DLD master projectAl Barsha South Third
Arjan 30 of 81 phases not yet completed · 10,432 units · 6,846 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Arjan has 81 projects in the Dubai Land Department projects register as of 1 November 2026: 30 not yet completed, with 10,432 units and villas. By DLD status: Not started 4 · Under construction 22 · Completed 51 · Pending 4. Under construction and past the DLD end date: 8.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 81 of the 81 phases: those with a map pin. Pins mark approximate locations.
Al Barsha South Third (DM community)
Phases (81)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Marquis One | Not started | 0.3% | Dec 2028 25 months to go | 25 months to go | 489 | 397 | +1.3% |
| The central downtown | Under construction | 10.5% | Mar 2028 16 months to go | 16 months to go | 1,254 | 365 | +12.6% |
| Samana Imperial Garden | Under construction | 4.2% | Dec 2028 25 months to go | 25 months to go | 344 | 326 | -7.4% |
| One Beverly | Under construction | 72.9% | Dec 2026 1 month to go | 1 month to go | 389 | 287 | — |
| Ashley Hills | Under construction | 74.1% | Mar 2027 4 months to go | 4 months to go | 616 | 287 | +2.2% |
| Binghatti Hillcrest | Under construction | 60% | Dec 2026 1 month to go | 1 month to go | 396 | 282 | -4.2% |
| Floarea Grande | Under construction | 48.2% | Aug 2027 9 months to go | 9 months to go | 222 | 222 | +4.1% |
| Vincitore Dolce Vita | Under construction | 40% | — | — | 715 | 210 | +3.7% |
| Empire Estates | Under construction | 60% | Dec 2026 1 month to go | 1 month to go | 344 | 207 | +6.8% |
| butterfly | Under construction | 7.7% | Jan 2029 26 months to go | 26 months to go | 596 | 198 | -2% |
| SKYZ By Danube | Completed | 100% | Nov 2025 | — | 827 | 179 | +26.7% |
| Torino By ORO24 | Completed | 100% | Oct 2025 | — | 625 | 173 | +49.3% |
| Siraj Tower | Completed | 100% | Oct 2014 | — | 374 | 167 | — |
| Enchante By GRID | Not started | 0% | Dec 2028 25 months to go | 25 months to go | 286 | 161 | +3.6% |
| Beverly Boulevard | Completed | 100% | Sep 2024 | — | 271 | 156 | +45% |
| 48 Parkside | Completed | 100% | May 2026 | — | 187 | 139 | +12.5% |
| Parkside Boulevard | Under construction | 51.9% | Dec 2027 13 months to go | 13 months to go | 171 | 128 | +6% |
| Miraclz Tower | Completed | 100% | Jul 2019 | — | 599 | 127 | — |
| Oxford Gardens | Completed | 100% | Sep 2025 | — | 240 | 124 | +49.3% |
| Vincitore Benessere | Completed | 100% | Jan 2023 | — | 419 | 118 | — |
| Avelon Boulevard | Completed | 100% | Dec 2025 | — | 135 | 117 | +10.9% |
| Marquis Insignia | Under construction | 67.3% | — | — | 249 | 111 | — |
| ELEVATE by Prescott | Completed | 100% | Jun 2026 | — | 223 | 107 | +36.7% |
| Gharbi I Residences | Completed | 100% | Sep 2026 | — | 170 | 107 | -2.4% |
| Lincoln Park | Completed | 100% | Jul 2014 | — | 519 | 100 | — |
| Resortz Residence | Completed | 100% | Sep 2019 | — | 444 | 96 | — |
| Jewelz Residence | Completed | 100% | Oct 2023 | — | 463 | 95 | — |
| Floarea Residence | Completed | 100% | Aug 2025 | — | 206 | 90 | +38.5% |
| Burj View Residence | Completed | 100% | Aug 2016 | — | 120 | 81 | — |
| Joya Dorado Residence | Completed | 100% | Aug 2026 | — | 422 | 79 | +26.5% |
| Art House Hills by Adaan and Tuscany | Not started | 0.2% | Dec 2028 25 months to go | 25 months to go | 328 | 66 | -2.3% |
| Arbor View | Completed | 100% | Apr 2026 | — | 171 | 66 | +10.4% |
| Trinity By Karma | Under construction | 30.9% | Dec 2026 1 month to go | 1 month to go | 309 | 63 | -0.6% |
| NAS3 | Completed | 100% | Apr 2026 | — | 288 | 62 | — |
| Gardenia Livings | Completed | 100% | Sep 2023 | — | 156 | 59 | +40.7% |
| Sunrise Legend | Completed | 100% | Aug 2021 | — | 112 | 55 | +15.2% |
| Aryene Greens | Under construction | 80.1% | Nov 2022 47 months past it | 47 months past it | 124 | 54 | — |
| Bond Enclave | Under construction | 20% | Nov 2027 12 months to go | 12 months to go | 158 | 54 | +7% |
| Joya Blanca Residences | Completed | 100% | Sep 2022 | — | 313 | 53 | +83% |
| Marquis Galleria | Completed | 100% | Apr 2026 | — | 126 | 52 | +35.1% |
| Samana Hills | Completed | 100% | Jun 2022 | — | 202 | 51 | — |
| Gardens 2 | Under construction | 68.5% | Dec 2025 10 months past it | 10 months past it | 223 | 50 | +7.4% |
| Divine Living | Completed | 100% | Sep 2025 | — | 118 | 50 | +33.4% |
| Genesis | Completed | 100% | Feb 2020 | — | 200 | 49 | — |
| Samana Park Views | Completed | 100% | Apr 2024 | — | 178 | 49 | +19.3% |
| ELZ Residence | Completed | 100% | May 2022 | — | 275 | 44 | — |
| The Wings | Completed | 100% | Sep 2019 | — | 340 | 43 | — |
| Vincitore Volare | Under construction | 63.4% | Jun 2025 17 months past it | 17 months past it | 415 | 40 | -1.3% |
| Green Diamond 1 | Completed | 100% | May 2018 | — | 194 | 40 | — |
| Vincitore Boulevard | Completed | 100% | Oct 2020 | — | 248 | 38 | — |
| Prime Gardens | Completed | 100% | Apr 2024 | — | 139 | 36 | +31.5% |
| Lincoln Park ( North Side) | Completed | 100% | Jul 2014 | — | 172 | 35 | — |
| Adhara Star | Completed | 100% | Dec 2025 | — | 115 | 34 | — |
| Vincitore Palacio | Completed | 100% | May 2017 | — | 179 | 33 | — |
| Legacy By Sunrise | Completed | 100% | May 2024 | — | 132 | 33 | — |
| Lincoln Park (Sheffield) | Completed | 100% | Apr 2014 | — | 170 | 32 | — |
| Samana Green | Completed | 100% | Dec 2020 | — | 122 | 31 | — |
| 2020 Marquis | Completed | 100% | May 2020 | — | 150 | 31 | — |
| Q Gardens Boutique Residences | Completed | 100% | Mar 2022 | — | 153 | 31 | — |
| Samana Skyros | Under construction | 71.3% | Apr 2026 6 months past it | 6 months past it | 441 | 30 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
30 phases| DLD end year | Projects | Units |
|---|---|---|
| 2022 | 1 | 124 |
| 2025 | 3 | 977 |
| 2026 | 8 | 2,936 |
| 2027 | 6 | 1,293 |
| 2028 | 7 | 2,701 |
| 2029 | 2 | 1,437 |
| No end date | 3 | 964 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Arjan
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology