Skip to content
DLD register · 1 Nov 20261,801 not completed1,239 under construction227 past DLD end date · median 7 mo238 registered to end in 2026487,805 units in pipeline
AED · sqft
Sign inTrack your unit

Have the DLD project number from your SPA or Oqood? Type it, for example 3334.

Menu

Account

Track my unit, freeSign in

E-mail and a 6-digit code. No password.

Language

Currency and area unit

Display and privacy

CraneScore is not part of, or affiliated with, the Dubai Land Department. Nobody can pay to change a figure. Contact · Privacy · Terms

DLD project no. 2733Completed189 units

Albarari Ixora Villas البراري أكسورا فيلاز Wadi Al Safa 3 · Al Barari by Al Barari Ixora Real Estate L.L.CAll phases of Al Barari Completed 9 October 2025 (DLD) no DLD end date registered DLD register as of 1 November 2026 DLD register as of 1 November 2026. Dates are the ones registered with DLD.

Completed projects cannot be added to My units.

Completed
Oct 2025
No DLD end date registered
Build time
28 months
Jun 2023 → Oct 2025
Launch → resale
4,031 AED/sqft
+74.9% on launch Launch 2,305 · 34 sales since completion
4 BR rent
460,000 AED/yr
Gross yield 5.6% · 97 leases
Developer
2 projects
1 completed · 189 units delivered

CompletionDLD readings of % built, beside the share of the planned period gone

% built

28 October 2026
Built
100%
Latest DLD register reading: 100% built on 28 October 2026 (register readings: 2). Latest DLD inspection: 100% built on 9 October 2025 (inspections: 6).
Every DLD inspection and every change in the register %, newest first
Date % built Source
9 October 2025 100% DLD inspection
4 June 2025 88.3% DLD inspection
26 September 2024 64% DLD inspection
12 May 2024 14% DLD register, archived export
3 May 2024 26% DLD inspection
15 February 2024 13.6% DLD inspection
17 August 2023 2.2% DLD inspection

Source: Dubai Land Department projects register, as of 1 November 2026. Earlier readings: archived DLD projects exports of 12 May 2024. Source: Dubai Land Department, Project Status inspections (dates and % only), collected on 7 November 2026. DLD Project Status ↗

Site timeline

± 6 months

Our imagery reading holds no milestone for this project yet.

Our reading of historical satellite imagery

Registered period and actual build

Actual build
28 months
Start date
1 June 2023
DLD end date
—
Completion date
9 October 2025
Completion vs DLD end date
—

Source: DLD projects register. Build time: our calculation from DLD’s start and completion dates.

Changes in the DLD register

No change to the end date, status or % built across the register exports we hold.

Source: DLD projects register exports, compared by CraneScore. Planned dates against DLD's completion date. In 69% of completed projects in the register the completion date and the DLD end date are the same day, which suggests DLD sets the end date at completion, so this comparison can show no gap where there was one.

DLD registration

DLD services ↗
DLD project number
2733
Escrow agent
Commercial Bank of Dubai(PSC)
Zoning authority
Dubai Development Authority (DDA)
Master project
Al Barari
DLD area
Wadi Al Safa 3
Units · villas
0 · 189
Start → DLD end
Jun 2023 → —
Registered units4 bed 189; sizes 4,756–4,764 sqft

Homes: villas 189.

Counts from DLD's units register; villas from its buildings register. Sizes: the middle half of the homes' registered areas (25th to 75th percentile), villas by built-up area. Source: Dubai Land Department open data (units and buildings registers, export of 5 November 2026), under the Dubai Data Open Data Licence.

Description in the DLD register: 189x G+2+R, the project designed to have a concrete structure and block with internal and external finishes.

DLD's own services for this project, including the Dubai REST app: dubailand.gov.ae

Price historyRegistered sale prices for this project, in AED per sq ft, with the number of sales in each figure.

