Wadi Al Safa 3 وادي الصفا 3 95 projects not yet completed · 20,345 units · 12,130 sales in 24 months DLD projects register as of 1 November 2026 · sales to 5 November 2026
Wadi Al Safa 3 has 95 projects not yet completed in the Dubai Land Department projects register as of 1 November 2026, with 20,345 units and villas; its projects had 12,130 registered sales in the last 24 months.
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Projects on the map95 of the 95 projects listed have a map pin.
Projects not yet completed (95)Projects not yet completed in Wadi Al Safa 3, by registered sales in 24 months
| Project | Developer | DLD status | Built | DLD end date | Past DLD end date | Sales, 24 mo |
|---|---|---|---|---|---|---|
| Binghatti Vintage4102 · Wadi Al Safa 3 · Majan | Binghatti Developers FZE | Not started | 0% | Mar 2027 4 mo to go | — | 1,522 |
| Binghatti Skyflame 14393 · Wadi Al Safa 3 · Majan | Binghatti Developers FZE | Not started | 0% | Dec 2027 13 mo to go | — | 913 |
| Binghatti Titania4104 · Wadi Al Safa 3 · Majan | Binghatti Developers FZE | Not started | 0% | Feb 2027 3 mo to go | — | 727 |
| Samana Barari Heights3871 · Wadi Al Safa 3 · Majan | Samana International Real Estate Development L.L.C | Under construction | 4% | Oct 2028 23 mo to go | — | 693 |
| Samana Barari Lagoons3422 · Wadi Al Safa 3 · Majan | Samana Signature Real Estate Developments L.L.C | Under construction | 16.5% | Mar 2028 16 mo to go | — | 524 |
| Binghatti Skyflame 24399 · Wadi Al Safa 3 · Majan | Binghatti Developers FZE | Not started | 0% | Dec 2027 13 mo to go | — | 480 |
| Rabdan Gates3587 · Wadi Al Safa 3 · Majan | Rabdan Real Estate Development L.L.C | Under construction | 5.2% | Jun 2028 19 mo to go | — | 428 |
| The Wilds 33607 · Wadi Al Safa 3 | Aurora SPV 2 L.L.C | Under construction | 3.1% | May 2029 30 mo to go | — | 399 |
| Living Legends Phase 51324 · Wadi Al Safa 3 · Living Legends | Amer Alghurair Real Estate Development CO. L.L.C | Under construction | 48.9% | Mar 2025 19 mo past | 19 mo | 360 |
| Taormina Village 13108 · Wadi Al Safa 3 | Reportage Prime Properties L.L.C | Under construction | 20.4% | Dec 2027 13 mo to go | — | 300 |
| The Wilds 23606 · Wadi Al Safa 3 · Living Legends | Aurora SPV 2 L.L.C | Under construction | 5.7% | Feb 2029 27 mo to go | — | 255 |
| Lazord By Lapis3209 · Wadi Al Safa 3 · Majan | Lapis Properties L.L.C | Under construction | 27.6% | Dec 2026 1 mo to go | — | 252 |
| The Wilds 13600 · Wadi Al Safa 3 · Living Legends | Aurora SPV 2 L.L.C | Under construction | 7.5% | Jan 2029 26 mo to go | — | 251 |
| Forest City Tower3330 · Wadi Al Safa 3 · Majan | Al Helal Al Zahaby Real Estate Development L.L.C | Under construction | 70.1% | Apr 2027 5 mo to go | — | 211 |
| Living Legends Phase 61325 · Wadi Al Safa 3 · Living Legends | Dawn Real Estate Development L.L.C | Under construction | 76.7% | Jul 2026 3 mo past | 3 mo | 207 |
| Jade Tower3074 · Wadi Al Safa 3 · Majan | Tiger Properties | Under construction | 11% | Mar 2027 4 mo to go | — | 202 |
| The Haven II3315 · Wadi Al Safa 3 · Majan | Meraki Real Estate Development L.L.C | Under construction | 56.3% | Dec 2026 1 mo to go | — | 202 |
| Vincitore Wellness Estate4148 · Wadi Al Safa 3 · Majan | Vincitore Premium Real Estate Development L.L.C | Not started | 0% | Feb 2030 39 mo to go | — | 170 |
| Samana Barari Views2835 · Wadi Al Safa 3 · Majan | Samana International Real Estate Development L.L.C | Under construction | 26.8% | Mar 2027 4 mo to go | — | 159 |
| The Wilds Residences4377 · Wadi Al Safa 3 | Aurora SPV 2 L.L.C | Not started | 0% | Jun 2030 43 mo to go | — | 159 |
| Gate Eleven Residences3729 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Amwaj Alkhaleej Real Estate Development L.L.C | Under construction | 30.6% | Mar 2028 16 mo to go | — | 147 |
| BARARIGATE by ADE4221 · Wadi Al Safa 3 · Majan | A D E Properties L.L.C | Under construction | 1.7% | Dec 2028 25 mo to go | — | 141 |
| The Cape4258 · Wadi Al Safa 3 · Al Barari | Barari Three Real Estate Development L.L.C | Under construction | 0.7% | Dec 2028 25 mo to go | — | 126 |
| Divine Al Barari3759 · Wadi Al Safa 3 · Majan | Takmeel Real Estate Development L.L.C | Under construction | 20.3% | Mar 2028 16 mo to go | — | 122 |
| Living Legends Phase 41323 · Wadi Al Safa 3 · Living Legends | Amer Alghurair Real Estate Development CO. L.L.C | Under construction | 62.1% | Mar 2027 4 mo to go | — | 114 |
| Samana Barari Views 22841 · Wadi Al Safa 3 · Majan | Samana International Real Estate Development L.L.C | Under construction | 19.7% | — | — | 107 |
| Tulip Oasis 113538 · Wadi Al Safa 3 · Majan | A M E Real Estate Development L.L.C | Under construction | 93% | Jun 2026 4 mo past | 4 mo | 92 |
| Rijas Suites3433 · Wadi Al Safa 3 · Majan | Dusit Rijas Properties L.L.C | Under construction | 3.3% | Dec 2028 25 mo to go | — | 83 |
| High Best Tower3493 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | True Future Real Estate Development L.L.C | Under construction | 90.6% | Nov 2026 under 1 mo past | — | 80 |
| The Watercrest By Ellington3444 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Ellington Properties Development L.L.C | Under construction | 2.2% | Mar 2028 16 mo to go | — | 79 |
| Rome 3 by SD3459 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Samana Star Real Estate Development L.L.C | Under construction | 10.2% | Jun 2028 19 mo to go | — | 65 |
| Barari Palace4164 · Wadi Al Safa 3 · Majan | Ary & Maz Development L.L.C | Not started | 0% | Dec 2028 25 mo to go | — | 64 |
| The Haven III3876 · Wadi Al Safa 3 · Majan | Meraki Real Estate Development L.L.C | Under construction | 6.2% | Dec 2027 13 mo to go | — | 54 |
| The Cube Quarter Residences3279 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Amwaj Alkhaleej Real Estate Development L.L.C | Under construction | 57% | Dec 2026 1 mo to go | — | 51 |
| Knightsbridge Park3361 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Leos Sof Real Estate Development L.L.C | Under construction | 10.8% | Nov 2027 12 mo to go | — | 50 |
| Woodland Terraces3457 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | A M I S Real Estate Development L.L.C | Under construction | 10.3% | Mar 2027 4 mo to go | — | 50 |
| Living Legends Phase 71326 · Wadi Al Safa 3 · Living Legends | Tanmiyat Global Real Estate Development L L C | Under construction | 91.9% | Sep 2021 61 mo past | 61 mo | 44 |
| Art House Private Residences By Viva4275 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Viva Real Estate Development L.L.C | Not started | 0% | Feb 2028 15 mo to go | — | 42 |
| Rome 2 by SD3329 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Samana Star Real Estate Development L.L.C | Under construction | 32.9% | Jun 2027 7 mo to go | — | 40 |
