Verdana Residence 10 of 10 phases not yet completed · 2,937 units · 1,364 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Verdana Residence has 10 projects in the Dubai Land Department projects register as of 1 November 2026: 10 not yet completed, with 2,937 units and villas. By DLD status: Not started 8 · Under construction 2. Under construction and past the DLD end date: 2.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Map of the phasesThe map shows 10 of the 10 phases: those with a map pin. Pins mark approximate locations.
Dubai Investment Park First (DM community)
Phases (10)Ordered by registered sales over 24 months
| Project | DLD status | Built | DLD end date / completion | To DLD end date | Units | Sales, 24 mo | Since launch |
|---|---|---|---|---|---|---|---|
| Verdana Residence 4 | Not started | 0% | Sep 2028 22 months to go | 22 months to go | 392 | 248 | -10.8% |
| Verdana Residence 5 | Not started | 0% | Sep 2028 22 months to go | 22 months to go | 392 | 225 | -18.8% |
| Verdana Residence 3 | Not started | 0% | Sep 2028 22 months to go | 22 months to go | 278 | 175 | +3.6% |
| Verdana Residence 7 | Not started | 0% | Dec 2028 25 months to go | 25 months to go | 392 | 164 | +9.3% |
| Verdana Residence 6 | Not started | 0% | Dec 2028 25 months to go | 25 months to go | 363 | 135 | -17.7% |
| Verdana Residence 2 | Under construction | 20% | Apr 2026 6 months past it | 6 months past it | 239 | 126 | +38.7% |
| Verdana Residence 10 | Not started | 0% | Mar 2029 28 months to go | 28 months to go | 191 | 92 | -22.2% |
| Verdana Residence 9 | Not started | 0% | Mar 2029 28 months to go | 28 months to go | 256 | 75 | — |
| Verdana Residence 8 | Not started | 0% | Dec 2028 25 months to go | 25 months to go | 210 | 64 | — |
| Verdana Residence | Under construction | 96.1% | Dec 2025 10 months past it | 10 months past it | 224 | 60 | +5.8% |
Phases under construction or not started come first, by DLD end date; then other DLD statuses, then completed phases. Since launch: the change in median AED/sqft of home sales from the project's launch window to the last 12 months, where both have enough sales (see the project page). DLD can change an end date; the dates here are those in the latest export.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
10 phases| DLD end year | Projects | Units |
|---|---|---|
| 2025 | 1 | 224 |
| 2026 | 1 | 239 |
| 2028 | 6 | 2,027 |
| 2029 | 2 | 447 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.