AED · sqft
Launch price
2,305 AED/sqft
Median of 187 off-plan sales in the 90 days from the first one (Nov 2023)
Latest registered sales
4,033 AED/sqft
Median of 33 home sales in the last 12 months, ready and off-plan
Change
+75%
Same home types on both sides, weighted by the later sales

Dubai Statistics Center residential price index (villas), 2023-Q4 to 2026-Q2: +29.5%.

Prices are over villas and townhouses, the type most sales in this project are.

Median AED/sqft (number of sales) by bedroom count, where both periods have at least 5 sales
Bedrooms Launch price Latest registered sales Change
4 BR 2,305 (187) 3,830 (12) +66.2%
Registered sales of villas and townhouses by bedroom count over the last 24 months, and the median AED/sqft of the latest ready sales (number of sales)
Bedrooms Sales, 24 months Latest median AED/sqft Latest sales
4 BR 81 3,830 (12) May 2026 – Nov 2026

Launch price: median AED/sqft of the project's off-plan home sales in the 90 days from its first one, for a first sale on or after 1 March 2020; Skyline Index uses the same rule. Latest: home sales of the last 12 months after the launch window, ready and off-plan; the change compares the same home types. The bedroom table compares the launch window with the last 6 months (12 when 6 have fewer than 5 sales). Off-plan registrations include developer sales and resales; DLD open data does not tell them apart. Sales more than 4 times off the median are left out.

Median AED/sqft by quarter

2023-Q4 → 2026-Q4

Median AED/sqft of registered sales per quarter (villas and townhouses). Source: DLD. Grey dashed line: DLD area Wadi Al Safa 3, median AED/sqft of ready sales of villas and townhouses by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.

Registered sales per quarter

Registered sales per quarter, off-plan and ready units. Source: DLD.

What launch buyers got

The launch price against the registered resales after completion, same home types on both sides.

Launch price
2,305 AED/sqft
Median of 187 off-plan sales, Nov 2023 – Feb 2024
Resales after completion
4,031 AED/sqft
Median of 34 ready sales, Nov 2025 – Nov 2026
Change
+74.9%
Same home types, weighted by the resales

Over the same span, ready homes in DLD area Wadi Al Safa 3 changed +11.9% (same home types).

Launch: the 90 days from the first off-plan sale (2020 onward). Resales: ready sales in the 12 months after the DLD completion date, or 24 when 12 hold fewer than 5. A price change is not a return: it leaves out fees, service charges, rent and the payment plan.

Rents and gross yield

New Ejari rent contracts for villas and townhouses in this project, 12 months to 5 November 2026, against the 12 months before. Gross yield: the median annual rent over the median registered ready sale price of the same bedroom count in this project over the same 12 months.

Bedrooms Median annual rent New contracts Change on a year earlier Gross yield
4 BR AED 460,000 97 — 5.6%

Gross yield is before service charges, other costs and empty months.

New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.

Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.

Mortgage registrations

Home mortgages DLD has registered on units in this project, per quarter, in the 12 quarters to 5 November 2026.

Mortgage registrations on homes per quarter. Source: DLD.

Mortgage registrations in the last 4 quarters (2026-Q1 to 2026-Q4): 19; registered amount AED 80.6M.

Since the first registration in 2025-Q2: 119 in all.

Counts DLD's mortgage registrations on homes in this project, including pre-registrations on off-plan units and lease-to-own registrations; portfolio and developer mortgages are left out. Amounts are the values DLD registers, shown for 5 registrations or more. A registration says nothing about the lender or the terms.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

Registered sales

The newest sales DLD has registered in this project, as DLD publishes them.

The newest 10 of 34 registered sales in the 12 months to 5 November 2026
DateMarketType Size (sqft) Price (AED) AED/sqft
19 October 2026readyVilla · 4 BR 1,941 7,000,000 3,606
12 October 2026readyVilla · 4 BR 1,941 8,200,000 4,225
9 October 2026readyVilla · 4 BR 1,941 6,800,000 3,503
2 October 2026readyVilla · 4 BR 1,935 8,575,000 4,432
21 September 2026readyVilla · 4 BR 1,935 8,600,000 4,444
16 September 2026readyVilla · 4 BR 1,934 7,360,000 3,806
9 September 2026readyVilla · 4 BR 1,934 6,450,000 3,335
26 June 2026readyVilla · 4 BR 1,934 8,400,000 4,343
25 June 2026readyVilla · 4 BR 1,934 6,600,000 3,413
12 June 2026readyVilla · 4 BR 1,940 8,600,000 4,433

Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.

Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence

LocationWadi Al Safa 3 · Dubai Municipality community

Zoom Market Al Bararri · 1.5 kmApproximate project location© OpenStreetMap contributors · Dubai Municipality · Makani
Approximate project location Malls and supermarkets

Places near the project

Straight-line distances from the project’s map pin, rounded to 10 m. The nearest place of each kind.

MallRemal Mall · 1.5 km
SupermarketZoom Market Al Bararri · 1.5 km
HospitalHospital · 6.3 km
SchoolSchool · 1.6 km
ParkPark · 2.2 km
BeachBeach · 6.9 km

School ratings: KHDA’s school directory ↗ · Report a wrong location

Dubai Municipality · Makani · © OpenStreetMap contributors

New homes within 1.5 km

Open projects within 1.5 km of the pin: 54, with 18,505 units and villas.

2022: 1202026: 7242027: 11,6722028: 4,1062029: 1,1442030: 0No end date: 739

Open projects within 1.5 km of the pin, by DLD end year Highlighted: this project’s DLD end year.

Open projects in Wadi Al Safa 3: 95

Open projects in the same DLD area, by registered sales in 24 months.

Project Built DLD end date AED/sqft, 12 mo Sales, 24 mo
Binghatti Vintage 0% Mar 2027 1,842 1,522
Binghatti Skyflame 1 0% Dec 2027 1,400 913
Binghatti Titania 0% Feb 2027 1,609 727
Samana Barari Heights 4% Oct 2028 1,826 693
Samana Barari Lagoons 16.5% Mar 2028 1,585 524
Binghatti Skyflame 2 0% Dec 2027 1,404 480
Rabdan Gates 5.2% Jun 2028 1,207 428
The Wilds 3 3.1% May 2029 — 399
Living Legends Phase 5 48.9% Mar 2025 1,430 360
Taormina Village 1 20.4% Dec 2027 2,415 300
The Wilds 2 5.7% Feb 2029 — 255
Lazord By Lapis 27.6% Dec 2026 1,458 252

AED/sqft: median of the project’s registered home sales in the last 12 months, ready and off-plan; a dash with too few sales.

Every project in Wadi Al Safa 3

Developer in DLD data Al Barari Ixora Real Estate L.L.C · DLD developer no. 1488

Projects registered
2
1 completed · 0 under construction · 1 not started
Units delivered
189
0 in the pipeline

Source: DLD projects register, export of 1 November 2026. Medians: our calculation, 3 projects or more.

Other projects in Al Barari

DLD lists 7 projects in the master project Al Barari.

The CapeUnder construction · 0.7% · Dec 2028
The Nest Revolution VillaPending · 5% · —
Project 1074, Wadi Al Safa 3Completed · 100% · Oct 2010
Seventh HeavenCompleted · 100% · Sep 2020
Seventh Heaven - AshjarCompleted · 100% · Dec 2022
Chorisia 1 VillasCompleted · 100% · Mar 2023
Chorisia 2 VillasCompleted · 100% · Mar 2024

Questions about Albarari Ixora Villas

When was Albarari Ixora Villas completed?

Albarari Ixora Villas is recorded as completed on 9 October 2025 (DLD register of 1 November 2026).

Who is the developer of Albarari Ixora Villas?

Al Barari Ixora Real Estate L.L.C, as registered with DLD.

What is the DLD project number of Albarari Ixora Villas?

2733.

Source: Dubai Land Department open data: projects register (export of 1 November 2026) and registered sales to 5 November 2026; Dubai Statistics Center price index. Methodology · Report a data error