DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2917Under construction304 units

Adeba Azizi أديبه عزيزى Al Jadaf · Dubai Health Care City Phase 2 by Azizi Developments L.L.CAll phases of Dubai Health Care City Phase 2 75.5% built (DLD register as of 1 November 2026) no DLD end date registered DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
75.5%
DLD register, 1 November 2026
Latest sales
2,028 AED/sqft
128 sales
1 BR estimate
1.44–1.51 M AED
Automated estimate, not a valuation
Developer
150 projects
91 completed · 20,380 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

1 November 2026
Built
75.5%
Latest DLD register reading: 75.5% built on 1 November 2026 (register readings: 3). Latest DLD inspection: 75.5% built on 30 June 2026 (inspections: 5).
Every DLD inspection and every change in the register %, newest first
Date % built Source
30 June 2026 75.5% DLD inspection
9 December 2025 56.2% DLD inspection
17 July 2025 41.9% DLD inspection
10 December 2024 21.4% DLD inspection
23 January 2024 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Our completion calculation

Pace since the last two DLD readings: —

Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Changes in the DLD register

1 Nov 2026Construction completed: 75.5% → 75.5%.

Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
2917
Escrow agent
First Abu Dhabi Bank P.J.S.C.
Zoning authority
Dubai Development Authority (DDA)
Master project
Dubai Health Care City Phase 2
DLD area
Al Jadaf
Units · villas
304 · 0
Start → DLD end
Jan 2024 → —
Registered unitsStudio 74 · 1 bed 140 · 2 bed 68 · 3 bed 8; sizes 461–1,066 sqft

Also registered: shops and showrooms 14.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: 2B+G+2P+19F+R.The project designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 sales with a size were registered in the first 90 days, so no launch price is shown.

Prices are over apartments, the type most sales in this project are.

Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 66 2,204 (33) May 2026 – Nov 2026
1 BR 88 2,027 (63) May 2026 – Nov 2026
2 BR 43 1,927 (27) May 2026 – Nov 2026
3 BR 8 1,938 (5) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2024-Q4 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Jadaf, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents in DLD area Al Jadaf

New Ejari rent contracts for apartments across DLD area Al Jadaf, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 55,000 808 0%
1 BR AED 72,000 1,928 -1.4%
2 BR AED 100,000 1,189 +7.5%
3 BR AED 140,000 212 -6.7%
4 BR AED 150,000 12 0%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 157 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
5 November 2026off-planApartment · 1 BR 724 1,506,369 2,081
4 November 2026off-planApartment · 1 BR 733 1,319,840 1,801
4 November 2026off-planApartment · 1 BR 733 1,319,110 1,800
2 November 2026off-planApartment · 1 BR 727 1,429,823 1,967
2 November 2026off-planApartment · 3 BR 2,064 400,000 194
20 October 2026off-planApartment · 1 BR 731 1,462,050 2,000
20 October 2026off-planApartment · 1 BR 733 1,462,050 1,995
15 October 2026off-planApartment · Studio 369 816,388 2,212
12 October 2026off-planApartment · 2 BR 1,322 2,283,840 1,728
25 September 2026off-planApartment · 1 BR 735 1,524,511 2,074

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Looking for a unit in this or similar projects?

Tell us what you are looking for in Adeba Azizi or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Estimated value range
Bedrooms Range, AED Based on Compared at
Studio 790,000 – 820,000 45 sales, 12 months This project
1 BR 1,440,000 – 1,510,000 73 sales, 12 months This project
2 BR 2,060,000 – 2,400,000 31 sales, 12 months This project
3 BR 3,570,000 – 3,690,000 6 sales, 12 months This project
Automated estimate, not a valuation

Estimate as of 5 November 2026 Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Resale asking prices against the original price

Fewer than 5 resale offers with an original price are tracked for this project.

Across all Dubai off-plan resale offers we track: -3.9% (1,105 offers).

