DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 251Completed165 units

Sandoval Gardens ساندوفال جاردن Al Barsha South Fourth · Jumeirah Village Circle by Bavaria Gulf Sandoval LimitedAll phases of Jumeirah Village Circle Completed 22 December 2011 (DLD) DLD end date Dec 2011 DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Dec 2011
DLD end date Dec 2011
Build time
34 months
Feb 2009 → Dec 2011
Latest sales
945 AED/sqft
11 sales
1 BR rent
68,000 AED/yr
17 leases, 12 months
Developer
2 projects
2 completed · 185 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 3).

DLD has no site-inspection readings for this project in our copy.

Every DLD inspection and every change in the register %, newest first
Date % built Source
5 August 2022 100% DLD register, archived export

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 5 August 2022, 12 May 2024.

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Registered period
34 monthsActual build
34 months
Start date
15 February 2009
DLD end date
22 December 2011
Completion date
22 December 2011
Completion vs DLD end date
On the date

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
251
Escrow agent
Mashreq Bank PSC
Zoning authority
Trakhees
Master project
Jumeirah Village Circle
DLD area
Al Barsha South Fourth
Units · villas
165 · 0
Start → DLD end
Feb 2009 → Dec 2011
Registered unitsStudio 57 · 1 bed 86 · 2 bed 22; sizes 605–976 sqft

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Freehold residential development located in Jumeirah Village First. The project consists of main building 2B+G+4 storey plus 2 townhouses blocks. The buildings are being constructed as concrete structure and block with external and internal finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft

No off-plan sales are registered for this project since 2020, so there is no launch price.

Prices are over apartments, the type most sales in this project are.

Registered sales of apartments by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
Studio 6 — —
1 BR 20 983 (8) Nov 2025 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2020-Q1 → 2026-Q3

Median AED/sqft of registered sales per quarter (apartments). Source: DLD. Grey dashed line: DLD area Al Barsha South Fourth, median AED/sqft of ready sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

Rents and gross yield

New Ejari rent contracts for apartments in this project, 12 months to 5 November 2026, against the 12 months before. Fewer than 10 ready sales per bedroom count in those 12 months, so no yield is shown.

Bedrooms Median annual rent New contracts Change on a year earlier
Studio AED 47,807 18 -0.4%
1 BR AED 68,000 17 +3%

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 5; registered amount AED 3.1M.

Since the first registration in 2012-Q1: 136 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Service charges

What owners pay a year in completed buildings of the project’s master community, from their owners’ association budgets. A building’s own charge is set by its own budget.

Apartment buildings’ budgets; villa and townhouse budgets are left out.
16.31 AED/sqft a year
Jumeirah Village Circle: median of 112 developments’ owners’ association budgets, 2026

Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.

Source: Dubai Land Department, owners’ association budgets (service charges).

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 13 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
30 September 2026readyApartment · 1 BR 1,802 1,075,000 597
6 August 2026readyApartment · 1 BR 752 823 1
18 June 2026readyApartment · Studio 590 502,855 852
18 May 2026readyApartment · Studio 1,129 660,000 585
5 March 2026readyApartment · 1 BR 814 1,050,000 1,290
25 February 2026readyApartment · 1 BR 1,073 775,000 722
23 February 2026readyApartment · 1 BR 814 800,000 983
20 January 2026readyApartment · 1 BR 741 700,000 945
12 January 2026readyApartment · 1 BR 752 2,312 3
26 December 2025readyApartment · 1 BR 834 925,000 1,109

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationAl Barsha South Fourth · Dubai Municipality community

Halfa · 350 mFarfar · 360 mStar Mart Supermarket · 410 mAl Nakhla · 410 mSupermarket · 630 mAwadia Grocery · 820 mKinderopvang smallsteps leidsche rijn · 880 mMe'aisem City Center · 1.1 kmCity Centre Meaisem · 1.1 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Malls and supermarkets Schools and hospitals Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationJumeirah Golf Estates Metro Station · Red Metro line · 5.1 km
MallMe'aisem City Center · 1.1 km
SupermarketStar Mart Supermarket · 410 m
HospitalMediclinic Springs · 2.9 km
SchoolKinderopvang smallsteps leidsche rijn · 880 m
ParkHalfa · 350 m
BeachBeach · 7.4 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 107, with 31,310 units and villas.

2010: 02013: 1652024: 2292025: 1,7482026: 7,9992027: 6,6762028: 7,1792029: 2,3952030: 0No end date: 4,919

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Barsha South Fourth: 153

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Binghatti Circle 22.1% May 2027 1,611 779
Serenz by Danube 0.1% Dec 2029 2,302 673
Binghatti Amberhall 70% Feb 2026 1,696 623
Binghatti Ruby 65% Feb 2026 1,967 552
One Sky Park By Iman 21.7% Mar 2028 1,650 549
Auresta Tower 4.4% Dec 2028 1,609 523
Skyhills II by HRE 96% Jun 2026 1,531 481
Skyhills III by HRE 75.7% Jun 2026 1,598 418
Legado By Prescott 23.3% Aug 2027 1,748 342
Violet Tower 90.2% Jun 2026 1,345 285
The AUTOGRAPH-I Series 4% Aug 2028 1,691 269
Maison Elysee Iii By Pantheon 4.4% Oct 2027 1,679 260

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Barsha South Fourth

Developer in DLD data Bavaria Gulf Sandoval Limited · DLD developer no. 141

Projects registered
2
2 completed · 0 under construction · 0 not started
Units delivered
185
0 in the pipeline

Completed a month or more after their DLD end date: 0 of 2 completed projects with both dates. In 2 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Jumeirah Village Circle

DLD lists 410 projects in the master project Jumeirah Village Circle.

Luxury Family ResidenceUnder construction · 76% · Dec 2023
North Forty Three Serviced ResidencesUnder construction · 94.7% · Jul 2024
7 Park Central By MeteoraUnder construction · 90.2% · Apr 2025
The PortmanUnder construction · 78.7% · Sep 2025
Serenity Lakes 2Under construction · 50.5% · Nov 2025
Levanto By ORO24Under construction · 66% · Dec 2025
Sky Suites by Peace HomesUnder construction · 55.5% · Dec 2025
Ashton Park Residences The SecondUnder construction · 70.1% · Dec 2025
Maimoon GardensUnder construction · 78% · Dec 2025
99 Park PlaceUnder construction · 90% · Dec 2025
Elitz By DanubeUnder construction · 91.8% · Dec 2025
Q Gardens LoftsUnder construction · 90.7% · Dec 2025

Questions about Sandoval Gardens

When was Sandoval Gardens completed?

Sandoval Gardens is recorded as completed on 22 December 2011 (DLD register of 1 November 2026).

Who is the developer of Sandoval Gardens?

Bavaria Gulf Sandoval Limited, as registered with DLD.

What is the DLD project number of Sandoval Gardens?

251.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error