DLD master projectMe'aisem First
Jumeirah Golf Estates 6 of 27 phases not yet completed · 249 units · 571 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Jumeirah Golf Estates has 27 projects in the Dubai Land Department projects register as of 1 November 2026: 6 not yet completed, with 249 units and villas. By DLD status: Completed 21 · Under construction 4 · Pending 2. Under construction and past the DLD end date: 2.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 26 of the 27 phases: those with a map pin. Pins mark approximate locations.
Me'aisem First (DM community)
Phases (27)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Jasmine Lane | Completed | 100% | Jan 2025 | — | 138 | 79 | +12.7% |
| Jumeirah Golf Estates | Completed | 100% | Aug 2015 | — | 0 | 50 | — |
| Alandalus | Completed | 100% | Jun 2018 | — | 215 | 47 | — |
| D Villas | Under construction | 9.1% | Dec 2028 25 months to go | 25 months to go | 0 | 46 | — |
| Terra Golf Collection | Under construction | 20.1% | Dec 2027 13 months to go | 13 months to go | 77 | 35 | +63.4% |
| ALandalus Building D | Completed | 100% | Apr 2020 | — | 136 | 34 | — |
| Jumeirah Luxury | Completed | 100% | Jun 2021 | — | 165 | 33 | +84% |
| Sienna Lakes | Completed | 100% | Jul 2013 | — | 1 | 25 | — |
| AL Andalus Phase 2 | Completed | 100% | Dec 2019 | — | 120 | 25 | — |
| Lime Tree Valley | Completed | 100% | Feb 2010 | — | 0 | 22 | — |
| Redwood Avenue | Completed | 100% | Dec 2016 | — | 0 | 21 | — |
| Alandalus Building E | Completed | 100% | Aug 2020 | — | 89 | 18 | — |
| Olive Point | Completed | 100% | Jan 2014 | — | 1 | 17 | — |
| The Sundials | Completed | 100% | Dec 2014 | — | 1 | 17 | — |
| ALandalus Townhouse | Completed | 100% | Apr 2020 | — | 0 | 16 | — |
| Sanctuary Falls | Completed | 100% | Apr 2011 | — | 0 | 13 | — |
| Orange Lake | Completed | 100% | Feb 2016 | — | 0 | 12 | — |
| Royal Golf Villas | Completed | 100% | Dec 2015 | — | 1 | 12 | — |
| Red Wood Park | Completed | 100% | Jul 2018 | — | 0 | 12 | — |
| Alandalus Building G | Completed | 100% | Apr 2021 | — | 29 | 12 | — |
| Redwood Park Phase2 | Completed | 100% | Sep 2017 | — | 0 | 9 | — |
| Jumeirah Golf Estates - Hillside | Completed | 100% | Feb 2020 | — | 0 | 6 | — |
| Signature Mansions | Under construction | 86.9% | May 2026 5 months past it | 5 months past it | 18 | 5 | — |
| Flame Tree Ridge | Completed | 100% | Jul 2016 | — | 0 | 5 | — |
| Jouri Hills | Under construction | 78.5% | Jun 2026 4 months past it | 4 months past it | 154 | 0 | — |
| Project 2601, Me'Aisem First | Pending | 0% | — | — | 0 | 0 | — |
| Project 2819, Me'Aisem First | Pending | 0% | — | — | 0 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
6 phases| DLD end year | Projects | Units |
|---|---|---|
| 2026 | 2 | 172 |
| 2027 | 1 | 77 |
| 2028 | 1 | 0 |
| No end date | 2 | 0 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Jumeirah Golf Estates
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology