DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectNakhlat Jabal Ali

Palm Jabal Ali 23 of 23 phases not yet completed · 434 units · 423 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

Palm Jabal Ali has 23 projects in the Dubai Land Department projects register as of 1 November 2026: 23 not yet completed, with 434 units and villas. By DLD status: Not started 4 · Under construction 18 · Pending 1.

Phases
23
0 completed
Not yet completed
23
18 under construction
Units not yet completed
434
units and villas
Sales, 24 mo
423
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 23 of the 23 phases: those with a map pin. Pins mark approximate locations.

Palm Central Private Residences - Frond M · Not started / Pending · Project locationPalm Central Private Residences - Frond N · Not started / Pending · Approximate project locationPalm Jebel Ali - Frond P · Under construction · Approximate project locationPalm Jebel Ali - Frond O · Under construction · Approximate project locationPalm Jebel Ali - Frond N · Under construction · Approximate project locationPalm Jebel Ali - Frond M · Under construction · Approximate project locationPalm Jebel Ali - Frond L · Under construction · Approximate project locationPalm Jebel Ali - Frond K · Under construction · Approximate project locationPalm Jebel Ali - Frond J · Not started / Pending · Approximate project locationPalm Jebel Ali - Frond I · Not started / Pending · Approximate project locationPalm Jebel Ali - Frond A · Under construction · Approximate project locationPalm Jebel Ali - Frond B · Under construction · Approximate project locationPalm Jebel Ali - Frond E · Under construction · Approximate project locationPalm Jebel Ali - Frond C · Under construction · Approximate project locationPalm Jebel Ali - Frond F · Under construction · Approximate project locationPalm Jebel Ali - Frond D · Under construction · Approximate project locationPalm Jebel Ali - The Beach and Coral Collection · Under construction · Approximate project locationPalm Jebel Ali - The Beach and Coral Collection - Frond B · Under construction · Approximate project locationPalm Jebel Ali - The Beach and Coral Collection - Frond C · Under construction · Approximate project locationPalm Jebel Ali - The Beach and Coral Collection - Frond D · Under construction · Approximate project locationPalm Jebel Ali - The Beach and Coral Collection - Frond E · Under construction · Approximate project locationPalm Jebel Ali - The Beach and Coral Collection - Frond F · Under construction · Approximate project locationProject 4613, Palm Jabal Ali · Not started / Pending · Approximate project locationDubai Municipality · Makani
Under construction Not started / Pending Approximate project locations

Nakhlat Jabal Ali (DM community)

Phases (23)Ordered by registered sales over 24 months

Phases (23)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
Palm Central Private Residences - Frond MNot started 0.1% Jul 2029 32 months to go 32 months to go 212 213 —
Palm Central Private Residences - Frond NNot started 0% Dec 2030 49 months to go 49 months to go 222 210 —
Palm Jebel Ali - Frond PUnder construction 34.7% Sep 2027 10 months to go 10 months to go 0 0 —
Palm Jebel Ali - Frond OUnder construction 55.7% Sep 2027 10 months to go 10 months to go 0 0 —
Palm Jebel Ali - Frond NUnder construction 47.1% Oct 2027 11 months to go 11 months to go 0 0 —
Palm Jebel Ali - Frond MUnder construction 40.3% Oct 2027 11 months to go 11 months to go 0 0 —
Palm Jebel Ali - Frond LUnder construction 42.7% — — 0 0 —
Palm Jebel Ali - Frond KUnder construction 47.9% Dec 2027 13 months to go 13 months to go 0 0 —
Palm Jebel Ali - Frond JNot started 0% — — 0 0 —
Palm Jebel Ali - Frond INot started 0% — — 0 0 —
Palm Jebel Ali - Frond AUnder construction 11.1% Jan 2028 14 months to go 14 months to go 0 0 —
Palm Jebel Ali - Frond BUnder construction 10% Jan 2028 14 months to go 14 months to go 0 0 —
Palm Jebel Ali - Frond EUnder construction 9.2% Jan 2028 14 months to go 14 months to go 0 0 —
Palm Jebel Ali - Frond CUnder construction 8.6% Jan 2028 14 months to go 14 months to go 0 0 —
Palm Jebel Ali - Frond FUnder construction 11.8% Jan 2028 14 months to go 14 months to go 0 0 —
Palm Jebel Ali - Frond DUnder construction 8.7% Jan 2028 14 months to go 14 months to go 0 0 —
Palm Jebel Ali - The Beach and Coral CollectionUnder construction 2.4% Dec 2028 25 months to go 25 months to go 0 0 —
Palm Jebel Ali - The Beach and Coral Collection - Frond BUnder construction 2.7% Dec 2028 25 months to go 25 months to go 0 0 —
Palm Jebel Ali - The Beach and Coral Collection - Frond CUnder construction 2.8% Dec 2028 25 months to go 25 months to go 0 0 —
Palm Jebel Ali - The Beach and Coral Collection - Frond DUnder construction 2.2% Dec 2028 25 months to go 25 months to go 0 0 —
Palm Jebel Ali - The Beach and Coral Collection - Frond EUnder construction 2.6% Dec 2028 25 months to go 25 months to go 0 0 —
Palm Jebel Ali - The Beach and Coral Collection - Frond FUnder construction 2.5% Dec 2028 25 months to go 25 months to go 0 0 —
Project 4613, Palm Jabal AliPending 0% Oct 2030 47 months to go 47 months to go 0 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

23 phases
2027: 02028: 02029: 2122030: 222No end date: 0

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on Palm Jabal Ali

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology