DLD project no. 2413Under construction127 units
Verdana(Phase 2) فيردانا (المرحلة الثانية) 94% built (DLD register as of 1 November 2026) · DLD end date Dec 2025 · past its DLD end date by 10 months DLD register as of 1 November 2026. DLD still lists the project as under construction.
CompletionDLD readings of % built, beside the share of the planned period gone
% built and period elapsed
1 November 2026Two separate measures: one is DLD's % built, the other is time on the calendar.
| Date | % built | Source |
|---|---|---|
| 3 June 2026 | 94% | DLD inspection |
| 11 February 2026 | 90.7% | DLD inspection |
| 20 October 2025 | 82.5% | DLD inspection |
| 17 March 2025 | 55.5% | DLD inspection |
| 6 November 2024 | 44.8% | DLD inspection |
| 4 June 2024 | 24% | DLD inspection |
| 12 May 2024 | 21% | DLD register, archived export |
| 26 March 2024 | 20.6% | DLD inspection |
| 6 December 2023 | 10.1% | DLD inspection |
| 25 September 2023 | 5.1% | DLD inspection |
| 26 July 2023 | 3.7% | DLD inspection |
| 2 March 2023 | 0.4% | DLD inspection |
| 9 November 2022 | 0.2% | DLD inspection |
| 5 August 2022 | 0% | DLD register, archived export |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.
Our completion calculation
Pace since the last two DLD readings: —
Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Changes in the DLD register
Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.
Inspection photos and reports
DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.
CraneScore links to DLD and does not copy or host its photos or reports.
Building permits
307 of 307 buildingsBuildings on the project’s plots: 307, on construction permits: 1, as Dubai Municipality lists them.
Furthest stage reached: Final works.
| Work stage | Buildings |
|---|---|
| Final works | 307 |
Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.
DLD registration
DLD services ↗Homes: villas 127.
Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: 127 (G+2F+R) + Gym Townhouses , The project designed to have a concrete structure and block with internal and external finishes.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
Dubai Statistics Center residential price index (villas), 2022-Q3 to 2026-Q2: +54.3%.
Prices are over villas and townhouses, the type most sales in this project are.
| Bedrooms | Launch price | Latest registered sales | Change |
|---|---|---|---|
| 4 BR | 1,540 (49) | 2,072 (8) | +34.5% |
| Bedrooms | Sales, 24 months | Latest median AED/sqft | Latest sales |
|---|---|---|---|
| 4 BR | 25 | 2,072 (8) | May 2026 – Nov 2026 |
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Median AED/sqft by quarter
2022-Q3 → 2026-Q4| Quarter | Registered sales | Median AED/sqft | DLD area Dubai Investment Park First |
|---|---|---|---|
| 2022-Q3 | 9 (off-plan 9, ready 0) | 1,165 | 1,159 |
| 2022-Q4 | 40 (off-plan 40, ready 0) | 1,564 | 1,520 |
| 2023-Q1 | 17 (off-plan 17, ready 0) | 1,585 | 1,361 |
| 2023-Q2 | 9 (off-plan 9, ready 0) | 1,673 | 1,588 |
| 2023-Q3 | 6 (off-plan 6, ready 0) | 1,563 | 1,563 |
| 2023-Q4 | 1 (off-plan 1, ready 0) | — | 1,533 |
| 2024-Q1 | 6 (off-plan 6, ready 0) | 1,475 | 884 |
| 2024-Q2 | 2 (off-plan 2, ready 0) | — | 909 |
| 2024-Q3 | 6 (off-plan 6, ready 0) | 1,478 | 1,279 |
| 2024-Q4 | 1 (off-plan 1, ready 0) | — | 872 |
| 2025-Q1 | 2 (off-plan 2, ready 0) | — | 1,330 |
| 2025-Q2 | 2 (off-plan 2, ready 0) | — | 1,596 |
| 2025-Q3 | 7 (off-plan 7, ready 0) | 1,973 | 1,667 |
| 2025-Q4 | 5 (off-plan 5, ready 0) | 1,549 | 1,461 |
| 2026-Q1 | 1 (off-plan 1, ready 0) | — | 1,162 |
| 2026-Q2 | 4 (off-plan 4, ready 0) | — | 1,237 |
| 2026-Q3 | 2 (off-plan 2, ready 0) | — | 1,196 |
| 2026-Q4 | 2 (off-plan 2, ready 0) | — | 1,204 |
Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Dubai Investment Park First, median AED/sqft of off-plan sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Registered sales per quarter
| Quarter | Registered sales | Median AED/sqft | DLD area Dubai Investment Park First |
|---|---|---|---|
| 2022-Q3 | 9 (off-plan 9, ready 0) | 1,165 | 1,159 |
| 2022-Q4 | 40 (off-plan 40, ready 0) | 1,564 | 1,520 |
| 2023-Q1 | 17 (off-plan 17, ready 0) | 1,585 | 1,361 |
| 2023-Q2 | 9 (off-plan 9, ready 0) | 1,673 | 1,588 |
| 2023-Q3 | 6 (off-plan 6, ready 0) | 1,563 | 1,563 |
| 2023-Q4 | 1 (off-plan 1, ready 0) | — | 1,533 |
| 2024-Q1 | 6 (off-plan 6, ready 0) | 1,475 | 884 |
| 2024-Q2 | 2 (off-plan 2, ready 0) | — | 909 |
| 2024-Q3 | 6 (off-plan 6, ready 0) | 1,478 | 1,279 |
| 2024-Q4 | 1 (off-plan 1, ready 0) | — | 872 |
| 2025-Q1 | 2 (off-plan 2, ready 0) | — | 1,330 |
| 2025-Q2 | 2 (off-plan 2, ready 0) | — | 1,596 |
| 2025-Q3 | 7 (off-plan 7, ready 0) | 1,973 | 1,667 |
| 2025-Q4 | 5 (off-plan 5, ready 0) | 1,549 | 1,461 |
| 2026-Q1 | 1 (off-plan 1, ready 0) | — | 1,162 |
| 2026-Q2 | 4 (off-plan 4, ready 0) | — | 1,237 |
| 2026-Q3 | 2 (off-plan 2, ready 0) | — | 1,196 |
| 2026-Q4 | 2 (off-plan 2, ready 0) | — | 1,204 |
Registered sales per quarter, off-plan and ready units. Source: DLD.
Rents in DLD area Dubai Investment Park First
New Ejari rent contracts for villas and townhouses across DLD area Dubai Investment Park First, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier |
|---|---|---|---|
| 3 BR | AED 255,000 | 31 | -9.6% |
| 4 BR | AED 341,250 | 54 | +8.3% |
| 5 BR | AED 375,000 | 9 | -1.3% |
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Service charges
What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.
Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.
Source: Dubai Land Department, owners’ association budgets (service charges).
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 29 October 2026 | off-plan | Villa · 4 BR | 846 | 1,736,281 | 2,052 |
| 19 October 2026 | off-plan | Villa · 4 BR | 846 | 2,146,200 | 2,537 |
| 11 September 2026 | off-plan | Villa · 4 BR | 846 | 1,600,000 | 1,891 |
| 10 July 2026 | off-plan | Villa · 4 BR | 863 | 2,150,000 | 2,491 |
| 10 June 2026 | off-plan | Villa · 4 BR | 846 | 1,752,904 | 2,072 |
| 19 May 2026 | off-plan | Villa · 4 BR | 846 | 1,752,904 | 2,072 |
| 13 May 2026 | off-plan | Villa · 4 BR | 849 | 2,190,000 | 2,580 |
| 11 May 2026 | off-plan | Villa · 4 BR | 862 | 1,327,200 | 1,540 |
| 22 January 2026 | off-plan | Villa · 4 BR | 846 | 1,752,904 | 2,072 |
| 24 December 2025 | off-plan | Villa · 4 BR | 846 | 1,194,480 | 1,412 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Looking for a unit in this or similar projects?
Tell us what you are looking for in Verdana(Phase 2) or similar projects. We reply by e-mail, and your request stays with CraneScore.
Estimated value range
| Bedrooms | Range, AED | Based on | Compared at |
|---|---|---|---|
| 4 BR | 1,330,000 – 2,150,000 | 14 sales, 12 months | This project |
Estimate as of 5 November 2026 Track this unit
Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.
Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Dec 2025); move it with the slider.
A scenario from your own inputs, not this project's verified payment plan.
Common plans
Plan shares add up to 100% (must be 100%).
Payments per quarter
AED| Quarter | Paid |
|---|---|
| 2026-Q4 | AED 1,045,000 · AED 1,045,000 paid so far |
Payments per quarter, AED, fees included. Illustration from your inputs.
The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.
Mortgage for a unit here
Questions about financing a unit in Verdana(Phase 2)? Leave your details and we reply by e-mail. Your request stays with CraneScore.
LocationDubai Investment Park First · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 21, with 3,168 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2025 | 2 | 224 |
| 2026 | 2 | 470 |
| 2028 | 12 | 2,027 |
| 2029 | 4 | 447 |
| No end date | 1 | 0 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Dubai Investment Park First: 21
Open projects in the same DLD area with a DLD end year from 2024 to 2026, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Verdana Residence 2 | 20% | Apr 2026 | 1,105 | 126 |
| Verdana Residence | 96.1% | Dec 2025 | 1,010 | 60 |
| Olivia Residences | 38.2% | Dec 2026 | 1,020 | 47 |
| Verdana (Phase 1) | 94.6% | Dec 2025 | 1,705 | 34 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Reportage Prime Properties L.L.C · DLD developer no. 1277
Completed a month or more after their DLD end date: 0 of 1 completed projects with both dates. In 1 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Reportage Prime Properties L.L.C is one of 7 DLD-registered developers we list together as Reportage. See the group
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Dubai Investment Park First
DLD lists 23 projects in the master project Dubai Investment Park First.
Questions about Verdana(Phase 2)
When is Verdana(Phase 2)'s handover?
DLD lists an end date of Dec 2025 (register of 1 November 2026); the SPA sets the handover terms.
Is Verdana(Phase 2) past its DLD end date?
Yes. Its DLD end date is Dec 2025, 10 months before the register of 1 November 2026.
How far along is Verdana(Phase 2)?
94% built in the DLD register of 1 November 2026.
Who is the developer of Verdana(Phase 2)?
Reportage Prime Properties L.L.C, as registered with DLD.
What is the DLD project number of Verdana(Phase 2)?
2413.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error