International Media Production Zone 25 of 39 phases not yet completed · 8,465 units · 7,996 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
International Media Production Zone has 39 projects in the Dubai Land Department projects register as of 1 November 2026: 25 not yet completed, with 8,465 units and villas. By DLD status: Under construction 16 · Completed 14 · Not started 5 · Pending 4. Under construction and past the DLD end date: 2.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 39 of the 39 phases: those with a map pin. Pins mark approximate locations.
Me'aisem First (DM community)
Phases (39)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Binghatti Elite | Under construction | 53.3% | Jun 2026 4 months past it | 4 months past it | 1,745 | 1,793 | +15.6% |
| Samana Resorts | Under construction | 5.9% | May 2028 18 months to go | 18 months to go | 969 | 960 | -1.4% |
| Samana Sky Views | Under construction | 2.2% | Jul 2028 20 months to go | 20 months to go | 556 | 546 | -0.6% |
| Elm At Park Five | Under construction | 16.2% | Jun 2027 7 months to go | 7 months to go | 532 | 529 | +2.4% |
| Lakeside | Completed | 100% | Aug 2014 | — | 1,967 | 442 | — |
| Vista by Vision | Under construction | 12.2% | Sep 2027 10 months to go | 10 months to go | 328 | 309 | +2% |
| Reef 996 | Not started | 0.1% | Sep 2028 22 months to go | 22 months to go | 505 | 247 | +5.4% |
| Ember At Park Five | Under construction | 18.2% | Jun 2027 7 months to go | 7 months to go | 205 | 197 | +0.9% |
| Samana Lake Views 2 | Under construction | 8.9% | — | — | 548 | 196 | +6.2% |
| Lago Vista | Completed | 100% | Jan 2011 | — | 1,018 | 190 | — |
| The Crescent | Completed | 100% | Dec 2008 | — | 863 | 189 | — |
| Ivy At Park Five | Under construction | 6.3% | Dec 2027 13 months to go | 13 months to go | 210 | 188 | -0.7% |
| Jannat | Completed | 100% | Jun 2026 | — | 362 | 181 | — |
| Soul by vision | Under construction | 77% | Dec 2026 1 month to go | 1 month to go | 176 | 176 | +3.6% |
| Midtown - Afnan | Completed | 100% | Oct 2019 | — | 677 | 160 | — |
| Midtown - Noor | Completed | 100% | Feb 2023 | — | 606 | 153 | +21.2% |
| Viera Residences | Completed | 100% | Feb 2026 | — | 144 | 145 | +5.4% |
| Sera Gardens by Vision | Not started | 0% | Apr 2028 17 months to go | 17 months to go | 246 | 141 | +1.9% |
| Neem At Park Five | Under construction | 15.2% | Dec 2027 13 months to go | 13 months to go | 145 | 131 | +4.6% |
| Midtown - Dania | Completed | 100% | Mar 2020 | — | 591 | 121 | — |
| Qasr Sabah I , Ii ,III | Completed | 100% | Aug 2015 | — | 406 | 120 | — |
| Centrium Tower | Completed | 100% | Dec 2013 | — | 585 | 117 | — |
| Samana Lake Views | Under construction | 22.9% | — | — | 451 | 109 | — |
| Midtown - Mesk | Completed | 100% | Aug 2022 | — | 282 | 106 | — |
| Golf Terrace Residences By ASAK | Under construction | 5.1% | Oct 2027 11 months to go | 11 months to go | 105 | 91 | -7.6% |
| Golf Grove by Regent | Under construction | 8.7% | Jan 2028 14 months to go | 14 months to go | 98 | 89 | -1.2% |
| Alder At Park Five | Under construction | 6.1% | Dec 2027 13 months to go | 13 months to go | 75 | 69 | 0% |
| Imperial Residence | Under construction | 43% | Apr 2026 6 months past it | 6 months past it | 137 | 64 | — |
| Oakwood Residency | Completed | 100% | Jul 2012 | — | 348 | 51 | — |
| Eira | Not started | 0% | Jun 2029 31 months to go | 31 months to go | 271 | 46 | — |
| Samana Portofino | Under construction | 60.1% | — | — | 226 | 40 | +7.6% |
| MYKA Residence | Completed | 100% | Feb 2023 | — | 120 | 32 | — |
| Lawncrest By Zimaya | Not started | 0% | Jun 2029 31 months to go | 31 months to go | 183 | 29 | — |
| Nirvana Residences - I | Not started | 0% | Dec 2028 25 months to go | 25 months to go | 326 | 21 | — |
| Sun Point Dubai | Completed | 100% | Mar 2022 | — | 255 | 18 | +14% |
| Golf Terraces | Pending | 0% | Dec 2026 1 month to go | 1 month to go | 60 | 0 | — |
| Al Ezz Tower by Abu Alnaga | Pending | 1.7% | Dec 2029 37 months to go | 37 months to go | 202 | 0 | — |
| Eterna by GRID | Pending | 0% | Mar 2029 28 months to go | 28 months to go | 166 | 0 | — |
| Project 4596, Me'Aisem First | Pending | 0% | Mar 2028 16 months to go | 16 months to go | 0 | 0 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
25 phases| DLD end year | Projects | Units |
|---|---|---|
| 2026 | 4 | 2,118 |
| 2027 | 7 | 1,600 |
| 2028 | 7 | 2,700 |
| 2029 | 4 | 822 |
| No end date | 3 | 1,225 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on International Media Production Zone
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology