DLD master projectMadinat Hind 4
Damac Hills 2 13 of 46 phases not yet completed · 1,834 units · 4,670 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Damac Hills 2 has 46 projects in the Dubai Land Department projects register as of 1 November 2026: 13 not yet completed, with 1,834 units and villas. By DLD status: Under construction 12 · Completed 33 · Not started 1. Under construction and past the DLD end date: 1.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 44 of the 46 phases: those with a map pin. Pins mark approximate locations.
Madinat Hind 4 (DM community)
Phases (46)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Damac Hills (2) - Violet 4 | Under construction | 14.2% | Aug 2027 9 months to go | 9 months to go | 0 | 762 | — |
| Damac Hills (2) - Violet 3 | Under construction | 36.2% | Jun 2027 7 months to go | 7 months to go | 1 | 631 | — |
| Damac Hills (2) - Elo 2 & Elo 3 | Under construction | 6.4% | Jun 2027 7 months to go | 7 months to go | 1,145 | 277 | +5% |
| Damac Hills (2) - Violet 2 | Under construction | 57.6% | Feb 2027 3 months to go | 3 months to go | 0 | 221 | — |
| Damac Hills (2) - Mulberry | Completed | 100% | Oct 2021 | — | 0 | 200 | — |
| Damac Hills (2) - Camelia | Completed | 100% | Nov 2025 | — | 578 | 158 | — |
| Damac Hills (2) - Vardon | Completed | 100% | Mar 2022 | — | 0 | 151 | — |
| Damac Hills (2) - Pacifica | Completed | 100% | Feb 2022 | — | 0 | 139 | — |
| Sold Without Project for Front Line Investment Managment | Not started | 0% | — | — | 0 | 136 | — |
| Damac Hills (2) - Violet | Under construction | 95.2% | — | — | 0 | 128 | — |
| Damac Hills (2) - Janusia | Completed | 100% | Feb 2020 | — | 0 | 109 | — |
| Damac Hills (2) - Viridis | Completed | 100% | Apr 2023 | — | 870 | 106 | — |
| Damac Hills (2) - Albizia | Completed | 100% | Mar 2022 | — | 0 | 103 | — |
| Damac Hills (2) - Basswood | Completed | 100% | Mar 2022 | — | 0 | 101 | — |
| Damac Hills (2) - Zinnia | Completed | 100% | Jun 2022 | — | 0 | 86 | — |
| Damac Hills (2) - Sanctnary | Completed | 100% | Jun 2019 | — | 0 | 84 | — |
| Damac Hills (2) - Aster | Completed | 100% | Oct 2021 | — | 0 | 83 | — |
| Damac Hills (2) - Primrose | Completed | 100% | Sep 2020 | — | 0 | 82 | — |
| Damac Hills (2) - Victoria | Completed | 100% | Aug 2022 | — | 0 | 80 | — |
| Damac Hills (2) - Juniper | Completed | 100% | Sep 2019 | — | 0 | 79 | — |
| Damac Hills (2) - Centaury | Completed | 100% | Mar 2022 | — | 0 | 79 | — |
| Damac Hills (2) - Elo | Under construction | 21.5% | — | — | 557 | 72 | +5.2% |
| Damac Hills (2) - Amargo | Completed | 100% | Dec 2022 | — | 0 | 70 | — |
| Damac Hills (2) - AVENCIA-2 | Completed | 100% | Aug 2022 | — | 0 | 66 | — |
| Damac Hills (2) - Navitas (A & B) | Completed | 100% | Jun 2023 | — | 218 | 66 | — |
| Damac Hills (2) - Claret | Completed | 100% | May 2019 | — | 0 | 61 | — |
| Damac Hills (2) - Mimosa | Completed | 100% | Aug 2021 | — | 0 | 54 | — |
| Damac Hills (2) - Odora | Completed | 100% | Oct 2021 | — | 0 | 47 | — |
| Damac Hills (2) - Verona | Completed | 100% | Jun 2026 | — | 0 | 45 | — |
| Damac Hills (2) - Coursetia | Completed | 100% | Mar 2022 | — | 0 | 40 | — |
| Damac Hills (2) - Amazonia | Completed | 100% | Feb 2021 | — | 0 | 40 | — |
| Damac Hills (2) - Natura | Under construction | 85.6% | — | — | 0 | 39 | — |
| Damac Hills (2) - Aquilegia | Completed | 100% | Aug 2022 | — | 0 | 38 | — |
| Damac Hills (2) - Sycamore | Completed | 100% | Oct 2017 | — | 0 | 34 | — |
| Damac Hills (2) - Victoria 2 | Completed | 100% | Dec 2024 | — | 0 | 32 | — |
| Damac Hills (2) - Park Greens 3 | Under construction | 33.1% | — | — | 0 | 30 | — |
| Damac Hills (2) - Trixis | Completed | 100% | Feb 2021 | — | 0 | 27 | — |
| Damac Hills (2) - AMAZONIA-EX | Completed | 100% | Jun 2021 | — | 0 | 20 | — |
| Damac Hills (2) - Amargo 2 | Completed | 100% | Jan 2024 | — | 0 | 20 | — |
| Damac Hills (2) - Evergreens | Under construction | 26.4% | — | — | 131 | 17 | -10.1% |
| Damac Hills (2) - Avencia | Completed | 100% | May 2022 | — | 230 | 17 | — |
| Damac Hills (2) - Park Greens 2 | Under construction | 30.8% | — | — | 0 | 16 | — |
| Damac Hills (2) - Park Greens 1 | Under construction | 21.7% | Mar 2027 4 months to go | 4 months to go | 0 | 12 | — |
| Damac Hills (2) - Acuna | Completed | 100% | Dec 2017 | — | 0 | 11 | — |
| Damac Hills (2) - Farmhouses | Under construction | 83% | Aug 2025 14 months past it | 14 months past it | 0 | 1 | — |
| DAMAC Hills (2) - Navitas | Completed | 100% | Dec 2022 | — | 304 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
13 phases| DLD end year | Projects | Units |
|---|---|---|
| 2025 | 1 | 0 |
| 2027 | 5 | 1,146 |
| No end date | 7 | 688 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Damac Hills 2
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology