DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectMadinat Dubai Al Melaheyah

Mina Rashid 21 of 23 phases not yet completed · 4,823 units · 1,641 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Mina Rashid has 23 projects in the Dubai Land Department projects register as of 1 November 2026: 21 not yet completed, with 4,823 units and villas. By DLD status: Under construction 15 · Not started 6 · Completed 2. Under construction and past the DLD end date: 1.

Phases
23
2 completed
Not yet completed
21
15 under construction
Units not yet completed
4,823
units and villas
Sales, 24 mo
1,641
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 23 of the 23 phases: those with a map pin. Pins mark approximate locations.

Baystar by VIDA · Under construction · Project locationMarina Place 2 · Under construction · Approximate project locationMarina Place 1 · Under construction · Approximate project locationAurea · Not started · Project locationSera 2 · Not started · Project locationPortside Square · Not started · Approximate project locationSeascape · Under construction · Project locationFior 1 · Not started · Project locationPier Point 2 · Under construction · Approximate project locationPorto View · Under construction · Approximate project locationSeagate · Completed · Project locationPier Point 1 · Under construction · Approximate project locationClearpoint · Under construction · Project locationOcean Views · Under construction · Project locationSera 1 · Not started · Project locationMarina Views · Under construction · Project locationOcean Cove · Under construction · Project locationBayline · Under construction · Project locationOcean Point · Under construction · Project locationOcean Star · Under construction · Project locationAvonlea · Under construction · Project locationSunridge · Completed · Project locationFior 2 · Not started · Project locationDubai Municipality · Makani
Under construction Not started Completed Approximate project locations

Madinat Dubai Al Melaheyah (DM community)

Phases (23)Ordered by registered sales over 24 months

Phases (23)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Baystar by VIDAUnder construction 6.3% Dec 2029 37 months to go 37 months to go 328 284 -4.4%
Marina Place 2Under construction 1.5% Dec 2028 25 months to go 25 months to go 180 183 —
Marina Place 1Under construction 4.2% Dec 2028 25 months to go 25 months to go 162 163 —
AureaNot started 0.2% Jun 2030 43 months to go 43 months to go 172 158 —
Sera 2Not started 0% Nov 2029 36 months to go 36 months to go 183 112 -5.3%
Portside SquareNot started 0% Dec 2029 37 months to go 37 months to go 413 112 —
SeascapeUnder construction 79.1% Nov 2026 This month This month 395 71 +4.3%
Fior 1Not started 0% Jul 2030 44 months to go 44 months to go 184 66 -1%
Pier Point 2Under construction 8.5% Oct 2028 23 months to go 23 months to go 121 64 —
Porto ViewUnder construction 6.3% Oct 2028 23 months to go 23 months to go 115 64 —
SeagateCompleted 100% Sep 2025 — 302 54 —
Pier Point 1Under construction 8.3% Oct 2028 23 months to go 23 months to go 122 52 —
ClearpointUnder construction 45.1% — — 478 41 +0.7%
Ocean ViewsUnder construction 6.2% Sep 2028 22 months to go 22 months to go 78 39 —
Sera 1Not started 0% Nov 2029 36 months to go 36 months to go 203 35 —
Marina ViewsUnder construction 7.1% Dec 2028 25 months to go 25 months to go 554 31 +4.5%
Ocean CoveUnder construction 17.9% Aug 2028 21 months to go 21 months to go 233 28 0%
BaylineUnder construction 61.3% — — 151 25 +0.4%
Ocean PointUnder construction 27% — — 217 18 +3.3%
Ocean StarUnder construction 30.5% Jul 2025 15 months past it 15 months past it 155 18 —
AvonleaUnder construction 63.7% — — 163 14 —
SunridgeCompleted 100% Mar 2026 — 130 9 —
Fior 2Not started 0% Aug 2030 45 months to go 45 months to go 216 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

21 phases
2025: 1552026: 3952028: 1,5652029: 1,1272030: 572No end date: 1,009

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Mina Rashid

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology