Our location listNakhlat Deira
Bay Grove 4 of 4 phases not yet completed · 1,154 units · 1,176 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Bay Grove has 4 projects in the Dubai Land Department projects register as of 1 November 2026: 4 not yet completed, with 1,154 units and villas. By DLD status: Under construction 4.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 4 of the 4 phases: those with a map pin. Pins mark approximate locations.
Nakhlat Deira (DM community)
Phases (4)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Bay Grove Residences C - Dubai Islands | Under construction | 7.3% | Apr 2028 17 months to go | 17 months to go | 360 | 369 | +1.7% |
| Bay Grove Residences, Dubai Islands | Under construction | 12.3% | Mar 2028 16 months to go | 16 months to go | 296 | 307 | +0.9% |
| Bay Grove Residences D - Dubai Islands | Under construction | 3.7% | Sep 2028 22 months to go | 22 months to go | 257 | 258 | +0.3% |
| Bay Grove Residences B - Dubai Islands | Under construction | 7.6% | Sep 2028 22 months to go | 22 months to go | 241 | 242 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
4 phases| DLD end year | Projects | Units |
|---|---|---|
| 2028 | 4 | 1,154 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.