DLD project no. 637Completed308 units
Knight Bridge Court & Kensngton Manor نايت بريدج كورت آند كينسنجتون مانور Completed 12 July 2015 (DLD) · DLD end date Jul 2015 · DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.
Completed projects cannot be added to My units.
CompletionDLD readings of % built, beside the share of the planned period gone
% built
28 October 2026| Date | % built | Source |
|---|---|---|
| 1 March 2016 | 100% | DLD inspection |
| 8 September 2015 | 98% | DLD inspection |
| 27 January 2014 | 91.6% | DLD inspection |
| 23 May 2013 | 80.4% | DLD inspection |
| 13 November 2012 | 71.1% | DLD inspection |
Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗
Site timeline
± 6 monthsOur imagery reading holds no milestone for this project yet.
Our reading of historical satellite imagery
Registered period and actual build
Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.
Changes in the DLD register
No change to the end date, status or % built across the register exports we hold.
Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.
DLD registration
DLD services ↗Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.
Description in the DLD register: Freehold residential development located at Jumeirah Village South. Designed and constructed as 2B+G+4 Floor level building; designed to be built as a concrete skeleton and block works with cement render finishes.
DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae
Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.
AED · sqft
No off-plan sales are registered for this project since 2020, so there is no launch price.
Prices are over apartments, the type most sales in this project are.
| Bedrooms | Sales, 24 months | Latest median AED/sqft | Latest sales |
|---|---|---|---|
| Studio | 49 | 961 (8) | May 2026 – Nov 2026 |
| 1 BR | 24 | 847 (12) | Nov 2025 – Nov 2026 |
| 2 BR | 17 | 799 (9) | Nov 2025 – Nov 2026 |
Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.
Skyline Index
Buildings with sales: 2
Registered sale prices, rents and yields for Knight Bridge Court & Kensngton Manor, from DLD records.
Knight Bridge Court & Kensngton Manor: registered prices and rents on Skyline Index ↗Median AED/sqft by quarter
2020-Q1 → 2026-Q4| Quarter | Registered sales | Median AED/sqft | DLD area Al Barsha South Fourth |
|---|---|---|---|
| 2020-Q1 | 2 (off-plan 0, ready 2) | — | 579 |
| 2020-Q2 | 5 (off-plan 0, ready 5) | 411 | 698 |
| 2020-Q3 | 9 (off-plan 0, ready 9) | 576 | 609 |
| 2020-Q4 | 5 (off-plan 0, ready 5) | 627 | 652 |
| 2021-Q1 | 6 (off-plan 0, ready 6) | 518 | 693 |
| 2021-Q2 | 2 (off-plan 0, ready 2) | — | 725 |
| 2021-Q3 | 2 (off-plan 0, ready 2) | — | 816 |
| 2021-Q4 | 8 (off-plan 0, ready 8) | 584 | 828 |
| 2022-Q1 | 4 (off-plan 0, ready 4) | — | 882 |
| 2022-Q2 | 3 (off-plan 0, ready 3) | — | 902 |
| 2022-Q3 | 5 (off-plan 0, ready 5) | 641 | 877 |
| 2022-Q4 | 4 (off-plan 0, ready 4) | — | 923 |
| 2023-Q1 | 10 (off-plan 0, ready 10) | 576 | 882 |
| 2023-Q2 | 11 (off-plan 0, ready 11) | 690 | 966 |
| 2023-Q3 | 12 (off-plan 0, ready 12) | 640 | 943 |
| 2023-Q4 | 19 (off-plan 0, ready 19) | 786 | 971 |
| 2024-Q1 | 9 (off-plan 0, ready 9) | 720 | 1,054 |
| 2024-Q2 | 9 (off-plan 0, ready 9) | 851 | 1,070 |
| 2024-Q3 | 10 (off-plan 0, ready 10) | 837 | 1,086 |
| 2024-Q4 | 15 (off-plan 0, ready 15) | 866 | 1,211 |
| 2025-Q1 | 11 (off-plan 0, ready 11) | 953 | 1,254 |
| 2025-Q2 | 19 (off-plan 0, ready 19) | 927 | 1,261 |
| 2025-Q3 | 14 (off-plan 0, ready 14) | 933 | 1,241 |
| 2025-Q4 | 9 (off-plan 0, ready 9) | 846 | 1,352 |
| 2026-Q1 | 13 (off-plan 0, ready 13) | 898 | 1,355 |
| 2026-Q2 | 5 (off-plan 0, ready 5) | 849 | 1,272 |
| 2026-Q3 | 9 (off-plan 0, ready 9) | 905 | 1,224 |
| 2026-Q4 | 4 (off-plan 0, ready 4) | — | 1,289 |
Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Barsha South Fourth, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Registered sales per quarter
| Quarter | Registered sales | Median AED/sqft | DLD area Al Barsha South Fourth |
|---|---|---|---|
| 2020-Q1 | 2 (off-plan 0, ready 2) | — | 579 |
| 2020-Q2 | 5 (off-plan 0, ready 5) | 411 | 698 |
| 2020-Q3 | 9 (off-plan 0, ready 9) | 576 | 609 |
| 2020-Q4 | 5 (off-plan 0, ready 5) | 627 | 652 |
| 2021-Q1 | 6 (off-plan 0, ready 6) | 518 | 693 |
| 2021-Q2 | 2 (off-plan 0, ready 2) | — | 725 |
| 2021-Q3 | 2 (off-plan 0, ready 2) | — | 816 |
| 2021-Q4 | 8 (off-plan 0, ready 8) | 584 | 828 |
| 2022-Q1 | 4 (off-plan 0, ready 4) | — | 882 |
| 2022-Q2 | 3 (off-plan 0, ready 3) | — | 902 |
| 2022-Q3 | 5 (off-plan 0, ready 5) | 641 | 877 |
| 2022-Q4 | 4 (off-plan 0, ready 4) | — | 923 |
| 2023-Q1 | 10 (off-plan 0, ready 10) | 576 | 882 |
| 2023-Q2 | 11 (off-plan 0, ready 11) | 690 | 966 |
| 2023-Q3 | 12 (off-plan 0, ready 12) | 640 | 943 |
| 2023-Q4 | 19 (off-plan 0, ready 19) | 786 | 971 |
| 2024-Q1 | 9 (off-plan 0, ready 9) | 720 | 1,054 |
| 2024-Q2 | 9 (off-plan 0, ready 9) | 851 | 1,070 |
| 2024-Q3 | 10 (off-plan 0, ready 10) | 837 | 1,086 |
| 2024-Q4 | 15 (off-plan 0, ready 15) | 866 | 1,211 |
| 2025-Q1 | 11 (off-plan 0, ready 11) | 953 | 1,254 |
| 2025-Q2 | 19 (off-plan 0, ready 19) | 927 | 1,261 |
| 2025-Q3 | 14 (off-plan 0, ready 14) | 933 | 1,241 |
| 2025-Q4 | 9 (off-plan 0, ready 9) | 846 | 1,352 |
| 2026-Q1 | 13 (off-plan 0, ready 13) | 898 | 1,355 |
| 2026-Q2 | 5 (off-plan 0, ready 5) | 849 | 1,272 |
| 2026-Q3 | 9 (off-plan 0, ready 9) | 905 | 1,224 |
| 2026-Q4 | 4 (off-plan 0, ready 4) | — | 1,289 |
Registered sales per quarter, off-plan and ready units. Source: DLD.
Rents and gross yield
New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Gross yield: the median annual rent over the median registered ready sale price of the same bedroom count in this project over the same 12 months.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier | Gross yield |
|---|---|---|---|---|
| Studio | AED 39,000 | 96 | -2.5% | 9.3% |
| 1 BR | AED 54,000 | 41 | -1.8% | 8.7% |
| 2 BR | AED 69,500 | 13 | -9.7% | — |
Gross yield is before service charges, other costs and empty months.
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Mortgage registrations
Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.
| Quarter | Mortgage registrations |
|---|---|
| 2024-Q1 | 1 |
| 2024-Q2 | 1 |
| 2024-Q3 | 0 |
| 2024-Q4 | 2 |
| 2025-Q1 | 1 |
| 2025-Q2 | 2 |
| 2025-Q3 | 3 |
| 2025-Q4 | 7 · registered amount AED 2.6M |
| 2026-Q1 | 3 |
| 2026-Q2 | 1 |
| 2026-Q3 | 3 |
| 2026-Q4 | 0 |
Mortgage registrations on homes per quarter. Source: DLD.
Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 7; registered amount AED 4.2M.
Since the first registration in 2016-Q1: 68 in all.
Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Service charges
What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.
Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.
Source: Dubai Land Department, owners’ association budgets (service charges).
Registered sales
The newest sales DLD has registered in this project, as DLD publishes them.
| Date | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|
| 21 October 2026 | ready | Apartment · 2 BR | 980 | 850,000 | 867 |
| 16 October 2026 | ready | Apartment · Studio | 384 | 405,000 | 1,055 |
| 14 October 2026 | ready | Apartment · 1 BR | 1,010 | 688,000 | 681 |
| 6 October 2026 | ready | Apartment · 1 BR | 731 | 610,000 | 834 |
| 14 September 2026 | ready | Apartment · 2 BR | 1,332 | 940,000 | 706 |
| 31 August 2026 | ready | Apartment · Studio | 408 | 415,000 | 1,017 |
| 26 August 2026 | ready | Apartment · Studio | 436 | 400,000 | 917 |
| 17 August 2026 | ready | Apartment · Studio | 231 | 173,526 | 751 |
| 3 August 2026 | ready | Apartment · Studio | 436 | 460,000 | 1,055 |
| 27 July 2026 | ready | Apartment · 1 BR | 704 | 555,000 | 788 |
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
LocationAl Barsha South Fourth · Dubai Municipality community
Places near the project
Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.
School ratings: KHDA’s school directory ↗ · Report a wrong location
Dubai Municipality · Makani · © OpenStreetMap contributors · RTA
New homes within 1.5 km
Open projects within 1.5 km of the pin: 124, with 33,017 units and villas.
| DLD end year | Projects | Units and villas |
|---|---|---|
| 2013 | 1 | 165 |
| 2024 | 1 | 229 |
| 2025 | 5 | 1,480 |
| 2026 | 32 | 8,331 |
| 2027 | 31 | 8,156 |
| 2028 | 29 | 8,395 |
| 2029 | 7 | 2,031 |
| No end date | 18 | 4,230 |
Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.
Open projects in Al Barsha South Fourth: 153
Open projects in the same DLD area, by registered sales in 24 months.
| Project | Built | DLD end date | AED/sqft, 12 mo | Sales, 24 mo |
|---|---|---|---|---|
| Binghatti Circle | 22.1% | May 2027 | 1,611 | 779 |
| Serenz by Danube | 0.1% | Dec 2029 | 2,302 | 673 |
| Binghatti Amberhall | 70% | Feb 2026 | 1,696 | 623 |
| Binghatti Ruby | 65% | Feb 2026 | 1,967 | 552 |
| One Sky Park By Iman | 21.7% | Mar 2028 | 1,650 | 549 |
| Auresta Tower | 4.4% | Dec 2028 | 1,609 | 523 |
| Skyhills II by HRE | 96% | Jun 2026 | 1,531 | 481 |
| Skyhills III by HRE | 75.7% | Jun 2026 | 1,598 | 418 |
| Legado By Prescott | 23.3% | Aug 2027 | 1,748 | 342 |
| Violet Tower | 90.2% | Jun 2026 | 1,345 | 285 |
| The AUTOGRAPH-I Series | 4% | Aug 2028 | 1,691 | 269 |
| Maison Elysee Iii By Pantheon | 4.4% | Oct 2027 | 1,679 | 260 |
AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.
Developer in DLD data Acw Holding LTD · DLD developer no. 414
Completed a month or more after their DLD end date: 0 of 4 completed projects with both dates. In 4 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.
Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.
Other projects in Jumeirah Village Circle
DLD lists 410 projects in the master project Jumeirah Village Circle.
Questions about Knight Bridge Court & Kensngton Manor
When was Knight Bridge Court & Kensngton Manor completed?
Knight Bridge Court & Kensngton Manor is recorded as completed on 12 July 2015 (DLD register of 1 November 2026).
Who is the developer of Knight Bridge Court & Kensngton Manor?
Acw Holding LTD, as registered with DLD.
What is the DLD project number of Knight Bridge Court & Kensngton Manor?
637.
Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error