DLD master projectAl Yalayis 2
Town Square 22 of 45 phases not yet completed · 4,156 units · 4,696 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Town Square has 45 projects in the Dubai Land Department projects register as of 1 November 2026: 22 not yet completed, with 4,156 units and villas. By DLD status: Completed 23 · Not started 5 · Under construction 16 · Pending 1.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 43 of the 45 phases: those with a map pin. Pins mark approximate locations.
Al Yalayis 2 (DM community)
Phases (45)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Town Square Zahra | Completed | 100% | Aug 2019 | — | 1,517 | 291 | — |
| Maha Townhouses | Completed | 100% | Aug 2025 | — | 500 | 250 | +58.5% |
| Rosewell | Not started | 0% | Dec 2028 25 months to go | 25 months to go | 217 | 178 | +0.7% |
| Rawda Apartments | Completed | 100% | Feb 2020 | — | 748 | 175 | — |
| Evelyn on the Park | Not started | 0% | Feb 2029 27 months to go | 27 months to go | 259 | 172 | -0.2% |
| The Baltimore | Under construction | 26.3% | Sep 2027 10 months to go | 10 months to go | 167 | 167 | +8.5% |
| Odessa | Under construction | 8% | Dec 2027 13 months to go | 13 months to go | 178 | 167 | — |
| Liva | Completed | 100% | Sep 2025 | — | 484 | 165 | +31.8% |
| Town Square Jenna And Warda | Completed | 100% | Sep 2019 | — | 729 | 159 | — |
| Augusta | Under construction | 5.3% | Jan 2028 14 months to go | 14 months to go | 154 | 143 | -2.1% |
| Hayat Boulevard | Completed | 100% | Feb 2020 | — | 678 | 142 | — |
| Lexington | Under construction | 4.5% | Sep 2027 10 months to go | 10 months to go | 142 | 139 | +3.7% |
| Berkshire Park | Under construction | 17.6% | Jun 2027 7 months to go | 7 months to go | 149 | 137 | +11.5% |
| Ellison | Under construction | 40.2% | Nov 2027 12 months to go | 12 months to go | 148 | 137 | -7.1% |
| Olbia | Not started | 0% | May 2028 18 months to go | 18 months to go | 156 | 134 | -3.6% |
| Camden | Under construction | 7.2% | Mar 2028 16 months to go | 16 months to go | 168 | 130 | +0.2% |
| Town Square Safi | Completed | 100% | Jan 2018 | — | 587 | 130 | — |
| Alton | Under construction | 5.2% | May 2028 18 months to go | 18 months to go | 149 | 119 | -3.9% |
| The Hamilton | Completed | 100% | Dec 2025 | — | 242 | 117 | +29.9% |
| The Regent | Completed | 100% | Jul 2025 | — | 238 | 116 | +48.1% |
| Hillcrest | Under construction | 38.4% | Jun 2027 7 months to go | 7 months to go | 171 | 114 | — |
| Fiori | Not started | 0% | Jun 2028 19 months to go | 19 months to go | 146 | 113 | -0.1% |
| Holland Gardens | Completed | 100% | Nov 2025 | — | 228 | 111 | +35% |
| The Mayfair | Completed | 100% | Aug 2026 | — | 242 | 106 | +24.1% |
| Una | Completed | 100% | Mar 2021 | — | 480 | 94 | — |
| Town Square Hayat | Completed | 100% | Dec 2017 | — | 730 | 92 | — |
| Noor Townhouses | Completed | 100% | Jun 2020 | — | 764 | 92 | — |
| Symphony | Under construction | 73.2% | — | — | 398 | 83 | +19.9% |
| Shams Townhouses | Completed | 100% | Dec 2024 | — | 212 | 73 | +68.4% |
| Ascot Residences | Completed | 100% | Nov 2024 | — | 153 | 68 | +42.5% |
| The Diplomat Residences | Completed | 100% | Nov 2024 | — | 153 | 68 | +35.9% |
| Grove | Under construction | 40.7% | — | — | 378 | 66 | +11.1% |
| Haya on the Park | Under construction | 35.3% | Feb 2027 3 months to go | 3 months to go | 196 | 52 | +13.5% |
| Naseem Townhouses | Completed | 100% | Dec 2020 | — | 322 | 45 | — |
| Oakmont | Not started | 0% | Apr 2029 29 months to go | 29 months to go | 281 | 42 | — |
| Fia | Under construction | 84.6% | — | — | 192 | 41 | +2.5% |
| Ora | Under construction | 47.4% | — | — | 157 | 40 | +5.3% |
| Safi Townhouses | Completed | 100% | Jun 2019 | — | 314 | 40 | — |
| Savannah | Under construction | 43.5% | Apr 2027 5 months to go | 5 months to go | 154 | 36 | +16.4% |
| Sama Townhouses | Completed | 100% | Apr 2021 | — | 264 | 35 | — |
| Reem Townhouses | Completed | 100% | Nov 2023 | — | 364 | 33 | +68.7% |
| Lana on the Park | Under construction | 35.9% | — | — | 196 | 31 | +5% |
| Kaya | Completed | 100% | Sep 2026 | — | 164 | 29 | +13.8% |
| Elaya | Completed | 100% | Oct 2026 | — | 153 | 24 | — |
| Project 4436, Al Yelayiss 2 | Pending | 0% | May 2029 30 months to go | 30 months to go | 0 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
22 phases| DLD end year | Projects | Units |
|---|---|---|
| 2027 | 8 | 1,305 |
| 2028 | 6 | 990 |
| 2029 | 3 | 540 |
| No end date | 5 | 1,321 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Town Square
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology