DLD master projectAl Hebiah Fifth
DAMAC Lagoons 14 of 19 phases not yet completed · 5,483 units · 4,472 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
DAMAC Lagoons has 19 projects in the Dubai Land Department projects register as of 1 November 2026: 14 not yet completed, with 5,483 units and villas. By DLD status: Under construction 11 · Completed 5 · Not started 3. Under construction and past the DLD end date: 5.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 19 of the 19 phases: those with a map pin. Pins mark approximate locations.
Al Hebiah Fifth (DM community)
Phases (19)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Damac Lagoons - Valencia | Under construction | 5.2% | Feb 2028 15 months to go | 15 months to go | 1,558 | 1,366 | -3.7% |
| Damac Lagoons - Lagoon Views 13 | Under construction | 6% | Dec 2027 13 months to go | 13 months to go | 1,509 | 1,110 | — |
| Damac Lagoons - Portofino | Under construction | 97.1% | Jun 2025 16 months past it | 16 months past it | 0 | 267 | — |
| Damac Lagoons - Mykonos | Under construction | 81.1% | Dec 2025 10 months past it | 10 months past it | 0 | 219 | — |
| Damac Lagoons - Santorini (1) | Completed | 100% | Jul 2025 | — | 0 | 211 | — |
| Damac Lagoons - Costa Brava (1) | Completed | 100% | Apr 2026 | — | 0 | 188 | — |
| Damac Lagoons - Costa Brava (2) | Completed | 100% | Aug 2026 | — | 0 | 173 | — |
| Damac Lagoons - Nice 1 | Under construction | 93.7% | Jul 2025 15 months past it | 15 months past it | 0 | 171 | — |
| Damac Lagoons - Lagoon Views 12 | Under construction | 36.5% | Jun 2027 7 months to go | 7 months to go | 322 | 161 | -2% |
| Damac Lagoons - Venice (1) | Under construction | 74.4% | Sep 2025 13 months past it | 13 months past it | 0 | 131 | — |
| Damac Lagoons - Santorini (2) | Completed | 100% | Feb 2026 | — | 0 | 130 | — |
| Damac Lagoons - Nice 2 | Under construction | 83.9% | Jul 2025 15 months past it | 15 months past it | 0 | 107 | — |
| Damac Lagoons - Morocco 2 | Under construction | 65.3% | — | — | 0 | 96 | — |
| Damac Lagoons - Lagoon Views 11 | Under construction | 42.6% | Jun 2027 7 months to go | 7 months to go | 322 | 82 | +2.7% |
| Damac Lagoons - Morocco 1 | Under construction | 76.9% | — | — | 0 | 32 | — |
| Damac Lagoons - Santorini (3) | Completed | 100% | Apr 2026 | — | 0 | 28 | — |
| Piazza Roma | Not started | 0.2% | Jun 2030 43 months to go | 43 months to go | 336 | 0 | — |
| Sorrento | Not started | 0.3% | Jan 2030 38 months to go | 38 months to go | 754 | 0 | — |
| Cetara | Not started | 0.3% | Jan 2030 38 months to go | 38 months to go | 682 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
14 phases| DLD end year | Projects | Units |
|---|---|---|
| 2025 | 5 | 0 |
| 2027 | 3 | 2,153 |
| 2028 | 1 | 1,558 |
| 2030 | 3 | 1,772 |
| No end date | 2 | 0 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on DAMAC Lagoons
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology