DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1–8 of 8 projects, most registered sales in 24 months first

1–8 of 8 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date / completion Sales, 24 mo
Terra Tower3278 · Wadi Al Safa 5 · Dubai Land Residence ComplexDugasta Properties Development L.L.C Under construction 7.4% Apr 2027 5 mo to go 323
Al Haseen Residence 43562 · Saih Shuaib 2Dugasta Properties Development L.L.C Under construction 11.8% Dec 2026 1 mo to go 155
Al Haseen Residence 33484 · Saih Shuaib 2Dugasta Properties Development L.L.C Under construction 10.1% May 2027 6 mo to go 148
Moonsa Residences 23280 · Warsan Fourth · International City Phase 3Dugasta Properties Development L.L.C Under construction 1% Dec 2026 1 mo to go 99
MOONSA Residences2834 · Warsan Fourth · International City Phase 3Dugasta Properties Development L.L.C Completed 100% Oct 2026 Completed 79
Astra Residences4040 · Madinat Al Mataar · Dubai South Residential DistrictDugasta Properties Development L.L.C Under construction 15.3% Aug 2027 9 mo to go 23
Al Haseen Residence1867 · Saih Shuaib 2Dugasta Properties Development L.L.C Completed 100% Apr 2020 Completed 14
Al Haseen Residence 54461 · Saih Shuaib 2Dugasta Properties Development L.L.C Under construction 4.2% Jun 2027 7 mo to go 6

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.