DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026

1–13 of 13 projects, most registered sales in 24 months first

1–13 of 13 projects, most registered sales in 24 months first
Project Developer DLD status Built DLD end date Past DLD end date Sales, 24 mo
Samana Barari Lagoons3422 · Wadi Al Safa 3 · MajanSamana Signature Real Estate Developments L.L.C Under construction 16.5% Mar 2028 16 mo to go— 524
Samana Hills South3796 · Saih Shuaib 2Samana Signature Real Estate Developments L.L.C Under construction 12.1% May 2028 18 mo to go— 512
Samana Parkville3791 · Wadi Al Safa 5 · Dubai Land Residence ComplexSamana Signature Real Estate Developments L.L.C Under construction 13.9% Sep 2028 22 mo to go— 419
Samana Imperial Garden3797 · Al Barshaa South Third · ArjanSamana Signature Real Estate Developments L.L.C Under construction 4.2% Dec 2028 25 mo to go— 326
Samana Lake Views 23087 · Me'Aisem First · International Media Production ZoneSamana Signature Real Estate Developments L.L.C Under construction 8.9% — — 196
Samana Hills South 34074 · Saih Shuaib 2Samana Signature Real Estate Developments L.L.C Under construction 4.6% Aug 2028 21 mo to go— 145
Samana Hills South 24025 · Saih Shuaib 2Samana Signature Real Estate Developments L.L.C Under construction 5.3% Aug 2028 21 mo to go— 130
Samana Lake Views3071 · Me'Aisem First · International Media Production ZoneSamana Signature Real Estate Developments L.L.C Under construction 22.9% — — 109
Samana Skyros2608 · Al Barshaa South Third · ArjanSamana Signature Real Estate Developments L.L.C Under construction 71.3% Apr 2026 6 mo past6 mo 30
Samana Business Park 24110 · Wadi Al Safa 3 · MajanSamana Signature Real Estate Developments L.L.C Under construction 3% Oct 2028 23 mo to go— 2
Samana Business Park3812 · Wadi Al Safa 3 · MajanSamana Signature Real Estate Developments L.L.C Under construction 12.8% Sep 2028 22 mo to go— 1
Project 4572, Wadi Al Safa 34572 · Wadi Al Safa 3 · MajanSamana Signature Real Estate Developments L.L.C Pending 0% Sep 2030 46 mo to go— 0
Samana Barari Avenue3829 · Wadi Al Safa 3 · MajanSamana Signature Real Estate Developments L.L.C Under construction 6% Oct 2028 23 mo to go— 0

How to read this list

DLD status
Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
Built
The latest % complete that DLD publishes for the project.
DLD end date
The completion date in the DLD register, with whole months to go from the export date.
Past DLD end date
Whole months since the DLD end date, for projects DLD still lists as under construction.
Sales, 24 mo
Sales of units in the project registered with DLD in the last 24 months.