DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD master projectAl Wasl

City Walk 9 of 27 phases not yet completed · 1,924 units · 1,644 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026

City Walk has 27 projects in the Dubai Land Department projects register as of 1 November 2026: 9 not yet completed, with 1,924 units and villas. By DLD status: Under construction 6 · Not started 3 · Completed 18.

Phases
27
18 completed
Not yet completed
9
6 under construction
Units not yet completed
1,924
units and villas
Sales, 24 mo
1,644
registered with DLD

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Map of the phasesThe map shows 27 of the 27 phases: those with a map pin. Pins mark approximate locations.

City Walk Crestlane 2 · Under construction · Project locationCity Walk Crestlane 1 · Not started · Project locationCity Walk Crestlane 3 · Under construction · Project locationCity Walk Crestlane 4 · Not started · Project locationCity Walk Crestlane 5 · Not started · Project locationNo.17, No.18a,No.18b and No.19 Citywalk Residential · Completed · Project locationCastleton · Completed · Project locationLaurel · Completed · Project locationFern · Completed · Project locationCentral Park at City Walk -Building 1 · Completed · Project locationMyrtle · Completed · Project locationErin · Completed · Project locationNO.9 & NO.10 Citywalk Residential · Completed · Project locationCeladon · Completed · Project locationVerve City Walk · Under construction · Project locationNo. 4A, NO.4B, NO.5 Citywalk Residential · Completed · Project locationNO.1, NO.2A, NO.2B, NO.3A And 3B Citywalk Residential · Completed · Project locationViridian · Completed · Project locationThyme · Completed · Project locationCity Walk Northline 2 · Under construction · Project locationNo. 6A And NO.6B Citywalk Residential · Completed · Project locationNO.20, NO.21A, NO.21B And NO.22 Citywalk Residential · Completed · Project locationCentral Park Plaza · Under construction · Project locationCity Walk Northline 1 · Under construction · Project locationNO.15 & NO.16 Citywalk Residential · Completed · Project locationNO.23A and 23B Citywalk Residential · Completed · Project locationRove City Walk · Completed · Project locationDubai Municipality · Makani
Under construction Not started Completed

Al Wasl (DM community)

Phases (27)Ordered by registered sales over 24 months

Phases (27)
ProjectDLD status Built DLD end date / completion To DLD end date Units Sales, 24 mo Since launch
City Walk Crestlane 2Under construction 6.8% Dec 2028 25 months to go 25 months to go 203 202 —
City Walk Crestlane 1Not started 0.2% Sep 2029 34 months to go 34 months to go 202 199 —
City Walk Crestlane 3Under construction 4.6% Dec 2028 25 months to go 25 months to go 195 195 —
City Walk Crestlane 4Not started 0% Apr 2030 41 months to go 41 months to go 204 186 -4.1%
City Walk Crestlane 5Not started 0% Apr 2030 41 months to go 41 months to go 161 151 -1.2%
No.17, No.18a,No.18b and No.19 Citywalk ResidentialCompleted 100% Jan 2017 — 196 100 —
CastletonCompleted 100% Aug 2026 — 214 74 +26.9%
LaurelCompleted 100% Jul 2026 — 218 61 +34.3%
FernCompleted 100% Oct 2026 — 214 58 +28.8%
Central Park at City Walk -Building 1Completed 94.4% Oct 2021 — 184 53 —
MyrtleCompleted 100% Apr 2025 — 130 49 +47.3%
ErinCompleted 100% Jun 2026 — 200 48 +16.5%
NO.9 & NO.10 Citywalk ResidentialCompleted 100% Dec 2016 — 166 36 —
CeladonCompleted 100% Sep 2025 — 161 36 +54.4%
Verve City WalkUnder construction 13.7% Sep 2028 22 months to go 22 months to go 440 35 +3.6%
No. 4A, NO.4B, NO.5 Citywalk ResidentialCompleted 100% Dec 2016 — 148 29 —
NO.1, NO.2A, NO.2B, NO.3A And 3B Citywalk ResidentialCompleted 100% Feb 2017 — 286 26 —
ViridianCompleted 100% Nov 2024 — 130 26 +61.9%
ThymeCompleted 100% Aug 2026 — 148 18 —
City Walk Northline 2Under construction 37.1% — — 192 13 —
No. 6A And NO.6B Citywalk ResidentialCompleted 100% Dec 2016 — 68 13 —
NO.20, NO.21A, NO.21B And NO.22 Citywalk ResidentialCompleted 100% May 2017 — 187 12 —
Central Park PlazaUnder construction 43.7% Oct 2026 This month This month 212 10 —
City Walk Northline 1Under construction 38.1% — — 115 7 —
NO.15 & NO.16 Citywalk ResidentialCompleted 100% May 2017 — 113 7 —
NO.23A and 23B Citywalk ResidentialCompleted 100% Jul 2017 — 68 0 —
Rove City WalkCompleted 100% Sep 2021 — 517 0 —

Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.

Units not yet completed, by DLD end year

9 phases
2026: 2122028: 8382029: 2022030: 365No end date: 307

Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.

More on City Walk

Own a unit in one of these phases? Track it free

Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology