DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4240Under construction

Salva The Heights سالفا ذا هايتس Al Yelayiss 5 by Emaar Development P.J.S.C. 0.5% built (DLD register as of 1 November 2026) DLD end date Jul 2030 44 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0.5%
DLD register, 1 November 2026
Period elapsed
11%
May 2026 → Jul 2030
Latest sales
—
Fewer than 5 recent sales
Developer
110 projects
58 completed · 22,947 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built and period elapsed

28 October 2026
Built
0.5%Elapsed
11%

Two separate measures: one is DLD's % built, the other is time on the calendar.

Latest DLD register reading: 0.5% built on 28 October 2026 (register readings: 1). Latest DLD inspection: 0.5% built on 9 June 2026 (inspections: 2).
Every DLD inspection and every change in the register %, newest first
Date % built Source
9 June 2026 0.5% DLD inspection
18 November 2025 0% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗ Period elapsed: our calculation from DLD’s start and end dates.

Our completion calculation

Recent pace
0.1 pt/month
0% on 18 November 2025 → 0.5% on 9 June 2026
At the register date
0.9%
1 November 2026

Our calculation from DLD readings. It describes the recent pace only; it is not a forecast of the completion date.

Site timeline

± 6 months
Works startedDec 2025 ± 6 months
Structure risingNot seen yet
Topped outNot seen yet
FinishedNot seen yet

Each date is ± 6 months. This is our reading, not DLD's; no image is shown. Read from imagery dated 21 March 2024 to 28 January 2026; method imagery-v1.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Dates and progress are those in the Dubai Land Department projects register on each register date, not inspection dates. DLD can revise the end date; we keep every register reading from 28 October 2026 on and list the changes here.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
4240
Escrow agent
Emirates Islamic Bank P.J.S.C.
Zoning authority
Dubai Municipality
DLD area
Al Yelayiss 5
Units · villas
0 · 0
Start → DLD end
May 2026 → Jul 2030
Registered units3 bed 185 · 4 bed 232 · 5+ bed 66; sizes 3,463–4,312 sqft

Homes: villas 483.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Residential development consisting of 483 villas (G+2)

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Looking for a unit in this or similar projects?

Tell us what you are looking for in Salva The Heights or similar projects. We reply by e-mail, and your request stays with CraneScore.

We send a 6-digit code to confirm it.
Bedrooms

Estimated value range

Not enough registered off-plan sales for an estimate (at least 5 of one bedroom count in 12 months).

Automated estimate, not a valuation

Track this unit

Automated estimate from registered off-plan sales (developer sales and resales mixed); not a valuation by a registered valuer; not for mortgage or court use.

Resale asking prices against the original price

Fewer than 5 resale offers with an original price are tracked for this project.

Across all Dubai off-plan resale offers we track: -3.9% (1,105 offers).

Median asking premium by share of the price already paid (number of offers); shown from 5 offers
Paid to the developer This project All Dubai
0–30% paid—0% (9)
30–50% paid—-5% (51)
50–70% paid—-1.5% (65)
70% paid or more—-3.5% (45)

Asking prices of off-plan resale offers we track, compared with each offer's original price, with the 4% DLD fee removed on both sides. A negative value means asking below the original price. Only aggregates of at least 5 offers are shown; no individual offer, seller or agent is.

Thinking of selling your unit?

Thinking of reselling your unit in Salva The Heights? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

Payment scenarioEnter the developer’s plan to see what you pay and when. Handover starts at the DLD end date (Jul 2030); move it with the slider.

A scenario from your own inputs, not this project's verified payment plan.

Common plans

Plan shares add up to 100% (must be 100%).

Handover
Jul 2030
Paid by handover
AED 1,045,000
Fees included
Price paid at handover
100%
Total cost
AED 1,045,000
Fees: AED 45,000

Payments per quarter

AED

Payments per quarter, AED, fees included. Illustration from your inputs.

The DLD fee (4% of the price) and the fees above are paid at booking. With a resale price, the unit is sold at handover and the buyer takes over any unpaid balance; agent fees, mortgage costs and service charges are left out. An illustration from your inputs, not financial advice.

Mortgage for a unit here

Questions about financing a unit in Salva The Heights? Leave your details and we reply by e-mail. Your request stays with CraneScore.

We send a 6-digit code to confirm it.

LocationAl Yalayis 5 · Dubai Municipality community

Approximate project location© OpenStreetMap contributors · Dubai Municipality · Makani
Approximate project location

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallRijat Retail Mall-12 · 5.3 km
ParkMag 5 Park area · 2.1 km

Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 6, with 0 units and villas.

2029: 02030: 0

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Yalayis 5: 4

Open projects in the same DLD area with a DLD end year from 2029 to 2031, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Serro The Heights 0.5% Mar 2030 — 0
Serro 2 The Heights 0.5% May 2030 — 0
Faro The Heights 0% Jun 2030 — 0
Faro 2 The Heights 0% Jun 2030 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Yalayis 5

Developer in DLD data Emaar Development P.J.S.C. · DLD developer no. 1211

Projects registered
110
58 completed · 44 under construction · 8 not started
Units delivered
22,947
12,652 in the pipeline
Median build time
40 months
completed projects measured: 58
Past the DLD end date
0
of 41 under construction with a DLD end date

Completed a month or more after their DLD end date: 0 of 57 completed projects with both dates. In 38 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Emaar Development P.J.S.C. is one of 7 DLD-registered developers we list together as Emaar. See the group

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Questions about Salva The Heights

When is Salva The Heights's handover?

DLD lists an end date of Jul 2030 (register of 1 November 2026); the SPA sets the handover terms.

Is Salva The Heights past its DLD end date?

No. Its DLD end date is Jul 2030, 44 months after the register of 1 November 2026.

How far along is Salva The Heights?

0.5% built in the DLD register of 1 November 2026.

Who is the developer of Salva The Heights?

Emaar Development P.J.S.C., as registered with DLD.

What is the DLD project number of Salva The Heights?

4240.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error