Median asking premium by share of the price already paid (number of offers); shown from 5 offers
Paid to the developer This project All Dubai
0–30% paid—0% (9)
30–50% paid—-5% (51)
50–70% paid—-1.5% (65)
70% paid or more—-3.5% (45)

Asking prices of off-plan resale offers we track, compared with each offer's original price, with the 4% DLD fee removed on both sides. A negative value means asking below the original price. Only aggregates of at least 5 offers are shown; no individual offer, seller or agent is.

Thinking of selling your unit?

Thinking of reselling your unit in Adeba Azizi? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

Payment scenarioEnter the developer’s plan to see what you pay and when. DLD has no end date for this project, so handover starts a year from now; move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Nov 2027
No end date registered
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in Adeba Azizi? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationAl Jadaf · Dubai Municipality community

MS FM Supermarket · 200 mBarraquer Eye Hospital · 420 mDubai Herbal And Treatment Centre · 860 mLatifa Hospital Women and Children · 1 kmSwiss International Scientific School in Dubai · 1.3 kmPark · 1.4 kmCarryfood · 1.5 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationAl Jadaf Metro Station · Green Metro line · 1.9 km
MallWafi Mall · 1.7 km
SupermarketMS FM Supermarket · 200 m
HospitalBarraquer Eye Hospital · 420 m
SchoolSwiss International Scientific School in Dubai · 1.3 km
ParkPark · 1.4 km
BeachBeach · 2.1 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 10, with 2,933 units and villas.

2026: 7422027: 1,5332028: 6582029: 0

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Jadaf: 30

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Binghatti Cullinan 0% Jun 2027 2,146 524
Binghatti Starlight 63.1% Mar 2026 2,058 481
Montage 40% Aug 2027 1,861 245
Binghatti Moonlight 19.2% Jun 2026 1,983 227
Binghatti Twilight 55.4% Apr 2026 1,834 221
Binghatti Wraith 0% Dec 2027 — 163
Azizi David 2% Sep 2028 2,362 146
Val By Kasco 72.6% Dec 2026 1,695 126
Boutique 23 64.9% — 1,831 118
La Boutique 52.5% Dec 2026 1,634 113
Lumiere Heights 2.1% Jun 2027 — 103
J188 0% Apr 2028 1,581 68

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Jadaf

Developer in DLD data Azizi Developments L.L.C · DLD developer no. 1002

Projects registered
150
91 completed · 43 under construction · 16 not started
Units delivered
20,380
40,083 in the pipeline
Median build time
56 months
completed projects measured: 91
Past the DLD end date
10
of 38 under construction with a DLD end date

Completed a month or more after their DLD end date: 13 of 90 completed projects with both dates. In 65 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Azizi Developments L.L.C is one of 3 DLD-registered developers we list together as Azizi. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Dubai Health Care City Phase 2

DLD lists 15 projects in the master project Dubai Health Care City Phase 2.

Binghatti StarlightUnder construction · 63.1% · Mar 2026
Keturah ResortConditionally activating · 15.3% · Feb 2026
Project 4438, Al JadafPending · 0% · Dec 2029
Azizi Aliyah ResidencesCompleted · 100% · Jun 2019
Binghatti GatewayCompleted · 100% · Jun 2021
Binghatti AvenueCompleted · 100% · Apr 2022
Farhad Azizi ResidenceCompleted · 100% · Jul 2022
O10Completed · 100% · Nov 2022
Binghatti CreekCompleted · 100% · Apr 2023
Al Waleed Garden 2Completed · 100% · Feb 2024
Fawad Azizi ResidenceCompleted · 100% · Apr 2024
Kempinski Residences The CreekCompleted · 100% · Dec 2025

Questions about Adeba Azizi

When is Adeba Azizi's handover?

DLD lists no end date for it (register of 1 November 2026); the SPA sets the handover terms.

How far along is Adeba Azizi?

75.5% built in the DLD register of 1 November 2026.

Who is the developer of Adeba Azizi?

Azizi Developments L.L.C, as registered with DLD.

What is the DLD project number of Adeba Azizi?

2917.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error