| Rome by SD3218 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Samana Star Real Estate Development L.L.C | Under construction | 38.7% | Dec 2027 13 mo to go | — | 33 |
| Barari Parks By Bahat4302 · Wadi Al Safa 3 · Majan | Bahat Real Estate Development L.L.C | Under construction | 0.9% | Mar 2028 16 mo to go | — | 31 |
| Karl Lagerfeld Villas By Taraf2982 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Taraf Development L.L.C | Under construction | 10.5% | — | — | 29 |
| Numa Reserve3786 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Mirfa Serenity Real Estate Development L.L.C | Under construction | 10.3% | Dec 2026 1 mo to go | — | 27 |
| Lua Residences2974 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Swank Real Estate Development L.L.C | Under construction | 64.4% | Mar 2026 7 mo past | 7 mo | 25 |
| Knightsbridge Park 23491 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Leos Sof Real Estate Development L.L.C | Not started | 0% | Nov 2027 12 mo to go | — | 21 |
| The Willows Residences3571 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Scc Vertex Property L.L.C | Under construction | 0.7% | Jun 2027 7 mo to go | — | 19 |
| Wadi Villas by Arista2967 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Pbg Real Estate Development L.L.C | Under construction | 60.4% | Dec 2026 1 mo to go | — | 18 |
| Wellington Grand Villas3518 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Mbr Mansions Real Estate Development L.L.C | Under construction | 62.1% | Jan 2028 14 mo to go | — | 18 |
| Selora Residences3573 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Swank Real Estate Development L.L.C | Under construction | 3.5% | Apr 2027 5 mo to go | — | 18 |
| Derby Heights4131 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | A M I S Signature Development L.L.C | Under construction | 10.1% | Oct 2027 11 mo to go | — | 14 |
| Mira Villas designed by Bentley Home3128 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | M I R A Developments L.L.C | Under construction | 31.8% | Dec 2026 1 mo to go | — | 13 |
| Blossom 404205 · Wadi Al Safa 3 · Majan | Tranquil Infra Developers L.L.C | Not started | 0% | Mar 2028 16 mo to go | — | 13 |
| Wadi 6452999 · Wadi Al Safa 3 · Majan | Greenside Development L.L.C | Under construction | 55.2% | — | — | 12 |
| Estrella By Nexus3284 · Wadi Al Safa 3 · Majan | Nexus Capital Real Estate Developement L.L.C | Under construction | 45.5% | May 2026 5 mo past | 5 mo | 11 |
| The Lakeview Villas By Ellington2816 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Ellington Properties Development L.L.C | Under construction | 20.1% | Aug 2026 2 mo past | 2 mo | 10 |
| Symphony by Chaimaa3592 · Wadi Al Safa 3 · Majan | Deval Real Estate Development L.L.C | Not started | 0% | Aug 2027 9 mo to go | — | 10 |
| Nineteen Riviera Lagoon2980 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Riviera Properties Development | Under construction | 34.1% | Feb 2027 3 mo to go | — | 9 |
| Sherena Residence 22101 · Wadi Al Safa 3 · Majan | Rose Homes Investment (L.L.C) | Under construction | 82% | Aug 2022 50 mo past | 50 mo | 8 |
| The Lakeshore Villas By Ellington2918 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Ellington Properties Development L.L.C | Under construction | 1.4% | — | — | 6 |
| The Collection by NASER3282 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | N A S E R Real Estate Development L.L.C | Under construction | 0.6% | Jun 2027 7 mo to go | — | 6 |
