Rose Homes Investment (L.L.C) روز هومز للاستثمار (ش.ذ.م.م) 5 projects in the DLD register: 3 completed, 2 under construction, 0 not started or pending. 1 of the 2 under construction with a DLD end date are past it. DLD projects register, export of 1 November 2026
Delivery record
Projects: 5- Median time from start to completion: 36 months (3 completed projects).
- 855 units and villas in completed projects; 168 in projects not yet completed.
- Completed a month or more after their DLD end date: 0 of 3 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
- Under construction past their DLD end date: 1 of 2 projects with an end date.
One page per legal entity registered with DLD; companies of the same group are shown separately. Figures come from the DLD projects register; each project page shows the dates they are based on.
Source: DLD projects register, export of 1 November 2026. Build times and counts: our calculation from DLD dates; a median needs at least 3 completed projects.
Completed projects: launch to resale
Loading…
Projects by Rose Homes Investment (L.L.C) Most registered sales in the last 24 months first
| Project | DLD status | Built | DLD end date / completion | Past DLD end date | Units | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Ontario Tower349 · Business Bay | Completed | 100% | Aug 2010 Completed | — | 300 | 68 |
| Roxana Residence1844 · Al Barsha South Fourth · Jumeirah Village Circle | Completed | 100% | Apr 2019 Completed | — | 255 | 62 |
| Sherena Residence1628 · Wadi Al Safa 3 · Majan | Completed | 100% | Mar 2017 Completed | — | 300 | 53 |
| Sherena Residence 22101 · Wadi Al Safa 3 · Majan | Under construction | 82% | Aug 2022 50 mo past | 50 mo | 120 | 8 |
| Al Warsan Star3674 · Al Warsan First · Warsan First Development | Under construction | 7.5% | Feb 2027 3 mo to go | — | 48 | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Months to go: our calculation.
Where the open projects are Projects not yet completed: 2, all pinned
Pins: DLD area data and Dubai Municipality plots, our matching. % built: DLD projects register, 1 November 2026.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Developer names: DLD developers register, 1 November 2026.