DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectMadinat Al Mataar

Dubai World Central 61 of 73 phases not yet completed · 30,812 units · 17,212 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Dubai World Central has 73 projects in the Dubai Land Department projects register as of 1 November 2026: 61 not yet completed, with 30,812 units and villas. By DLD status: Under construction 41 · Not started 17 · Completed 12 · Pending 3. Under construction and past the DLD end date: 9.

Phases
73
12 completed
Not yet completed
61
41 under construction
Units not yet completed
30,812
units and villas · 4,547
Sales, 24 mo
17,212
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 65 of the 73 phases: those with a map pin. Pins mark approximate locations.

Azizi Venice 14 · Under construction · Project locationAzizi Venice 6 · Under construction · Project locationAzizi Venice 7 · Under construction · Project locationAzizi Venice 15 · Not started / Pending · Project locationazizi venice 13 · Under construction · Project locationAzizi Venice 10 · Under construction · Project locationazizi venice 12 · Under construction · Project locationAzizi Venice 11 · Under construction · Project locationAzizi Venice 9 · Under construction · Project locationSouth Square · Under construction · Project locationAzizi Venice 8 · Under construction · Project locationAzizi Venice 16 · Not started / Pending · Project locationAzizi Venice 5 · Under construction · Project locationAzizi Venice 2 · Under construction · Project locationExpo Valley Views · Not started / Pending · Approximate project locationGreenspoint 2 · Under construction · Approximate project locationGolf Vale · Not started / Pending · Approximate project locationWaada - Altura 2 · Under construction · Project locationWaada - Altura 1 · Under construction · Project locationGreenspoint · Under construction · Approximate project locationHayat 4 · Under construction · Approximate project locationGolf Meadow · Under construction · Approximate project locationGreenridge · Under construction · Approximate project locationGolf Dale · Not started / Pending · Approximate project locationGolf Hills 2 · Under construction · Approximate project locationGolf Fields · Not started / Pending · Approximate project locationWaada - Cascada 1 · Under construction · Project locationGolf Hills · Under construction · Approximate project locationGolf Verge · Under construction · Approximate project locationGolf Edge · Not started / Pending · Approximate project locationAzizi Venice 4 · Under construction · Project locationVista Ridge · Not started / Pending · Approximate project locationGrove Ridge · Not started / Pending · Approximate project locationGreenville 2 · Under construction · Approximate project locationWaada - Rayhan 1 · Under construction · Approximate project locationHayat 2 · Under construction · Approximate project locationHayat 3 · Under construction · Approximate project locationGreenville · Under construction · Approximate project locationHayat 1 · Not started / Pending · Approximate project locationGolf Acres · Under construction · Approximate project locationHayat 5 · Not started / Pending · Approximate project locationGolf Trails · Not started / Pending · Approximate project locationHayat 6 · Not started / Pending · Approximate project locationGolf Point · Under construction · Approximate project locationGreenview 3 · Completed · Approximate project locationWaada - Cascada 2 · Not started / Pending · Project locationAzizi Venice 3 · Under construction · Project locationAzizi Venice 1 · Under construction · Project locationGreenway 2 · Under construction · Approximate project locationExpo City Valley · Under construction · Approximate project locationGolf Views · Completed · Approximate project locationWaada- Raiha · Under construction · Approximate project locationGolf Links · Completed · Approximate project locationHayat 7 · Not started / Pending · Approximate project locationGolf Lane · Under construction · Approximate project locationGreenway · Under construction · Approximate project locationFairway Villas 3 · Under construction · Approximate project locationFairway Villas 2 · Under construction · Approximate project locationDiscovery Dunes · Under construction · Approximate project locationExpo Valley Views 2 · Not started / Pending · Approximate project locationExpo Valley Views 1 · Not started / Pending · Approximate project locationProject 3044, Madinat Al Mataar · Not started / Pending · Project locationProject 4609, Madinat Al Mataar · Not started / Pending · Approximate project locationProject 4612, Madinat Al Mataar · Not started / Pending · Approximate project locationFairway Villas · Completed · Approximate project location© OpenStreetMap contributors · Dubai Municipality · Makani
Under construction Not started / Pending Completed Approximate project locations

Madinat Al Mataar (DM community)