| The Beachfront Villas By Ellington2894 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Ellington Properties Development L.L.C | Under construction | 47.4% | Aug 2026 2 mo past | 2 mo | 5 |
| Forum 23807 · Wadi Al Safa 3 · Majan | K X G Real Estate Development L.L.C | Under construction | 7% | Dec 2027 13 mo to go | — | 4 |
| Bottega Nove by Lalav4324 · Wadi Al Safa 3 · Majan | Bottega Nove By Lalav Real Estate Development L.L.C | Under construction | 30% | Jul 2027 8 mo to go | — | 4 |
| The Waterside Villas By Ellington2716 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Ellington Properties Development L.L.C | Under construction | 45% | Jun 2026 4 mo past | 4 mo | 3 |
| The Woodland Residences2854 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | A M I S Real Estate Development L.L.C | Under construction | 75.4% | Apr 2026 6 mo past | 6 mo | 2 |
| Samana Business Park 24110 · Wadi Al Safa 3 · Majan | Samana Signature Real Estate Developments L.L.C | Under construction | 3% | Oct 2028 23 mo to go | — | 2 |
| Amis & GPD Presents Fleur De Jardin Villas4389 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Amis Gpd Developer L.L.C | Under construction | 0.6% | Oct 2028 23 mo to go | — | 2 |
| Barari Parkview by Al Mawared2971 · Wadi Al Safa 3 · Majan | Almawared Properties L.L.C | Under construction | 44.7% | Dec 2027 13 mo to go | — | 1 |
| Samana Business Park3812 · Wadi Al Safa 3 · Majan | Samana Signature Real Estate Developments L.L.C | Under construction | 12.8% | Sep 2028 22 mo to go | — | 1 |
| Noore4252 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Eight Square Developers L.L.C | Under construction | 15.9% | Jun 2027 7 mo to go | — | 1 |
| The Vault By Imtiaz4576 · Wadi Al Safa 3 · Majan | Imtiaz Vault Real Estate Development L.L.C | Not started | 0% | Jun 2029 31 mo to go | — | 1 |
| The Nest Revolution Villa2218 · Wadi Al Safa 3 · Al Barari | Abwab Real Estate Limited CO (L.L.C) | Pending | 5% | — | — | 0 |
| Project 2766, Wadi Al Safa 32766 · Wadi Al Safa 3 | Al Barari Ixora Real Estate L.L.C | Pending | 2.2% | — | — | 0 |
| Opulence Residences by Sido Development3368 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Sido Development L.L.C | Pending | 0% | Apr 2027 5 mo to go | — | 0 |
| Project 3569, Wadi Al Safa 33569 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Mag W5 Property Development L.L.C | Pending | 0% | Jul 2028 20 mo to go | — | 0 |
| Mangrove 23597 · Wadi Al Safa 3 · Majan | Mangrove Real Estate Development L.L.C | Under construction | 37.8% | Sep 2026 1 mo past | 1 mo | 0 |
| Project 3652, Wadi Al Safa 33652 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Aizn Real Estate Development L.L.C | Pending | 0% | Apr 2028 17 mo to go | — | 0 |
| White Opals3676 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Aizn Real Estate Development L.L.C | Under construction | 1.1% | Sep 2028 22 mo to go | — | 0 |
| Project 3742, Wadi Al Safa 33742 · Wadi Al Safa 3 · Majan | Centurion Star Developers L.L.C | Pending | 0% | May 2027 6 mo to go | — | 0 |
| Samana Barari Avenue3829 · Wadi Al Safa 3 · Majan | Samana Signature Real Estate Developments L.L.C | Under construction | 6% | Oct 2028 23 mo to go | — | 0 |
| Project 3863, Wadi Al Safa 33863 · Wadi Al Safa 3 · Majan | Noor Primo Real Estate Development L.L.C | Pending | 0% | Sep 2027 10 mo to go | — | 0 |
| Taormina Village 24121 · Wadi Al Safa 3 | M H L REAL ESTATE DEVELOPMENT (Br of MILLENNIUM HOLDING LIMITED ) - DUBAI BRANCH | Not started | 0% | Jul 2029 32 mo to go | — | 0 |
| Koyo Residence by Fuji Properties4169 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Fuji Properties L.L.C | Under construction | 30.7% | Sep 2026 1 mo past | 1 mo | 0 |
| Renascent Tower4173 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | S A M A R A Real Estate Development L.L.C | Under construction | 1.9% | Mar 2028 16 mo to go | — | 0 |
| Tulip Oasis 11 Tower 24358 · Wadi Al Safa 3 · Majan | A M E Real Estate Development L.L.C | Pending | 0% | Dec 2029 37 mo to go | — | 0 |
| Project 4361, Wadi Al Safa 34361 · Wadi Al Safa 3 · Majan | Sky Harbor Real Estate Development L.L.C S.O.C | Pending | 13.9% | Jun 2027 7 mo to go | — | 0 |
| Nejm 14400 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Danf Developments L.L.C | Not started | 0% | Jun 2027 7 mo to go | — | 0 |
| Binghatti Square 14405 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Binghatti Developers FZE | Pending | 0% | Jun 2027 7 mo to go | — | 0 |
| Binghatti Square 24408 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Binghatti Developers FZE | Pending | 0% | Jun 2027 7 mo to go | — | 0 |
| Binghatti Square 34409 · Wadi Al Safa 3 · Mohammed Bin Rashid AL Maktoum District 11 | Binghatti Developers FZE | Pending | 0% | Jun 2027 7 mo to go | — | 0 |
| Project 4420, Wadi Al Safa 34420 · Wadi Al Safa 3 · Majan | Shriya Properties Development L.L.C S.O.C | Pending | 0% | Apr 2028 17 mo to go | — | 0 |
| Vista Hub by DSI Prestige One4458 · Wadi Al Safa 3 · Majan | Drake And Scull Real Estate Development L.L.C | Pending | 0% | May 2028 18 mo to go | — | 0 |
| Project 4571, Wadi Al Safa 34571 · Wadi Al Safa 3 · Majan | Samana Prime Real Estate Developments L.L.C | Pending | 0% | Dec 2029 37 mo to go | — | 0 |
| Project 4572, Wadi Al Safa 34572 · Wadi Al Safa 3 · Majan | Samana Signature Real Estate Developments L.L.C | Pending | 0% | Sep 2030 46 mo to go | — | 0 |
| Project 4603, Wadi Al Safa 34603 · Wadi Al Safa 3 · Majan | Zoya One Real Estate Developments L.L.C | Pending | 0% | Nov 2028 24 mo to go | — | 0 |
Source: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026.
Units not yet completed, by DLD end year
95 phases| DLD end year | Projects | Units |
|---|---|---|
| 2021 | 1 | 343 |
| 2022 | 1 | 120 |
| 2025 | 1 | 920 |
| 2026 | 17 | 1,786 |
| 2027 | 33 | 9,146 |
| 2028 | 26 | 4,449 |
| 2029 | 7 | 531 |
| 2030 | 3 | 2,222 |
| No end date | 6 | 828 |
Units · phases. “None”: no DLD end date registered yet. Source: DLD projects register, export of 1 November 2026.
More on Wadi Al Safa 3
Own a unit in one of these projects? Track it free
Area prices
2022-Q1 – 2026-Q4Median AED/sqft of off-plan sales of apartments by quarter in DLD area Wadi Al Safa 3, where most of the community’s projects are registered.
| Quarter | DLD area Wadi Al Safa 3 |
|---|---|
| 2022-Q1 | 1,031 |
| 2022-Q2 | 886 |
| 2022-Q3 | 786 |
| 2022-Q4 | — |
| 2023-Q1 | 739 |
| 2023-Q2 | 799 |
| 2023-Q3 | 899 |
| 2023-Q4 | 1,050 |
| 2024-Q1 | 1,454 |
| 2024-Q2 | 1,429 |
| 2024-Q3 | 1,363 |
| 2024-Q4 | 1,440 |
| 2025-Q1 | 1,523 |
| 2025-Q2 | 1,357 |
| 2025-Q3 | 1,466 |
| 2025-Q4 | 1,823 |
| 2026-Q1 | 1,826 |
| 2026-Q2 | 1,437 |
| 2026-Q3 | 1,432 |
| 2026-Q4 | 1,452 |
DLD area Wadi Al Safa 3, median AED/sqft of off-plan sales of apartments by quarter. A quarter with fewer than 5 sales is left as a gap. The last quarter runs to 5 November 2026.
