DLD master projectAl Barsha South Second
Dubai Science Park 12 of 16 phases not yet completed · 9,079 units · 6,937 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Dubai Science Park has 16 projects in the Dubai Land Department projects register as of 1 November 2026: 12 not yet completed, with 9,079 units and villas. By DLD status: Under construction 9 · Conditionally activating 1 · Completed 4 · Pending 2. Under construction and past the DLD end date: 3.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 16 of the 16 phases: those with a map pin. Pins mark approximate locations.
Al Barsha South Second (DM community)
Phases (16)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Binghatti Hillviews | Under construction | 32.6% | Apr 2026 7 months past it | 7 months past it | 1,575 | 1,556 | — |
| Skyhills Astra by HRE | Under construction | 47.1% | Jun 2028 19 months to go | 19 months to go | 1,911 | 1,555 | +15.2% |
| Binghatti Hills | Under construction | 90% | — | — | 1,701 | 1,085 | +25% |
| Vincitore Aqua Dimore | Conditionally activating | 14.1% | — | — | 987 | 570 | +2.6% |
| SAAS Hills | Under construction | 13% | Mar 2027 4 months to go | 4 months to go | 859 | 459 | +4.8% |
| Vincitore Aqua Flora | Under construction | 1.3% | Jun 2028 19 months to go | 19 months to go | 546 | 406 | +3.5% |
| Binghatti Hillside | Under construction | 80% | Jun 2026 4 months past it | 4 months past it | 411 | 356 | +6.1% |
| Skyhills I by HRE | Completed | 100% | Jul 2026 | — | 1,145 | 252 | — |
| 11 Hills Park | Under construction | 80.1% | Mar 2027 4 months to go | 4 months to go | 571 | 224 | +18.7% |
| Empire Livings | Under construction | 13.3% | Nov 2027 12 months to go | 12 months to go | 210 | 173 | +3.2% |
| Opalz By Danube | Completed | 100% | Apr 2025 | — | 575 | 110 | +9.4% |
| Bella Rose | Completed | 100% | Dec 2020 | — | 490 | 92 | — |
| Nova Tower | Under construction | 40.1% | Sep 2026 1 month past it | 1 month past it | 134 | 53 | -1.1% |
| Montrose | Completed | 100% | Apr 2018 | — | 302 | 46 | — |
| Azure Park Residences | Pending | 0% | Aug 2027 9 months to go | 9 months to go | 174 | 0 | — |
| Project 4574, Al Barshaa South Second | Pending | 0% | Dec 2029 37 months to go | 37 months to go | 0 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
12 phases| DLD end year | Projects | Units |
|---|---|---|
| 2026 | 3 | 2,120 |
| 2027 | 4 | 1,814 |
| 2028 | 2 | 2,457 |
| 2029 | 1 | 0 |
| No end date | 2 | 2,688 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Dubai Science Park
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology