The Valley 15 of 22 phases not yet completed · 5,156 units · 3,650 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
The Valley has 22 projects in the Dubai Land Department projects register as of 1 November 2026: 15 not yet completed, with 5,156 units and villas. By DLD status: Under construction 15 · Completed 7.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 22 of the 22 phases: those with a map pin. Pins mark approximate locations.
Al Yufrah 1 (DM community)
Phases (22)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| The Valley - Farm Grove | Under construction | 10% | Dec 2028 25 months to go | 25 months to go | 482 | 499 | 0% |
| The Valley - Rivera | Under construction | 3.9% | Nov 2028 24 months to go | 24 months to go | 378 | 385 | +1.8% |
| The Valley - Velora 2 | Under construction | 40.3% | Jul 2028 20 months to go | 20 months to go | 312 | 322 | +2.6% |
| The Valley - Farm Grove 2 | Under construction | 9.8% | Oct 2028 23 months to go | 23 months to go | 290 | 300 | — |
| The Valley - Elva | Under construction | 25.9% | Oct 2028 23 months to go | 23 months to go | 244 | 254 | -8.9% |
| The Valley - Avena | Under construction | 24.5% | Jun 2028 19 months to go | 19 months to go | 322 | 190 | -6.6% |
| The Valley - Avena 2 | Under construction | 42.9% | Jul 2028 20 months to go | 20 months to go | 332 | 176 | -3.6% |
| The Valley - Kaia | Under construction | 19.1% | Jul 2028 20 months to go | 20 months to go | 156 | 160 | — |
| The Valley-Nara | Completed | 100% | Dec 2024 | — | 372 | 156 | +97.2% |
| The Valley - Elora | Completed | 100% | Mar 2026 | — | 430 | 156 | +58.8% |
| The Valley - Talia | Completed | 100% | Mar 2025 | — | 330 | 142 | +82.9% |
| The Valley - Elea | Under construction | 22% | Jun 2028 19 months to go | 19 months to go | 128 | 128 | — |
| The Valley - Orania | Completed | 100% | Dec 2025 | — | 308 | 127 | +70.6% |
| The Valley - Rivana | Under construction | 95.2% | Mar 2027 4 months to go | 4 months to go | 486 | 123 | +16.8% |
| The Valley - Nima | Under construction | 80% | — | — | 520 | 121 | +15.3% |
| The Valley - Venera | Under construction | 51.7% | Sep 2028 22 months to go | 22 months to go | 696 | 88 | +1.4% |
| The Valley - Lillia | Completed | 100% | Jul 2026 | — | 406 | 87 | +18.3% |
| The Valley - Velora | Under construction | 50.1% | Aug 2028 21 months to go | 21 months to go | 488 | 52 | +7.2% |
| The Valley - Alana | Under construction | 81.6% | — | — | 322 | 51 | +0.1% |
| The Valley - Farm Gardens 2 | Under construction | 59.1% | — | — | 0 | 49 | — |
| The Valley - Farm Gardens | Completed | 100% | Apr 2026 | — | 0 | 47 | — |
| The Valley - Eden | Completed | 100% | Jun 2023 | — | 362 | 37 | — |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
15 phases| DLD end year | Projects | Units |
|---|---|---|
| 2027 | 1 | 486 |
| 2028 | 11 | 3,828 |
| No end date | 3 | 842 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on The Valley
Own a unit in one of these phases? Track it free
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026. Methodology