DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4403Not started226 units

Azizi Rose عزيزي روز Jabal Ali Industrial Second · Down Town Jabal Ali by Azizi Developments L.L.CAll phases of Down Town Jabal Ali DLD status: Not started (DLD register as of 1 November 2026) DLD end date Jul 2028 20 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0%
DLD register, 1 November 2026
Registered start
Jul 2026
DLD end date Jul 2028
Latest sales
1,654 AED/sqft
51 sales
1 BR estimate
1.02–1.11 M AED
Automated estimate, not a valuation
Developer
150 projects
91 completed · 20,380 units delivered

Completion

DLD status: Not started. 0% built, DLD end date 4 July 2028. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
28 October 2026 0% 4 July 2028Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
4403
Escrow agent
Ajman Bank /P.J.S.C
Zoning authority
Trakhees
Master project
Down Town Jabal Ali
DLD area
Jabal Ali Industrial Second
Units · villas
226 · 0
Start → DLD end
Jul 2026 → Jul 2028
Registered unitsStudio 156 · 1 bed 63; sizes 338–688 sqft

Also registered: shops and showrooms 7.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: 4B+G+3P+8+R COMMERCIAL / RESIDENTIAL

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

Fewer than 5 home sales after the launch window in the last 12 months, so no comparison is shown.

Prices are over apartments, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
Studio 1,767 (33) 1,767 (34) 0%
1 BR 1,479 (17) 1,479 (17) 0%
Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest off-plan sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 34 1,767 (34) May 2026 – Nov 2026
1 BR 17 1,479 (17) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2026-Q3 → 2026-Q4

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Jabal Ali Industrial Second, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents in DLD area Jabal Ali Industrial Second

New Ejari rent contracts for apartments across DLD area Jabal Ali Industrial Second, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 45,000 316 0%
1 BR AED 60,000 267 0%
2 BR AED 88,000 47 +17.3%
3 BR AED 95,000 17 +8%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 51 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
3 November 2026off-planApartment · Studio 352 641,520 1,823
21 October 2026off-planApartment · Studio 352 582,360 1,654
19 October 2026off-planApartment · 1 BR 709 1,104,850 1,558
19 October 2026off-planApartment · Studio 345 623,000 1,806
14 October 2026off-planApartment · Studio 345 554,400 1,607
12 October 2026off-planApartment · Studio 343 611,520 1,783
7 October 2026off-planApartment · Studio 345 621,000 1,800
7 October 2026off-planApartment · Studio 388 594,520 1,532
6 October 2026off-planApartment · Studio 345 609,560 1,767
5 October 2026off-planApartment · Studio 352 624,260 1,773

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Looking for a unit in this or similar projects?

Tell us what you are looking for in Azizi Rose or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Estimated value range
Bedrooms Range, AED Based on Compared at
Studio 590,000 – 620,000 34 sales, 12 months This project
1 BR 1,020,000 – 1,110,000 17 sales, 12 months This project
Automated estimate, not a valuation

Estimate as of 5 November 2026 Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Jul 2028); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Jul 2028
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in Azizi Rose? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationJabal Ali Industrial Second · Dubai Municipality community

UAE Exchange Metro Station · 570 mProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Metro and tram

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationUAE Exchange Metro Station · Red Metro line · 570 m
MallMall · 4 km
SupermarketSupermarket · 2.7 km
HospitalCedars Jebel Ali Free Hospital · 4.8 km
BeachBeach · 5.5 km

Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 14, with 6,111 units and villas.

2027: 4202028: 1,1422029: 3,195No end date: 1,354

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Jabal Ali Industrial Second: 18

Open projects in the same DLD area with a DLD end year from 2027 to 2029, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Raw District By Imtiaz R 0% Dec 2029 1,702 621
Raw District 2 By Imtiaz 0% Dec 2029 — 393
Raw District By Imtiaz Cr 0% Dec 2029 1,735 386
Azizi Noura 0% Jul 2028 1,701 190
Azizi Wares 2% Mar 2028 1,706 182
Azizi Lina 2% Sep 2028 1,743 176
Azizi Gabriel 0% Jul 2028 — 169
Portside by Samana Developers 0% Jun 2029 — 86
Peace Avenue By Peace Homes 3.5% Jan 2029 1,125 83
Azizi Abraham 2% Aug 2027 — 1
Samana Business Hub 0.8% Sep 2029 — 1
Raw District 2 Tower C By Imtiaz 0% Dec 2029 — 1

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Jabal Ali Industrial Second

Developer in DLD data Azizi Developments L.L.C · DLD developer no. 1002

Projects registered
150
91 completed · 43 under construction · 16 not started
Units delivered
20,380
40,083 in the pipeline
Median build time
56 months
completed projects measured: 91
Past the DLD end date
10
of 38 under construction with a DLD end date

Completed a month or more after their DLD end date: 13 of 90 completed projects with both dates. In 65 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Azizi Developments L.L.C is one of 3 DLD-registered developers we list together as Azizi. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error