DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 4381Not started754 units

Sorrento سورينتو Al Hebiah Fifth · DAMAC Lagoons by Island Oasis PropertiesAll phases of DAMAC Lagoons DLD status: Not started (DLD register as of 1 November 2026) DLD end date Jan 2030 38 months to go DLD register as of 1 November 2026. The end date is the one registered with DLD, not a handover forecast.

% built
0.3%
DLD register, 1 November 2026
Registered start
Jul 2026
DLD end date Jan 2030
Latest sales
—
Fewer than 5 recent sales
Developer
36 projects
9 completed · 912 units delivered

Completion

DLD status: Not started. 0.3% built, DLD end date 31 January 2030. DLD Project Status shows inspection reports once works begin.

DLD register readings
Date % built DLD end dateDLD status
1 November 2026 0.3% 31 January 2030Not started
28 October 2026 0.3% 31 January 2030Not started

Source: DLD projects register, export of 1 November 2026.

Inspection photos and reports

DLD’s Project Status service (Mashrooi) shows inspection details and site photos. Look the project up by its number.

CraneScore links to DLD and does not copy or host its photos or reports.

DLD registration

DLD services ↗
DLD project number
4381
Escrow agent
Abu Dhabi Commercial Bank
Zoning authority
Dubai Development Authority (DDA)
Master project
DAMAC Lagoons
DLD area
Al Hebiah Fifth
Units · villas
754 · 0
Start → DLD end
Jul 2026 → Jan 2030
Registered unitsStudio 524 · 1 bed 224; sizes 398–735 sqft

Also registered: shops and showrooms 6.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: Project consists of 4 Residential towers of G+1P+7+R floors. it is designed to have concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

LocationAl Hebiah Fifth · Dubai Municipality community

Park · 1.2 kmProject location© OpenStreetMap contributors · Dubai Municipality · RTA · Makani
Project location Parks and beaches

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

Metro stationJumeirah Golf Estates Metro Station · Red Metro line · 6.1 km
MallMall · 2.5 km
SupermarketSpinneys · 2.5 km
HospitalNMC dip · 7.1 km
SchoolSouth View School · 2.2 km
ParkPark · 1.2 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors · RTA

New homes within 1.5 km

Open projects within 1.5 km of the pin: 27, with 5,871 units and villas.

2025: 82026: 02027: 2,3692028: 1,5582029: 02030: 1,018No end date: 918

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Al Hebiah Fifth: 28

Open projects in the same DLD area with a DLD end year from 2029 to 2031, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Cetara 0.3% Jan 2030 — 0
Piazza Roma 0.2% Jun 2030 — 0

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Al Hebiah Fifth

Developer in DLD data Island Oasis Properties · DLD developer no. 921

Projects registered
36
9 completed · 24 under construction · 3 not started
Units delivered
912
6,617 in the pipeline
Median build time
49 months
completed projects measured: 9
Past the DLD end date
8
of 14 under construction with a DLD end date

Completed a month or more after their DLD end date: 6 of 9 completed projects with both dates. In 3 of them the completion date equals the DLD end date, which DLD may set at completion, so this count can understate the gap.

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error