Source: Dubai Land Department transactions, on Dubai Data.
Rents in DLD area Wadi Al Safa 3
New Ejari rent contracts for apartments across DLD area Wadi Al Safa 3, 12 months to 5 November 2026, against the 12 months before: the rent level around this project. No yield is shown before the project is completed.
| Bedrooms | Median annual rent | New contracts | Change on a year earlier |
|---|---|---|---|
| Studio | AED 43,600 | 447 | +1.4% |
| 1 BR | AED 65,000 | 859 | 0% |
| 2 BR | AED 90,000 | 547 | 0% |
| 3 BR | AED 130,000 | 67 | +4% |
New single-unit contracts only; renewals and contracts over several units are left out. A bedroom count shows from 5 contracts, a change needs 5 in both years and a yield 10 ready sales.
Source: Dubai Land Department open data (Ejari rent contracts and registered sales), under the Dubai Data Open Data Licence.
Service charges
What owners pay a year in completed buildings of the master communities here, from their owners’ association budgets: one figure per master community, the one with the most projects first.
Median AED per sq ft a year of residential owners’ association budgets, each development counted once, in the newest budget year with at least 10 developments. Plots, shared areas and hotel rooms are left out. A budget is not any one owner’s bill.
Source: Dubai Land Department, owners’ association budgets (service charges).
Registered sales in DLD area Wadi Al Safa 3
The newest home sales DLD has registered in DLD area Wadi Al Safa 3, as DLD publishes them, with the project where DLD names one.
| Date | Project | Market | Type | Size (sqft) | Price (AED) | AED/sqft |
|---|---|---|---|---|---|---|
| 5 November 2026 | — | ready | Villa | 16,400 | 41,000,000 | 2,500 |
| 5 November 2026 | The Fields At D11 - Mbrmc | ready | Villa · 4 BR | 3,096 | 3,800,000 | 1,227 |
| 5 November 2026 | The Fields At D11 - Mbrmc | ready | Villa · 4 BR | 2,015 | 3,400,000 | 1,687 |
| 5 November 2026 | Binghatti Skyflame 2 | off-plan | Apartment · 2 BR | 2,234 | 2,410,000 | 1,079 |
| 5 November 2026 | Living Legends Phase 4 | ready | Apartment · 2 BR | 1,431 | 1,550,000 | 1,083 |
| 5 November 2026 | Paradise View 1 | ready | Apartment · 2 BR | 1,132 | 1,200,000 | 1,060 |
| 5 November 2026 | Divine Al Barari | off-plan | Apartment · 1 BR | 1,020 | 1,180,800 | 1,158 |
| 5 November 2026 | — | ready | Apartment · 1 BR | 856 | 1,121,712 | 1,310 |
| 5 November 2026 | Binghatti Skyflame 1 | off-plan | Apartment · 1 BR | 723 | 1,050,000 | 1,452 |
| 5 November 2026 | Binghatti Skyflame 1 | off-plan | Apartment · 1 BR | 680 | 1,050,000 | 1,544 |
The newest 10 of 7,857 registered sales in the 12 months to 5 November 2026
Each sale as DLD registers it. Off-plan registrations include developer sales and resales, which DLD open data does not tell apart. DLD publishes no buyer or seller names. Shown on this page only, not as a download.
Source: Dubai Land Department open data, published on Dubai Data under the Dubai Data Open Data Licence. DLD Transactions dataset · Licence
Places inside the community
Places inside the Dubai Municipality outline of the community, by kind.
Metro and tram stations: Roads and Transport Authority (RTA) via Dubai Data. Other places: © OpenStreetMap contributors.
Data: DLD projects register, export of 1 November 2026; DLD sales register to 5 November 2026; Dubai Municipality community outlines. Methodology