DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectDubai Investment Park First

Dubai Investment Park First 22 of 24 phases not yet completed · 5,456 units · 2,238 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Dubai Investment Park First has 24 projects in the Dubai Land Department projects register as of 1 November 2026: 22 not yet completed, with 5,456 units and villas. By DLD status: Not started 16 · Under construction 6 · Completed 2. Under construction and past the DLD end date: 4.

Phases
24
2 completed
Not yet completed
22
6 under construction
Units not yet completed
5,456
units and villas · 2,288
Sales, 24 mo
2,238
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 23 of the 24 phases: those with a map pin. Pins mark approximate locations.

Verdana Residence 4 · Not started · Project locationVerdana Residence 5 · Not started · Project locationVerdana 4 · Not started · Approximate project locationVerdana Residence 3 · Not started · Project locationVerdana Residence 7 · Not started · Project locationVerdana Residence 6 · Not started · Project locationVerdana Residence 2 · Under construction · Project locationVerdana 5 · Not started · Approximate project locationVerdana 6 · Not started · Approximate project locationVerdana Residence 10 · Not started · Project locationVerdana 7 · Not started · Approximate project locationVerdana 3 · Not started · Project locationVerdana Residence 9 · Not started · Project locationVerdana 10 · Not started · Project locationVerdana Residence 8 · Not started · Project locationVerdana Residence · Under construction · Project locationOlivia Residences · Under construction · Project locationVerdana 9 · Not started · Approximate project locationVerdana 2 · Under construction · Project locationVerdana (Phase 1) · Under construction · Approximate project locationVerdana 8 · Not started · Project locationVerdana(Phase 2) · Under construction · Approximate project locationSchon Business Park · Completed · Project locationDubai Municipality · Makani
Under construction Not started Completed Approximate project locations

Dubai Investment Park First (DM community)

Phases (24)Ordered by registered sales over 24 months

Phases (24)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Verdana Residence 4Not started 0% Sep 2028 22 months to go 22 months to go 392 248 -10.8%
Verdana Residence 5Not started 0% Sep 2028 22 months to go 22 months to go 392 225 -18.8%
Verdana 4Not started 0.1% Sep 2028 22 months to go 22 months to go 306 193 +3.4%
Verdana Residence 3Not started 0% Sep 2028 22 months to go 22 months to go 278 175 +3.6%
Verdana Residence 7Not started 0% Dec 2028 25 months to go 25 months to go 392 164 +9.3%
Verdana Residence 6Not started 0% Dec 2028 25 months to go 25 months to go 363 135 -17.7%
Verdana Residence 2Under construction 20% Apr 2026 6 months past it 6 months past it 239 126 +38.7%
Verdana 5Not started 0.1% Sep 2028 22 months to go 22 months to go 271 118 +14.5%
Verdana 6Not started 0.1% Dec 2028 25 months to go 25 months to go 280 106 -9.5%
Verdana Residence 10Not started 0% Mar 2029 28 months to go 28 months to go 191 92 -22.2%
Verdana 7Not started 0.1% Dec 2028 25 months to go 25 months to go 293 88 +14.6%
Verdana 3Not started 0.1% Sep 2028 22 months to go 22 months to go 131 84 +3.4%
Verdana Residence 9Not started 0% Mar 2029 28 months to go 28 months to go 256 75 —
Verdana 10Not started 0% Mar 2029 28 months to go 28 months to go 135 69 -23.9%
Verdana Residence 8Not started 0% Dec 2028 25 months to go 25 months to go 210 64 —
Verdana ResidenceUnder construction 96.1% Dec 2025 10 months past it 10 months past it 224 60 +5.8%
Olivia ResidencesUnder construction 38.2% Dec 2026 1 month to go 1 month to go 231 47 -0.8%
Verdana 9Not started 0% Mar 2029 28 months to go 28 months to go 204 46 +19.8%
Verdana 2Under construction 56% — — 209 36 +37.1%
Verdana (Phase 1)Under construction 94.6% Dec 2025 10 months past it 10 months past it 178 34 +31.9%
Verdana 8Not started 0% Dec 2028 25 months to go 25 months to go 154 28 —
Verdana(Phase 2)Under construction 94% Dec 2025 10 months past it 10 months past it 127 25 +34.5%
Schon Business ParkCompleted 100% Dec 2015 — 375 0 —
Green Community WEST- EXTENSION- Phase IiiCompleted 100% Oct 2018 — 226 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

22 phases
2025: 5292026: 4702028: 3,4622029: 786No end date: 209

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Dubai Investment Park First

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology