Dubai off-plan projects 1,801 of 3,486 DLD projects are not yet completed: 1,239 under construction, 562 not started or pending. 227 under construction are past their DLD end date. DLD projects register, export of 1 November 2026 · sales to 5 November 2026
| Project | Developer | DLD status | Built | DLD end date / completion | Past DLD end date | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Ritaj1042 · Dubai Investment Park Second | Dubai Investment Real Estate (L L C) | Completed | 100% | Jun 2011 Completed | — | 291 |
| Violet Tower2824 · Al Barsha South Fourth · Jumeirah Village Circle | Dubai Investment Real Estate (L L C) | Under construction | 90.2% | Jun 2026 4 mo past | 4 mo | 285 |
| Mirdif Hills - Asayel Avenue3389 · Mirdif | Dubai Investment Real Estate (L L C) | Under construction | 33.1% | May 2027 6 mo to go | — | 109 |
| Mirdif HILLS- Nasayem Avenue1834 · Mirdif | Dubai Investment Real Estate (L L C) | Completed | 100% | Mar 2020 Completed | — | 79 |
| Mirdif HILLS- Al Multaqa Avenue1835 · Mirdif | Dubai Investment Real Estate (L L C) | Completed | 100% | Aug 2021 Completed | — | 43 |
| Mirdif HILLS- Janayen Avenue1073 · Mirdif | Dubai Investment Real Estate (L L C) | Completed | 100% | Jan 2020 Completed | — | 38 |
| Al Vista3802 · Bukadra | Dubai Investment Real Estate (L L C) | Under construction | 9.5% | Oct 2027 11 mo to go | — | 3 |
How to read this list
- DLD status
- Under construction, not started, pending or completed, as the Dubai Land Department records it. The status filter counts not started and pending together.
- Built
- The latest % complete that DLD publishes for the project.
- DLD end date
- The completion date in the DLD register, with whole months to go from the export date.
- Past DLD end date
- Whole months since the DLD end date, for projects DLD still lists as under construction.
- Sales, 24 mo
- Sales of units in the project registered with DLD in the last 24 months.