 | 3,797 |
| 2029 | 19 | 4,085 |
| 2030 | 6 | 732 |
| No end date | 7 | 3,697 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Dubai World Central
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology