Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 3256Completed178 units

Binghatti Pinnacle بن غاطي بيناكل Al Jadaf · Dubai Health Care City Phase 2 by Binghatti Developers FZEAll phases of Dubai Health Care City Phase 2 Completed 30 July 2026 (DLD) DLD end date Dec 2025 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Jul 2026
DLD end date Dec 2025
Build time
23 months
Sep 2024 → Jul 2026
Launch → resale
1,815 AED/sqft
-23.5% on launch Launch 2,122 · 17 sales since completion
1 BR rent
78,000 AED/yr
5 leases, 12 months
Developer
85 projects
43 completed · 13,228 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 1). Latest DLD inspection: 100% built on 29 July 2026 (inspections: 6).
Every DLD inspection and every change in the register %, newest first
Date % built Source
29 July 2026 100% DLD inspection
14 July 2026 97.5% DLD inspection
29 June 2026 96.9% DLD inspection
14 July 2025 30.5% DLD inspection
6 March 2025 8.5% DLD inspection
3 September 2024 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
16 monthsActual build
23 months
Start date
1 September 2024
DLD end date
31 December 2025
Completion date
30 July 2026
Completion vs DLD end date
6 months after

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
3256
Escrow agent
Emirates Nbd Bank (P.J.S.C)
Zoning authority
Dubai Development Authority (DDA)
Master project
Dubai Health Care City Phase 2
DLD area
Al Jadaf
Units · villas
178 · 0
Start → DLD end
Sep 2024 → Dec 2025
Registered units1 bed 48 · 2 bed 96 · 3 bed 32; sizes 874–1,314 sqft

Also registered: shops and showrooms 2.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: 4B + G + 17 FLOORS + ROOF.The project designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft
Launch price
2,122 AED/sqft
Median of 76 off-plan sales in the 90 days from the first one (Oct 2025)
Latest registered sales
2,013 AED/sqft
Median of 83 home sales after the launch window, in the last 12 months
Change
-15.3%
Same home types on both sides, weighted by the later sales

Dubai Statistics Center residential price index (flats), 2025-Q4 to 2026-Q2: -0.9%.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
2 BR 2,447 (25) 1,948 (22) -20.4%
3 BR 2,215 (9) 1,748 (6) -21.1%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
1 BR 45 2,045 (35) Nov 2025 – Nov 2026
2 BR 85 1,948 (22) May 2026 – Nov 2026
3 BR 29 1,748 (6) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2025-Q4 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Jadaf, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

What launch buyers got

The launch price against the registered resales after completion, same home types on both sides.

Launch price
2,122 AED/sqft
Median of 76 off-plan sales, Oct 2025 – Jan 2026
Resales after completion
1,815 AED/sqft
Median of 17 ready sales, Jul 2026 – Nov 2026
Change
-23.5%
Same home types, weighted by the resales

Over the same span, ready homes in DLD area Al Jadaf changed -0.1% (same home types).

Launch: the 90 days from the first off-plan sale (2020 onward). Resales: ready sales in the 12 months after the DLD completion date, or 24 when 12 hold fewer than 5. A price change is not a return: it leaves out fees, service charges, rent and the payment plan.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
1 BR AED 78,000 5 —

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 146 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
5 November 2026readyApartment · 2 BR 1,066 2,000,000 1,876
3 November 2026readyApartment · 2 BR 1,072 1,900,000 1,772
2 November 2026readyApartment · 2 BR 1,066 1,950,000 1,829
2 November 2026readyApartment · 2 BR 1,103 1,900,000 1,723
22 October 2026readyApartment · 3 BR 1,519 2,800,000 1,843
21 October 2026readyApartment · 2 BR 1,075 2,000,000 1,860
14 October 2026readyApartment · 2 BR 1,075 1,900,000 1,767
13 October 2026readyApartment · 1 BR 873 1,406,091 1,611
12 October 2026readyApartment · 2 BR 1,103 1,850,000 1,677
6 October 2026readyApartment · 3 BR 1,712 2,800,000 1,636

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Jadaf · Dubai Municipality community

Dubai Herbal And Treatment Centre · 360 mMS FM Supermarket · 390 mBarraquer Eye Hospital · 620 mLatifa Hospital Women and Children · 1.2 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationDubai Healthcare City Metro Station · Green Metro line · 2.2 km
MallWafi Mall · 1.9 km
SupermarketMS FM Supermarket · 390 m
HospitalDubai Herbal And Treatment Centre · 360 m
SchoolSwiss International Scientific School in Dubai · 1.7 km
ParkPark · 1.8 km
BeachBeach · 2.1 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 8, with 2,981 units and villas.

2026: 7422027: 1,5332028: 402No end date: 304

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Jadaf: 31

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Binghatti Cullinan 0% Jun 2027 2,146 524
Binghatti Starlight 63.1% Mar 2026 2,058 481
Montage 40% Aug 2027 1,861 245
Binghatti Moonlight 19.2% Jun 2026 1,983 227
Binghatti Twilight 55.4% Apr 2026 1,834 221
Adeba Azizi 75.5% — — 205
Binghatti Wraith 0% Dec 2027 — 163
Azizi David 2% Sep 2028 2,362 146
Val By Kasco 72.6% Dec 2026 1,695 126
Boutique 23 64.9% — 1,831 118
La Boutique 52.5% Dec 2026 1,634 113
Lumiere Heights 2.1% Jun 2027 — 103

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Jadaf

Developer in DLD data Binghatti Developers FZE · DLD developer no. 1051

Projects registered
85
43 completed · 24 under construction · 18 not started
Units delivered
13,228
37,137 in the pipeline
Median build time
16 months
completed projects measured: 43
Past the DLD end date
13
of 23 under construction with a DLD end date

Completed a month or more after their DLD end date: 6 of 37 completed projects with both dates. In 27 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Binghatti Developers FZE is one of 2 DLD-registered developers we list together as Binghatti. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Dubai Health Care City Phase 2

DLD lists 15 projects in the master project Dubai Health Care City Phase 2.

Binghatti StarlightUnder construction · 63.1% · Mar 2026
Adeba AziziUnder construction · 75.5% · —
Keturah ResortConditionally activating · 15.3% · Feb 2026
Project 4438, Al JadafPending · 0% · Dec 2029
Azizi Aliyah ResidencesCompleted · 100% · Jun 2019
Binghatti GatewayCompleted · 100% · Jun 2021
Binghatti AvenueCompleted · 100% · Apr 2022
Farhad Azizi ResidenceCompleted · 100% · Jul 2022
O10Completed · 100% · Nov 2022
Binghatti CreekCompleted · 100% · Apr 2023
Al Waleed Garden 2Completed · 100% · Feb 2024
Fawad Azizi ResidenceCompleted · 100% · Apr 2024

Questions about Binghatti Pinnacle

When was Binghatti Pinnacle completed?

Binghatti Pinnacle is recorded as completed on 30 July 2026 (DLD register of 1 November 2026).

Who is the developer of Binghatti Pinnacle?

Binghatti Developers FZE, as registered with DLD.

What is the DLD project number of Binghatti Pinnacle?

3256.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error