Phases (73)Ordered by registered sales over 24 months

Phases (73)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Azizi Venice 14Under construction 30.3% May 2026 5 months past it 5 months past it 3,438 2,546 +6.3%
Azizi Venice 6Under construction 11.6% Dec 2027 13 months to go 13 months to go 2,965 1,302 +3.4%
Azizi Venice 7Under construction 29.2% Jan 2026 9 months past it 9 months past it 2,276 1,180 +17.6%
Azizi Venice 15Not started 0% May 2027 6 months to go 6 months to go 1,855 904 +6.4%
azizi venice 13Under construction 45.9% Sep 2027 10 months to go 10 months to go 1,888 797 +4.4%
Azizi Venice 10Under construction 36.3% — — 1,263 776 +8.9%
azizi venice 12Under construction 21.6% Sep 2027 10 months to go 10 months to go 1,428 753 +2.1%
Azizi Venice 11Under construction 25.9% Aug 2027 9 months to go 9 months to go 1,094 696 +7.2%
Azizi Venice 9Under construction 54% — — 778 428 +8.4%
South SquareUnder construction 2.6% Jun 2028 19 months to go 19 months to go 571 428 +0.9%
Azizi Venice 8Under construction 53% — — 778 372 -2.7%
Azizi Venice 16Not started 0% Jun 2027 7 months to go 7 months to go 1,055 310 -1%
Azizi Venice 5Under construction 63.5% Oct 2025 12 months past it 12 months past it 484 309 -2.8%
Azizi Venice 2Under construction 57.2% Dec 2025 10 months past it 10 months past it 526 264 —
Expo Valley ViewsNot started 0% Oct 2029 35 months to go 35 months to go 490 255 +0.3%
Greenspoint 2Under construction 40.1% Mar 2029 28 months to go 28 months to go 244 245 —
Golf ValeNot started 0% Mar 2030 40 months to go 40 months to go 262 238 +17.9%
Waada - Altura 2Under construction 7.2% Mar 2029 28 months to go 28 months to go 365 237 +3.1%
Waada - Altura 1Under construction 1.9% Apr 2029 29 months to go 29 months to go 381 222 +0.7%
GreenspointUnder construction 42.9% Mar 2029 28 months to go 28 months to go 196 197 —
Hayat 4Under construction 4.5% Jul 2028 20 months to go 20 months to go 200 194 -13%
Golf MeadowUnder construction 4.5% Jul 2029 32 months to go 32 months to go 188 183 —
GreenridgeUnder construction 35.6% Dec 2028 25 months to go 25 months to go 520 182 0%
Golf DaleNot started 0.3% Dec 2028 25 months to go 25 months to go 200 182 —
Golf Hills 2Under construction 4.2% Sep 2029 34 months to go 34 months to go 204 181 +4.2%
Golf FieldsNot started 0% Feb 2030 39 months to go 39 months to go 181 181 —
Waada - Cascada 1Under construction 1.6% Oct 2028 23 months to go 23 months to go 249 178 +3.2%
Golf HillsUnder construction 3.7% Sep 2029 34 months to go 34 months to go 204 178 -1%
Golf VergeUnder construction 4.2% May 2029 30 months to go 30 months to go 204 177 +14.4%
Golf EdgeNot started 0% Feb 2029 27 months to go 27 months to go 179 168 —
Azizi Venice 4Under construction 62.2% Dec 2025 10 months past it 10 months past it 389 167 +3.1%
Vista RidgeNot started 0% Sep 2029 34 months to go 34 months to go 198 161 -1.9%
Grove RidgeNot started 0% Sep 2029 34 months to go 34 months to go 193 160 -0.3%
Greenville 2Under construction 47.3% Mar 2029 28 months to go 28 months to go 148 150 —
Waada - Rayhan 1Under construction 15.1% Oct 2028 23 months to go 23 months to go 287 144 0%
Hayat 2Under construction 2% May 2028 18 months to go 18 months to go 142 142 -2%
Hayat 3Under construction 3.9% May 2028 18 months to go 18 months to go 144 141 —
GreenvilleUnder construction 46% Mar 2029 28 months to go 28 months to go 140 140 —
Hayat 1Not started 0% Mar 2029 28 months to go 28 months to go 122 117 —
Golf AcresUnder construction 3.5% Dec 2028 25 months to go 25 months to go 158 113 —
Hayat 5Not started 0% Jul 2028 20 months to go 20 months to go 112 109 +1.9%
Golf TrailsNot started 0% Oct 2030 47 months to go 47 months to go 161 97 —
Hayat 6Not started 0% Mar 2029 28 months to go 28 months to go 104 93 —
Golf PointUnder construction 4.8% Oct 2028 23 months to go 23 months to go 590 87 +1.3%
Greenview 3Completed 100% Oct 2025 — 241 87 +95%
Waada - Cascada 2Not started 0% Mar 2029 28 months to go 28 months to go 249 84 +0.3%
Azizi Venice 3Under construction 76% Dec 2025 10 months past it 10 months past it 352 83 -1.1%
Greenview 2Completed 100% Jan 2024 — 292 80 —
Parkside 2Completed 100% Jun 2023 — 422 79 —
Parkside 3Completed 100% May 2022 — 365 78 —
ParksideCompleted 100% Dec 2021 — 371 71 —
GreenviewCompleted 100% Jan 2024 — 286 68 —
Urbana IiiCompleted 100% May 2020 — 372 67 —
Azizi Venice 1Under construction 67.4% Dec 2025 10 months past it 10 months past it 143 66 —
Greenway 2Under construction 34.4% May 2028 18 months to go 18 months to go 492 59 +2.6%
Expo City ValleyUnder construction 66% Jan 2026 9 months past it 9 months past it 528 50 +16%
Golf ViewsCompleted 100% May 2020 — 291 50 —
Waada- RaihaUnder construction 7% Oct 2028 23 months to go 23 months to go 132 42 +7.7%
UrbanaCompleted 100% Sep 2019 — 324 42 —
Golf LinksCompleted 100% May 2020 — 1 32 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

61 phases
2023: 802025: 1,8942026: 6,2422027: 10,2852028: 3,7972029: 4,0852030: 732No end date: 3,697

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Dubai World Central

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology