Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4266Not started392 units

Verdana Residence 7 فيردانا ريسدينس 7 Dubai Investment Park First by Reportage Plus A Real Estate Development L.L.CAll phases of Dubai Investment Park First DLD status: Not started (DLD register as of 1 November 2026) DLD end date Dec 2028 25 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0%
DLD register, 1 November 2026
Registered start
Dec 2025
DLD end date Dec 2028
Latest sales
956 AED/sqft
+9.3% on launch 64 sales
1 BR estimate
0.56–0.87 M AED
Automated estimate, not a valuation
Developer
16 projects
0 completed · 0 units delivered

Completion

DLD status: Not started. 0% built, DLD end date 31 December 2028. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0% 31 December 2028Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

Building permits

1 of 1 buildings

Buildings on the project’s plots: 1, on construction permits: 1, as Dubai Municipality lists them.

Furthest stage reached: Work not started.

Work not started
Site works
Foundations
Structure
Masonry
Finishes
Final works
Completed
Buildings
1
1 on construction permits
Permit status
Open
446290
Issued
27 March 2026
Expected completion
1 June 2028
Consultant · contractor
BONYAN ENGINEERING CONSULTANCY L.L.C · MODUN GULF BUILDING CONTRACTING L.L.C
Buildings by the furthest work stage Dubai Municipality lists
Work stage Buildings
Work not started1

Source: Dubai Municipality building permits, export of 26 October 2026. These dates and stages are Dubai Municipality’s records, not DLD’s register.

DLD registration

DLD services ↗
DLD project number
4266
Escrow agent
Commercial Bank of Dubai(PSC)
Zoning authority
Dubai Municipality
Master project
Dubai Investment Park First
DLD area
Dubai Investment Park First
Units · villas
392 · 0
Start → DLD end
Dec 2025 → Dec 2028
Registered unitsStudio 119 · 1 bed 119 · 2 bed 109 · 3 bed 15 · 4 bed 30; sizes 408–1,071 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Residential Building ?1B+2P+G+15+R?

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft
Launch price
1,204 AED/sqft
Median of 100 off-plan sales in the 90 days from the first one (Apr 2026)
Latest registered sales
956 AED/sqft
Median of 64 home sales after the launch window, in the last 12 months
Change
+9.3%
Same home types on both sides, weighted by the later sales

Dubai Statistics Center residential price index (flats), 2026-Q2 to 2026-Q2: 0%.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
Studio 928 (18) 1,202 (28) +29.5%
1 BR 1,204 (48) 1,202 (32) -0.2%
2 BR 1,238 (28) 1,033 (29) -16.6%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 43 1,202 (28) May 2026 – Nov 2026
1 BR 64 1,202 (32) May 2026 – Nov 2026
2 BR 44 1,033 (29) May 2026 – Nov 2026
3 BR 8 706 (5) May 2026 – Nov 2026
4 BR 5 651 (5) Nov 2025 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2026-Q2 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Dubai Investment Park First, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents in DLD area Dubai Investment Park First

New Ejari rent contracts for apartments across DLD area Dubai Investment Park First, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 33,915 270 -10.8%
1 BR AED 65,000 472 +1.6%
2 BR AED 85,000 402 +1.2%
3 BR AED 110,000 37 -18.5%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
19.07 AED/sqft a year
Dubai Investment Park: median of 12 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 164 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
5 November 2026off-planApartment · 2 BR 969 1,184,830 1,223
29 October 2026off-planApartment · Studio 389 560,000 1,440
29 October 2026off-planApartment · Studio 408 524,500 1,286
28 October 2026off-planApartment · 4 BR 1,800 1,370,250 761
27 October 2026off-planApartment · 1 BR 687 929,000 1,352
27 October 2026off-planApartment · 1 BR 687 922,000 1,342
27 October 2026off-planApartment · 1 BR 676 598,600 886
27 October 2026off-planApartment · 1 BR 687 579,980 844
27 October 2026off-planApartment · 1 BR 736 539,380 733
22 October 2026off-planApartment · 1 BR 687 895,400 1,303

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Looking for a unit in this or similar projects?

Tell us what you are looking for in Verdana Residence 7 or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Estimated value range
Bedrooms Range, AED Based on Compared at
Studio 340,000 – 510,000 375 sales, 12 months This project
1 BR 560,000 – 870,000 471 sales, 12 months This project
2 BR 720,000 – 1,320,000 372 sales, 12 months This project
3 BR 820,000 – 2,090,000 59 sales, 12 months This project
4 BR 930,000 – 1,370,000 22 sales, 12 months This project
Automated estimate, not a valuation

Estimate as of 5 November 2026 Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Dec 2028); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Dec 2028
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in Verdana Residence 7? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationDubai Investment Park First · Dubai Municipality community

School · 300 mCarrefour Market · 990 mExtra · 1 kmSchool · 1.1 kmGrossery · 1.2 kmSchool · 1.2 kmCentral Park · 1.2 kmGreenfield International School · 1.5 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationDubai Investment Park Metro Station · Red Metro line · 2.4 km
MallRijat Retail Mall-12 · 3.1 km
SupermarketCarrefour Market · 990 m
HospitalNMC dip · 2.3 km
SchoolSchool · 300 m
ParkCentral Park · 1.2 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 21, with 2,776 units and villas.

2025: 2242026: 4702028: 1,6352029: 447No end date: 0

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Dubai Investment Park First: 21

Open projects in the same DLD area with a DLD end year from 2027 to 2029, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Verdana Residence 4 0% Sep 2028 846 248
Verdana Residence 5 0% Sep 2028 852 225
Verdana 4 0.1% Sep 2028 1,235 193
Verdana Residence 3 0% Sep 2028 858 175
Verdana Residence 6 0% Dec 2028 1,021 135
Verdana 5 0.1% Sep 2028 1,213 118
Verdana 6 0.1% Dec 2028 1,121 106
Verdana Residence 10 0% Mar 2029 948 92
Verdana 7 0.1% Dec 2028 1,196 88
Verdana 3 0.1% Sep 2028 1,237 84
Verdana Residence 9 0% Mar 2029 1,149 75
Verdana 10 0% Mar 2029 1,255 69

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Dubai Investment Park First

Developer in DLD data Reportage Plus A Real Estate Development L.L.C · DLD developer no. 1936

Projects registered
16
0 completed · 0 under construction · 16 not started
Units delivered
0
4,248 in the pipeline

Reportage Plus A Real Estate Development L.L.C is one of 7 DLD-registered developers we list together as Reportage. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error