DLD master projectJabal Ali Industrial Second
Down Town Jabal Ali 19 of 23 phases not yet completed · 7,186 units · 3,349 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Down Town Jabal Ali has 23 projects in the Dubai Land Department projects register as of 1 November 2026: 19 not yet completed, with 7,186 units and villas. By DLD status: Not started 10 · Under construction 7 · Completed 4 · Pending 2.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 22 of the 23 phases: those with a map pin. Pins mark approximate locations.
Jabal Ali Industrial Second (DM community)
Phases (23)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Raw District By Imtiaz R | Not started | 0% | Dec 2029 37 months to go | 37 months to go | 672 | 621 | -3.1% |
| Eleve By Deyaar | Under construction | 20% | — | — | 818 | 514 | +3.9% |
| Raw District 2 By Imtiaz | Not started | 0% | Dec 2029 37 months to go | 37 months to go | 770 | 393 | — |
| Raw District By Imtiaz Cr | Not started | 0% | Dec 2029 37 months to go | 37 months to go | 610 | 386 | — |
| Azizi Noura | Not started | 0% | Jul 2028 20 months to go | 20 months to go | 269 | 190 | -0.6% |
| Azizi Wares | Under construction | 2% | Mar 2028 16 months to go | 16 months to go | 336 | 182 | +1.5% |
| Azizi Lina | Under construction | 2% | Sep 2028 22 months to go | 22 months to go | 242 | 176 | +0.7% |
| Azizi Gabriel | Not started | 0% | Jul 2028 20 months to go | 20 months to go | 234 | 169 | — |
| Alexis Tower | Completed | 100% | May 2024 | — | 378 | 147 | — |
| Equiti Gates | Completed | 100% | Oct 2025 | — | 284 | 146 | — |
| Azizi Aura Residences | Completed | 100% | Dec 2020 | — | 487 | 110 | — |
| Suberbia | Completed | 100% | Mar 2013 | — | 387 | 91 | — |
| Portside by Samana Developers | Not started | 0% | Jun 2029 31 months to go | 31 months to go | 148 | 86 | — |
| Peace Avenue By Peace Homes | Under construction | 3.5% | Jan 2029 26 months to go | 26 months to go | 266 | 83 | -1.5% |
| Azizi Rose | Not started | 0% | Jul 2028 20 months to go | 20 months to go | 226 | 52 | — |
| Azizi Abraham | Under construction | 2% | Aug 2027 9 months to go | 9 months to go | 420 | 1 | — |
| Samana Business Hub | Under construction | 0.8% | Sep 2029 34 months to go | 34 months to go | 323 | 1 | — |
| Raw District 2 Tower C By Imtiaz | Not started | 0% | Dec 2029 37 months to go | 37 months to go | 149 | 1 | — |
| Arian By Azizi | Under construction | 2% | Jan 2028 14 months to go | 14 months to go | 631 | 0 | — |
| Portside 2 by Samana Developers | Not started | 0% | Dec 2029 37 months to go | 37 months to go | 279 | 0 | — |
| Samana Downtown One | Not started | 0% | Dec 2029 37 months to go | 37 months to go | 257 | 0 | — |
| Sabah Square | Pending | 22.6% | — | — | 536 | 0 | — |
| Project 4611, Jabal Ali Industrial Second | Pending | 0% | Dec 2029 37 months to go | 37 months to go | 0 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
19 phases| DLD end year | Projects | Units |
|---|---|---|
| 2027 | 1 | 420 |
| 2028 | 6 | 1,938 |
| 2029 | 10 | 3,474 |
| No end date | 2 | 1,354 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Down Town Jabal Ali
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology